Task1 - PP Interim Payment
Task1 - PP Interim Payment
ASSIGNMENT 1
A - PARTICULARS OF CONTRACT
1
C – BUILDING WORKS
%OF
ITEM DESCRIPTION AMOUNT (RM)
WORKDONE
1 Piling 42,037.50 100
2 WBLFF 43,857.50 90
3 Frame 49,329.30 100
4 Upper Floor 23,751.50 100
5 Roof 129,971.40 100
6 Staircase 8,029.90 100
7 External Walls 11,931.70 100
8 Internal Walls & Partitions 15,724.55 100
9 Window 49,635.00 80
10 Door 18,288.00 80
11 Int. Wall Finishes 18,659.50 90
12 Int. Floor Finishes 5,906.00 90
13 Int. Ceiling Finishes 14,107.00 90
14 External Finishes 18,791.50 80
15 Fittings and Furnishings 6,220.00 70
16 Sanitary Fittings 24,894.00 70
17 BWIC with services 4,157.00 80
D – EXTERNAL WORKS
%OF
ITEM DESCRIPTION AMOUNT (RM)
WORKDONE
1 Earthworks 45,316.00 100
2 Soil Drainage 23,713.25 100
3 Surface Water Drainage 21,648.60 100
4 Road & Carparks 108,769.50 80
5 Water Reticulation 29,179.30 100
6 Street Lightings 10,300.00 50
%OF
ALLOWED ACCEPTED
ITEM DESCRIPTION WORKDONE
FIGURE (RM) FIGURE (RM)
1 Building Automation 200,000.00 185,900.00 90
System
Profit @ 2% 4,000.00
Attendance 4,000.00
b) PROVISIONAL SUM
ALLOWED
ITEM DESCRIPTION
AMOUNT (RM)
1 Landscaping Works 60,000.00
2 Signages 10,000.00
3 Contingencies 30,000.00
2
G - MATERIALS ON SITE
H – VARIATION ORDER
SUMMARY OF VARIATIONS
Building works.
Omission: RM 4,500.00
Addition: RM 6,500.00
Omission: RM 3,300.00
Addition: RM 2,000.00
Omission: RM 10,300.00
Addition: RM 15,000.00
Omission: RM 4,300.00
Addition: RM 6,000.00
J - PROVISIONAL SUM
The final contract figure for Provisional Sum undertaken by the main Contractor has been agreed
as follows :
ALLOWED
ITEM DESCRIPTION
AMOUNT (RM)
1 Landscaping Works 40,000.00
2 Signages 8,000.00
Note: - All variations on building works are completed prior to the site valuation.
- Deduction of Non-Compliance Report for poor alignment of brick wall to be included in this
payment – RM1,200.00
3
PAM
PROJECT :
MAIN CONTRACTOR :
ORIGINAL CONTRACT SUM : RM
Additions as per V.O. No. : RM
Omissions as per V.O. No : RM
Nett Additions/Omissions : RM RM
ADJUSTED CONTRACT SUM : RM
Ringgit
Malaysia : ………………………………………………………………………………………………………………………......
PREPARED BY :
Date : …………………….. ……………………………………………………
(QUANTITY SURVEYOR)
CERTIFIED BY :
Date : …………………….. ……………………………………………………
(ARCHITECT)
4
JKR66 (Latest Version)
TAJUK KERJA :
NO. KONTRAK :
HARGA ASAL KONTRAK : RM
JUMLAH BERSIH TAMBAHAN / POTONGAN : RM
HARGA BARU KONTRAK : RM
C. PERAKUAN BAYARAN
1. Kredit Akaun Deposit Wang Jaminan Pelaksanaan RM
(10% dari Bayaran Disyorkan sehingga 5% harga kontrak)
2. Bayaran Interim No.
a) Kepada Subkontraktor/Penerima Bayaran (Seperti di Lampiran A) RM
b) Kepada Kontraktor Utama RM
Jumlah Bayaran Interim RM RM
BAYARAN DIPERAKUKAN RM
Adalah disahkan bahawa semua peraturan kewangan dan kehendak di bawah kontrak telah dipenuhi.