A.s02 Traffic Accommodation Strategy Component Checklist

This document is a checklist for a traffic accommodation strategy with 27 items. It includes identifying the project details like contract number, scope of work and schedule. It also checks that signage plans, detours, drawings and safety procedures are identified for things like flagpersons, speed limits and accident reporting. The strategy must conform to the current manual for traffic accommodation in work zones and additional details may be needed depending on the specific project.

Uploaded by

Sami Aj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
161 views

A.s02 Traffic Accommodation Strategy Component Checklist

This document is a checklist for a traffic accommodation strategy with 27 items. It includes identifying the project details like contract number, scope of work and schedule. It also checks that signage plans, detours, drawings and safety procedures are identified for things like flagpersons, speed limits and accident reporting. The strategy must conform to the current manual for traffic accommodation in work zones and additional details may be needed depending on the specific project.

Uploaded by

Sami Aj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

TRAFFIC ACCOMMODATION STRATEGY

COMPONENT CHECK LIST


Contract #       YES NO N/A
1. Is Project Identified?
- contract number
- highway number
- project limits shown

2. Is the Project ‘Scope of Work’ Identified?

3. Is Contractor Identified?

4. Are Sub-Contractors Identified?


- contact names/phone numbers
- assorted tasks

5. Is Schedule Identified?
- date of commencement/completion
- milestone dates/interim stage of completion

6. Is the Process for Sign Installation/Covering/Removal Identified?


- two-lane highways
- four-lane highways

7. Will the Project be Pre-Signed?


- strategy for covering/monitoring signs

8. Are the Type of Sign Supports Identified?


- posts/portables/windmaster/etc…

9. Are the Sign Height Requirements Identified?


- long duration signs (1.5m)
- short duration signs (0.3m)

10. Are Responsibilities for TCS Identified?


- name(s) of on-site designate & contact numbers
- monitoring of TCD’s during inactive periods

11. Are Day/Night Procedures Established?

12. Is Accommodating Vehicles Around Tack Coat &


Non-Standard Lane Widths Identified?

13. Are Special User Issues Identified?


- over-dimensional loads, emergency vehicles, etc…

14. Are Non-Typical Conditions Identified?


- did contractor address items from S.P.’s?

15. Is Work Staging Identified?


- template for each stage
- no situations missing
CONT’D

Revised July 2016


AppendixA.s02
TRAFFIC ACCOMMODATION STRATEGY
COMPONENT CHECK LIST
Contract #       YES NO N/A

16. Are Detour(s) Identified?


- customized drawings

17. Are Drawings Submitted?


-all activities

18. Is Parking of Vehicles/Equipment Identified?


- during working hours
- during non-working hours

19. Have the Requirements for Flagpersons Been Identified?


- certifying agency
- protective clothing
- certificate readily available

20. Has the Procedure for Centreline Spotting Been Identified?


- strategy for the protection of workers

21. Speed Limits Identified?


- all activities
- non-active periods
- distinct phase breaks

22. Is the Use of Pilot Vehicles Identified?

23. Have the Requirements for the Daily Sign Log Been Identified?
- include timeline for submission of information to consultant

24. Has the Reporting of Accidents Been Identified?

25. Are the Haul Route(s) Identified?

26. Is the Process for Truck Turning Movements Within the


Work Area/Zone Identified?

27. Emergency Response Strategy?


- names/contact numbers
- arrangement with emergency responders

NOTES
Strategy must conform to TRANS Traffic Accommodation In Work Zones Manual (current edition).
Not an all-inclusive list. Additional information may have to be considered & provided on a
project-by-project basis.

REVIEWED BY
Name Title/Position Date
                 

Revised July 2016


AppendixA.s02