Diversion Headworks: Module-III
Diversion Headworks: Module-III
Module-III
• Diversion Headworks:
• Types- selection of the suitable site for the
diversion headwork- components of diversion
headwork- Causes of failure of structure on
pervious foundation- Khosla’s theory- Design
of concrete sloping glacis weir
Diversion Head-Works
• The works which are constructed at the head
of the canal in order to divert the river water
toward the canal, so as to ensure a regulated
continuous supply mostly silt free water with
certain minimum head into the canal, are
known as diversion headworks.
Diversion Head-Works
Objectives of Diversion Head Works
• The Following are the objective of Diversion
Head works
• To Raise the water level at the head of canal.
• To form a storage by construction of dykes on
both side of banks of the river so that water is
available throughout the year.
• To control the entry of silt into the canal and to
control the deposition of silt at the head of canal.
• To control the fluctuation of water level in the
river during different seasons.
Objective of Diversion Head works
Objective of Diversion Head works
Objective of Diversion Head works
Objective of Diversion Head works
Selection of Site for Diversion Head
Works
• The following points should be considered to
select a site for this diversion headworks.
• The river should be straight and narrow at the
site
• The elevation of site should be higher than the
area to be irrigated for gravity flow.
• River banks at site should be well defined and
stable.
• Valuable land upstream of the barrier like
weir or barrage should not be submerged.
Selection of Site for Diversion Head
Works
• Material of construction should be locally
available.
• Roads or railway communication to the site is
essential to carry the material of construction.
• Site should be close to the cropland to
minimize loss of water due to seepage and
evaporation of canal.
• The site should provide a good foundation for
construction of weir or barrage.
Selection of Site for Diversion Head
Works
Components of Diversion Headworks
Components of Diversion Headworks
Components of Diversion Headworks
• The components of diversion headworks are:
• Weir or barrage
• Canal head regulator
• Divide Wall
• Fish Ladder
• Scouring Sluices Under sluices
• Silt excluder
• Silt ejector.
• Marginal embankment or dikes
• Guide bank
• Silt pocket or trap.
Weir or Barrage
• Weir is a solid obstruction placed across the
river. Its main function is to raise the water
level so that water can be diverted by canal to
crop field due to difference of head.
• Barrage is practically a low weir with an
adjustable gate over this low weir. Heading up
of water is affected by gate.
Weir
Weir
Weir
Barrage
Barrage
Barrage
Comparison Between Weir & a
Barrage
Types of Weir
Types of Weir
• Weir may be of different types based on material of
construction, design features and types of soil
foundation as:
• Vertical Drop Weir
• A crest gate may be provided to store more water
during flood period. At the upstream and downstream
ends of impervious floor cut off piles are provided.
Launching apron are provided both at upstream and
downstream ends of floor to safeguard against
scouring action. A graded filter is provided
immediately at the downstream end of impervious
floor to relieve the uplift pressure. This type of weir is
suitable for any type of foundation.
Vertical Drop Weir
Vertical Drop Weir
Vertical Drop Weir
Types of Weir
• Sloping Weir of Concrete:
• This type is suitable for soft sandy foundation.
It is used where difference in weir crest and
downstream riverbed is not more than 3 m.
Hydraulic jump is formed when water passes
over the sloping glacis. Weir of this type is of
recent origin.
Sloping Weir of Concrete
Sloping Weir of Concrete
Types of Weir
• Parabolic Weir:
• A parabolic weir is almost similar to spillway
section of dam. The weir body wall for this
weir is designed as low dam. A cistern is
provided at downstream.
Types of Weir
Types of Weir
• Dry Stone Slopping Weir:
• It is dry stone or rock fill weir. It consists of
body wall and upstream and downstream dry
stones are laid in the form of glacis with some
intervening core wall.
Dry Stone Slopping Weir
Dry Stone Slopping Weir
Barrage
• When the water level on the upstream side of
the weir is required to be raised to different
levels at different time, then the barrage is
constructed. Practically a barrage is an
arrangement of adjustable gates or shutters at
different tiers over the weir. The water level
can be adjusted by the opening of gates.
