Analysis of Cost Control and Project Time in Performance Process With Earned Value Method, Case Study Improvement of Maliku-Bantanan Road in Pulang Pisau District, Indonesia
Analysis of Cost Control and Project Time in Performance Process With Earned Value Method, Case Study Improvement of Maliku-Bantanan Road in Pulang Pisau District, Indonesia
ISSN No:-2456-2165
Abstract:- A construction project is an activity that construction project has targets that must be fulfilled by a
requires a detailed calculation in its planning. It is not contractor in terms of quality, implementation time, and cost
only planning that needs attention, but construction [3,4].
projects have their complexities in terms of management.
The management of a construction project has targets II. REVIEW OF RESEACH
that must be fulfilled by a contractor in terms of quality,
implementation time, and cost. This study aimed at Construction is one of the important economic sectors
determining how the application of Earned Value in for a country which summarizes the implementation of
estimating the cost and project time. This study took a several activities that produce certain construction building
case study on the 8.505 m Maliku-Bantanan road products [5,6]. A construction project is said to be successful
improvement project located in Maliku and Sebangau if it fulfils six factors, such as the project runs on time,
Kuala sub-district, Pulang Pisau district, Central according to capital, achieves client satisfaction, the
Kalimantan province, Indonesia. This earned value satisfaction of the project manager and work team,
included budget and cost plans, unit price analysis, and according to its function, and according to the measure of
project progress reports processed to obtain BCWS success [7,8].A simple and general project is a series of
(Budgeted Cost of Work Scheduled), ACWP (Actual activities that are planned and carried out sequentially with
Cost of Work Performance), and BCWP (Budgeted Cost logic and using many types of resources, which are limited
of Work Performance)which affected the control of the by the dimensions of cost, quality, and time [9, 10,11].
implementation time and project costs. The results
showed that in the fifth month, the BCWP value was
IDR 13,668,602,892.99 and the BCWS value was IDR
13,513,565,248.85from the second calculation. The value
of BCWS was smaller than the value of BCWP, which
was 1.13% of the budget plan. The conditions indicated
that the implementation of activities in the field has been
following the planned schedule at a lower cost. These
results are expected to be used as a guide for contractors
and consultants in project planning that are more
effective and efficient as well as on quality, time, and
cost. Fig. 1.The Project Management Goal Triangle [9]
Keywords:- Earned Value (EV), Construction Project,
Costs that have been incurred and the time that has
BCWS, BCWP.
been used to complete a job must be further measured in
deviation from a plan. The existence of significant deviation
I. INTRODUCTION in cost and time is a sign of poor project management
[12,13]. The existence of performance indicators in terms of
The rapid development of the world of construction
cost and time can allow preventive action so that the project
services in Indonesia is marked by the number of very large-
can be carried out as planned. There is a dependency
scale projects built by the government, the private sector, or between the costs incurred on the time of project
a combination of both. However, in practice, a construction implementation, where optimal activity scheduling is needed
project has limited resources, either in the form of labour, so that the costs incurred are minimum [14, 15]. Project
equipment, methods, materials, or costs [1,2]. This
control is needed to maintain the suitability between
limitation required project management from the initial
planning and implementation. Project control is a
phase to the project completion phase. The management of a methodology to collect, create, analyze, and distribute
Cost (IDR)
Time
Table 2 shows the results of the analysis of the Earned total cost of the project as stated in the cost budget, while the
Value (EV) calculation in five months of project percentage of project completion was obtained from the
implementation. The budget used in the calculation was the project work performance report data.
100
90 86.07 87.06
80
67.3
70 62.36
60
50
40 36.4 37.82
30
20 11.25
7.59
10 1.46 1.48
0
1 2 3 4 5
Fig. 5.The Progress of Project Planning and Realization in Percentage
Figure 5 shows the project activities in five months. The length of time distribution of materials to the project site due
work plan has relatively fulfilled the realization target. In the to road damage and the impact of implementing health
second month, it has been delayed due to the influence of the protocols in preventing the spread of Covid-19.
