0% found this document useful (0 votes)
39 views1 page

Project Schedule

This document outlines the tasks, timelines, and progress for a project called CKD. It includes 8 total tasks: 1) Engineering, 2) Procurement, 3) Construction, and 4) Start Up. Construction has 4 sub-tasks - Civil/Concrete, Silo Installation, Mechanical Installation, and Electrical Installation. The project is currently 41% complete overall and is scheduled to finish by March 31st, 2021.

Uploaded by

rpazb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views1 page

Project Schedule

This document outlines the tasks, timelines, and progress for a project called CKD. It includes 8 total tasks: 1) Engineering, 2) Procurement, 3) Construction, and 4) Start Up. Construction has 4 sub-tasks - Civil/Concrete, Silo Installation, Mechanical Installation, and Electrical Installation. The project is currently 41% complete overall and is scheduled to finish by March 31st, 2021.

Uploaded by

rpazb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Task Name Start Finish % September November January March

Mode Complete 7/27 8/24 9/21 10/19 11/16 12/14 1/11 2/8 3/8
0 CKD Mon 8/10/20 Wed 3/31/21 41%
1 1 Engineering Mon 8/10/20 Fri 12/18/20 75%
2 2 Procurement Fri 8/28/20 Thu 1/21/21 50%
3 3 Construction Thu 12/10/20 Wed 3/17/21 2%
4 3.1 Civil /Concrete Thu 12/10/20 Thu 1/7/21 10%
5 3.2 Silo Installation Mon 12/21/20 Fri 1/1/21 0%
6 3.3 Mechanical Installation Mon 1/11/21 Wed 3/17/21 0%
7 3.4 Electrical Installation Tue 2/9/21 Mon 3/8/21 0%
8 4 Start Up Thu 3/18/21 Wed 3/31/21 0%

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CKD
Summary Manual Summary Rollup Progress
Date: Fri 11/27/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only Slippage

Inactive Milestone Finish-only

Page 1

You might also like