Barrage
Divide Wall
• The Divide Wall is a long wall constructed at right angle to the
weir or barrage, it may be constructed with stone masonry or
cement concrete. On the upstream side, the wall is extended
just to cover the canal regulator and on the down stream side,
it is extended up to the launching apron. The functions of the
divide wall are as follows,
• (a) To form a still water pocket in front of the canal head so
that the suspended silt can be settled down which then later
can be cleared through the scouring sluices from time to time.
• (b) It controls the eddy current or cross current in front of the
canal head.
• (c) It provides a straight approach in front of the canal head.
• (d) It resists the overturning effect on the weir or barrage
caused by the pressure of the impounding water.
Divide Wall
Scouring Sluices or Under Sluices
• The Scouring sluices are the openings provided
at the base of the weir or barrage. These
openings are provided with adjustable gates.
Normally, the gates are kept closed. The
suspended silt goes on the depositing in front of
the canal head regulator. When the silt
deposition becomes appreciable the gates are
opened and the deposited silt is loosened with an
agitator mounting on a boat. The muddy water
flows towards the downstream side through the
scouring sluices. The gates are closed. But, at the
period of flood, the gates are kept opened.
Under Sluices
Scouring Sluices or Under Sluices
Fish Ladder
• The Fish Ladder is provided just by the side of the
divide wall for the movement of fishes. Rivers are
important source of fishes. There are various types of
fish in the river. The nature of fish varies from type
to type. But in general, the tendency of fish is to
move from upstream to downstream in winters and
from downstream to upstream in monsoons. This
movement is essential for their survival.
Fish Ladder
• Due to construction of weir or barrage, this
movement gets obstructed, and is detrimental to
the fishes. For the movement of the fishes along
the course of the river, the fish ladder is essential.
In the fish ladder, the baffle walls are
constructed in the zigzag manner so that the
velocities of flow within the ladder does not
exceed 3 m/s. The width, length, and height of
the fish ladder depends on the nature of the river
and the type of the weir or barrage.
Fish Ladder
Fish Ladder
Canal Head Regulator
• A structure which is constructed at the head of
the canal regulator to regulate the flow of water
is known as canal head regulator. It consists of a
number of piers which divide the total width of
the canal into a number of spans which are
known as bays. The pier consists of a number of
tiers on which the adjustable gates are placed.
The gates are operated from the top by suitable
mechanical device. A platform is produced on
the top of the piers for the facility of operating
the gates. Again some piers are constructed on
the downstream side of the canal head to support
the roadway.
Canal Head Regulator
Canal Head Regulator
Silt Excluder
• When still pocket is formed in front of the canal
head by constructing the divide wall, then it is found
that the lower layer of water contains heavy silt and
the upper layer contains very fine silt. The fine silt is
very fertile and it may be allowed to enter the canal.
But the heavy silt causes sedimentation in the
pocket.. To eliminate the suspended heavy silt, the
silt excluder is provided. It consists of a series of
tunnels starting from the side of the head regulator
up to the divide wall.
Silt Excluder
• The tunnel nearest to the head regulator is
longest, and the successive tunnels decrease in
length, the tunnel nearest to the divide wall is
shortest. The tunnels are covered by R.C.C. Slab.
The top level of the slab is kept below the sill
level of the head regulator. So, the completely
clear water is allowed to flow in the canal
through the head regulator. The suspended
heavy silt carried by the water enters the silt
excluder tunnels and passes out through the
scouring sluices.
Silt Excluder
• Silt excluders are those works which are
constructed on the bed of the river, upstream
of the head regulator. The clearer water
enters the head regulator and silted water
enters the silt excluder. In this type of
works, the silt is, therefore, removed from the
water before in enters the canal.
Silt Excluder
Silt Ejectors
• Silt ejectors, also called silt extractors, are
those devices which extract the silt from
the canal water after the silted water has
• traveled a certain distance in the off-take
canal. These works are, therefore, constructed
on the bed of the canal, and little distance
downstream from the head regulator.