16000000000.000
14000000000.000
12000000000.000
10000000000.000
8000000000.000
6000000000.000
4000000000.000
2000000000.000
-
1 2 3 4 5
Figure 6 shows the progress of the project activity costs were less than the planning costs, resulting in savings.
according to the results of the analysis of BCWS, BCWP, and This saving value was IDR 155,037,644.14 or 1.13% saving
ACWP. In the second month, the value of BCWP has from the contract value. This was also indicated by the low
decreased against the BCWS which indicated that the project value of ACWP against BCWP with a value selection of IDR
condition was delayed from the planned time. At the end of 5,601,980,130.38. This condition had a positive impact on
the project in the fifth month, the value of BCWP was cost and time efficiency during construction activities.
slightly higher than BCWP, which meant that the project
CPI SPI
5.18
2.68
1.62
1.29 1.29
1.01 1.04 1.08 1.01
0.67
1 2 3 4 5
Fig. 7.a. Analysis Cost and Schedule Variance b. CPI and SPI Analysis
Figure 7a shows the value of the cost variance (CV) and happened when the project was at the peak of its main work,
schedule variance (SV) which has a fairly varied level of where the cost requirements were higher. Figure 7b shows the
project values achievement. In the second month, the value of Cost Performance Index (CPI) and Schedule Performance
CV showed an increase in the use of costs, while SV has Index(SPI) values that occurred during project
decreased. This condition occurred because the level of cost implementation. Most of the CPI and SPI values had more
consumption was fixed but the project schedule was delayed. than 1.This indicated that the work performance was not
This delay could be caused by several factors such as material wasteful and was as expected since it was able to achieve the
supply conditions which were hampered by weather, the work targets as planned. In the second month, there was an
project location, and other non-technical factors. In the fourth SPI value below 1 which indicated a delay and waste of
month, the CV value has increased significantly. This was project costs.
also followed by an increase in the SV value. Generally, this
Figure 8 shows the total cost estimate (BEAC) and 5.18. This showed that the performance was better than the
project scheduling (SEAC) that occurred based on conditions planning, in the sense that the cost was less than the budget,
in the field. The increase in the number of days used in the and reporting activities from field supervision were going
second month of 60 days from the initial planning schedule of well. Judging from the calculation of the Schedule
180 daysshowed a time waste for implementation and would Performance Index (SPI), the value was 1.01 which indicated
impact the future project activities. To overcome this, it was the project was following the planned target.
necessary to save time in the following month, so that the
time allocation could be as planned. Based on the cost The Budget Estimate at Completion (BEAC) value was
prediction (BEAC) in the fifth month, the calculation of the obtained as IDR. 8,423,151,042.14 showed the total
estimated total cost until the end of the project was IDR remaining cost of project completion at the time of reporting
8,423,151,042.14. This value meant that it was smaller than at the end of the project (cost savings). The Schedule
the total budget of IDR 15,700,000,000.00 (Include Tax). Estimate at Completion (SEAC) value obtained an estimated
Based on the prediction of the fifth schedule, the predicted time of 179 days;one day faster than the planning schedule
project completion time was 179 calendar days, one day (180 days). This showed that the project estimationwas
faster than the planning schedule, which was 180 calendar running according to the planned schedule.
days.
ACKNOWLEDGMENT
V. CONCLUSION
The authors show gratitude to the Department of Public
Based on the results of project data processing using the Works of Pulang Pisau district, Central Kalimantan, and
Earned Value method, it is known that project activities are Master Program of Civil Engineering, University of Lambung
generally following the plan. This study also found some Mangkurat, Indonesia.
delays in the progress of project implementation that occurred
in the second month. Conditions were caused by external REFERENCES
factors such as damaged road conditions that hindered the
material distribution, the project location, and the Covid-19 [1]. Abma,“Analisis Pengendalian Waktu Dengan Earned
pandemic prevention which required all workersto implement Value Pada Proyek Pembangunan Hotel Fave Kotabaru
health protocols. Yogyakarta (Analysis of Time Control with Earned
Value in the Construction Project of Fave Hotel
The calculation result showed that the value of the Kotabaru Yogyakarta)”. Civil Engineering Faculty,
Budget Cost for Work Scheduled (BCWS) at the end of the Indonesian Islamic University, Journal
project, namely in the fifth month was IDR. Teknisia,Vol.XXI, No.2, 2016.
13,513,565,248.85, budget Cost for Work Performance [2]. W.I. Ervianto, “Manajemen ProyekKonstruksi
(BCWP) was IDR. 13,668,602,892.99, and the Actual Cost (Construction Project Management)”, Edisi Revisi,
for Performance (ACWP) was IDR8,066,622,762.61. Andi Offset, Yogyakarta, 2005.
[3]. A. Husen, “Manajemen ProyekEdisi Revisi (Project
The calculation of Cost Variance (CV) and Schedule Management: Revised Edition)”, Yogyakarta:C.V
Variance (SV) showed positive numbers. This meant that the ANDI OFFSET, 2011.
cost to complete the project was less than the plan and the
work was carried out as planned. The result of the calculation
of the Cost Performance Index (CPI) in the fifth month was