MB Versoza Power System

This document provides a weekly summary of accomplishment for the MB Versoza Power System project to construct a feeder line for the CPC Housing Dormitory in Brgy. San Rafael, Calaca, Batangas. As of this week, excavation, sand and gravel fill/base works, reinforcing bar works, concrete encasement, and backfilling are 100% complete. Piping installation is 4.49% complete, with 668 meters installed so far. Cable pulling and transformer installation have not begun yet. The total work accomplished so far is 24.96% with a remaining balance of 75.03%.

Uploaded by

Mark Dizon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views

MB Versoza Power System

This document provides a weekly summary of accomplishment for the MB Versoza Power System project to construct a feeder line for the CPC Housing Dormitory in Brgy. San Rafael, Calaca, Batangas. As of this week, excavation, sand and gravel fill/base works, reinforcing bar works, concrete encasement, and backfilling are 100% complete. Piping installation is 4.49% complete, with 668 meters installed so far. Cable pulling and transformer installation have not begun yet. The total work accomplished so far is 24.96% with a remaining balance of 75.03%.

Uploaded by

Mark Dizon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

MB VERSOZA POWER SYSTEM

PROJECT: CPC HOUSING DORMITORY FEEDER LINE CONSTRUCTION


LOCATION: BRGY. SAN RAFAEL CALACA BATANGAS
SUBJECT:WEEKLY SUMMARY ACCOMPLISHMENT
Scope of Works wt% Previous This date Cummulative Balance qty unit
Excavation 2.50% 1.67% 0.82% 2.50% 0.00% 107.28 m3
Sand & Gravel fill/base 0.86% 0.67% 0.19% 0.86% 0.00% 32.00 m3
Reinforcing bar Works 10.28% 2.31% 7.97% 10.27% 0.00% 1,741.74 kgs
Concrete encasement 6.04% 2.54% 3.50% 6.04% 0.00% 34.20 m3
Backfilling 0.81% 0.40% 0.41% 0.81% 0.00% 31.91 m3
Piping Installation 4.49% 3.87% 0.62% 4.49% 0.00% 668.00 meter(s)
Cable pulling 33.85% 33.85% 1,566.00 meter(s)
Transformer Installation 37.71% 37.71% 2.00 unit(s)
Overhead Installation 3.47% 3.47% 2.00 set(s)
WEEKLY % ACCOMPLISHMENTS 100.00% 24.96% 75.03%

236.60 390.90 14.38


W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 TOTAL REMARKS
12.70 27.52 31.67 35.39 107.28 DONE
14.40 10.60 7.00 32.00
64.60 172.00 154.30 1,349.84 1,740.74
0.42 13.96 19.82 34.20
15.66 16.25 31.91
576.00 92.00 668.00
0.00
0.00
0.00

14.38
71.89 107.28

34.20 34.20 0.00