Silt Ejectors
Marginal Embankments or dykes
• The marginal embankments or dykes are earthen
embankments which are constructed parallel to the
river bank on one or both the banks according to the
condition. The top width is generally 3 to 4 m and side
slope is generally 1 ½ : 1 to 2: 1. The height of the
embankment depends on the highest flood level. A
suitable margin is provided between the toe of the
embankment and the bank of the river. To resist the
effect of erosion on the embankment, wooden piles are
driven along the river banks throughout the length of
dyke. The length of the dyke is protected by boulders
pitching with cement grouting and the downstream
side is protected by turfing.
Marginal Embankments or dykes
• The Marginal Bunds are constructed for the
following purposes.
• (a) It prevents the flood water or storage
water from entering the surrounding area.
• (b) It retains the flood water or storage water
within a specified section.
• (c) It Protects the towns and village from
devastation during the heavy flood.
• (d) It protects valuable agricultural lands.
Marginal Embankments
Guide Bank
• When a barrage is constructed across a river which
flows through the alluvial soil, the guide banks must
be constructed on both the approaches to protect the
structure from erosion. It is an earthen embankment
with curved head on both the ends.
• The Guide Bank serves the following purposes.
• It protects the barrage from the effect of scouring and
erosion.
• It controls the tendency of changing the course of the
river.
• It controls the velocity of the flow near the structure.
Guide Bank
Guide Bank
Guide Bank
• Components of Guide Banks are
• Upstream curved head
• Downstream curved head
• Shank portion which joins upstream and
downstream curved end
• Sloping apron
• Launching apron
• Pile protection
Guide Bank
Causes of Failure of weir or barrage
on permeable foundation
• The combined effect of surface flow and surface flow may
cause the failure of the weir or barrage.
• (i) Failure due to subsurface flow
• (a) By piping or undermining: The water from the
upstream side continuously percolates through the bottom
of the foundation and emerges at the downstream end of
the weir or barrage floor. The force of percolating water
removes the soil particles by scouring at the point of
emergence. As the process of removal of soil particles goes
on continuously, a depression is formed which extends
backwards towards the upstream through the bottom of
the foundation. A hollow pipe like formation thus develops
under the foundation due to which the weir or barrage
may fail by subsiding. This phenomenon is known as
failure by piping or undermining.
By Piping or Undermining
By Piping or Undermining
Causes of Failure of weir or barrage
on permeable foundation
• (b) By uplift Pressure: The percolating water exerts an upward pressure
on the foundation of the weir or barrage. If this uplift is not
counterbalanced by the self weight of the structure, it may fail by
rapture.
• 2. Failure by Surface Flow:
• (a) By Hydraulic Jump: When the water flows with a very high velocity
over the crust of the weir or over the gates of the barrage, then
hydraulic jump develops. This hydraulic jump causes a suction
pressure or negative pressure on the downstream side which acts in
the direction of uplift pressure. If the thickness of the impervious floor
is not sufficient, then the structure fails by rapture.
• (b) By Scouring During floods: The gates of the barrage are kept open
and the water flows with high velocity. The water may also flow with
very high velocity over the crest of the weir. Both the cases can result
in scouring effect on the downstream and on the upstream side of the
structure. Due to scouring effect on the downstream and on the
upstream side of the structure, its stability gets endangered by shearing.
By Uplift Pressure
By Hydraulic Jump
By Scouring During floods
Causes of Failure of Weir, and
Remedies
• If a weir is constructed on permeable soil, weir may fail
by piping, uplift force, suction caused by standing wave
and scouring on both upstream and downstream of the
weir.
• When hydraulic gradient or exit gradient exceeds the
critical value of soil, surface soil at down end starts
boiling first and is washed away by percolating water.
This process of removal or washing out of soil continuous
and eventually a channel in the form of pipe is formed by
seepage water. This is called piping which may cause the
failure of foundation. Similarly uplift force of percolating
water is acting on ther floor from bottom and if the
weight of floor is not enough to resist this uplift force,
floor may fail by cracking or bursting.
