This document provides a weekly summary of accomplishment for the MB Versoza Power System project to construct a feeder line for the CPC Housing Dormitory in Brgy. San Rafael, Calaca, Batangas. As of this week, excavation, sand and gravel fill/base works, reinforcing bar works, concrete encasement, and backfilling are 100% complete. Piping installation is 4.49% complete, with 668 meters installed so far. Cable pulling and transformer installation have not begun yet. The total work accomplished so far is 24.96% with a remaining balance of 75.03%.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
48 views
MB Versoza Power System
This document provides a weekly summary of accomplishment for the MB Versoza Power System project to construct a feeder line for the CPC Housing Dormitory in Brgy. San Rafael, Calaca, Batangas. As of this week, excavation, sand and gravel fill/base works, reinforcing bar works, concrete encasement, and backfilling are 100% complete. Piping installation is 4.49% complete, with 668 meters installed so far. Cable pulling and transformer installation have not begun yet. The total work accomplished so far is 24.96% with a remaining balance of 75.03%.