Causes of Failure of Weir, and
Remedies
• The main remedies against failure are:
• Path of percolation or creep length of seepage
water should be increased by providing sheet
piles at upstream, downstream or at
intermediate point to reduce the hydraulic
gradient.
• Floor thickness should be increased to
increase its self weight to balance the uplift
force.
Precautions Against Failure
• The following precautions can be taken to prevent
failure.
• (a) The length of the impervious layer should be
carefully designed so that the path of the percolating
water is increased consequently reducing the exit
gradient.
• (b) Sheet piles should be provided on the upstream
side and the downstream side of the impervious
floor to increase to the length of percolating water
so that the uplift pressure is considerable reduced.
• (c) The thickness of the impervious floor should be
such that the weight of the floor is a sufficient to
counterbalance the uplift pressure.
Precautions Against Failure
• (d) Energy dissipater blocks like friction
blocks, impact blocks, should be provided.
• (e) Inverted filter should be provided with
concrete blocks on the top so that the
percolating water does not wash out the soil
particles.
• Deep foundation like well foundation should
be provided for the barrage piers
Precautions Against Failure
Precautions Against Failure
Energy Dissipater Blocks
Increasing Floor
Thickness
Flow Net
• A flownet is a graphical representation of two-
dimensional steady-state groundwater flow
through aquifers.
• The method consists of filling the flow area with
stream lines and equipotential lines, which are
everywhere perpendicular to each other, making
a curvilinear grid.
• Stream Lines: The streamlines represent the paths
along which the water flows through the sub-soil.
• Equipotential lines: Equipotential lines are lines of
• equal hydraulic head.
Flow Net
Khosla’s Theory
• Khosla’s Theory and Concept of Flow Nets
• Many of the important hydraulic structures,
such as weirs and barrage, were designed on
the basis of Bligh’s theory between the periods
1910 to 1925. In 1926 – 27, the upper Chenab
canal siphons, designed on Bligh’s theory,
started posing undermining troubles.
Investigations started, which ultimately lead to
• Khosla’s theory. The main principles of this theory
are summarized below:
• (a) The seepage water does not creep along the
bottom contour of pucca flood as started by Bligh,
but on the other hand, this water moves along a set
of stream-lines. This steady seepage in a vertical
plane for a homogeneous soil can be expressed by
Laplacian equation:
Khosla’s Theory
• The equation represents two sets of curves
intersecting each other orthogonally. The resultant
flow diagram showing both of the curves is called a
Flow Net.
• Stream Lines: The streamlines represent the paths
along which the water flows through the sub-soil.
• Every particle entering the soil at a given point
upstream of the work, will trace out its own path and
will represent a streamline. The first streamline
follows the bottom contour of the works and is the
same as Bligh’s path of creep. The remaining
streamlines follows smooth curves transiting slowly
from the outline of the foundation to a semi-ellipse, as
shown below.
Khosla’s Theory
Where,
b′ = The distance between two pile lines.
D = The depth of the pile line, the influence of which has to be determined on
the neighboring pile of depth d. D is to be measured below the level at
which interference is desired.
d = The depth of the pile on which the effect is considered
b = Total floor length
The correction is positive for the points in the rear of back water, and
subtractive for the points forward in the direction of flow. This equation
does not apply to the effect of an outer pile on an intermediate pile, if the
intermediate pile is equal to or smaller than the outer pile and is at a
distance less than twice the length of the outer pile.
(a) Correction for the Mutual interference of
Piles
(a) Correction for the Mutual interference of
Piles
• Suppose in the above figure, we are considering the influence of
the pile no (2) on pile no (1) for correcting the pressure at C1.
Since the point C1 is in the rear, this correction shall be positive.
While the correction to be applied to E2 due to pile no (1)
shall be negative, since the point E2 is in the forward direction
of flow. Similarly, the correction at C2 due to pile no (3) is
positive and the correction at E2 due to pile no (2) is negative.
(b) Correction for the Thickness of Floor