KN Network Services - Job Diary Information Sheet: Products To Be Completed

This job diary provides information for a job located in Inverness, Scotland to complete cable installation works. The works include installing new cables in ducts and replacing non-pressurized cables. Notes indicate civil estimates are pending and that all necessary materials are available. The permit to dig/drill document outlines safety procedures and approvals required before commencing excavation work to install the new cables, including locating existing utilities and having an approved plan for the work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views

KN Network Services - Job Diary Information Sheet: Products To Be Completed

This job diary provides information for a job located in Inverness, Scotland to complete cable installation works. The works include installing new cables in ducts and replacing non-pressurized cables. Notes indicate civil estimates are pending and that all necessary materials are available. The permit to dig/drill document outlines safety procedures and approvals required before commencing excavation work to install the new cables, including locating existing utilities and having an approved plan for the work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

KN Network Services - Job Diary Information Sheet

Job Information
KN Reference : 1225355 Received Date 21/06/2018 04:09:49
Client Reference : IBUH6LUS RBD : 26/09/2018 23:59:00
NIMs Reference : 18933618 LRBD : 26/09/2018 23:59:00
VLAD :
Planner : SASI PARTHASARATHY
Job Category : H7 (BDUK Plan & Build)
Telephone : 01213117420
Date Fit for Purpose :
Main Program # : F274
f FFP date shown this is the date you need to complete your
Sub Program # : 5147 works by, as follow up activities are required also

Important Fluidity Information


GridRef 269654844130 Work Stream
Exchange IV ( INVERNESS MACDHUI )
Address : SO 7 CASTLEHILL COTTAGES CULLODEN ROAD INVERNESS MACDHUI,,,,,,IV2 5BA

Notes : Civil Estimates to follow. Please start this Job after completion of civil estimate of
this cab. In Stores all the items are available in KANABN list, so we have moved the
items to authorized list only
Project CU rearr/build E/O
Desc :
Road Type: - Waived
Notice Period : 0
Job Duration :
Earliest Start Date :
Latest Start Date :

Products to be Completed
Work Description: Units
Rate Description Plan DFE Cost Sales
N324 Cable in Duct Heavy 3.00 0.00 0.00 0.00
N326 Cable in Duct Light 3.00 0.00 0.00 0.00
N35E E0 Intervention Non Pressure to Non Pressure 1st 1 2.00 0.00 0.00 0.00
N478 Non-Pressurised Cable Length Renewal 2.00 0.00 0.00 0.00
KNUK FRM-HSE-0040
Version : 1.0 Permit to Dig / Drill
Author: Julie Saville
Date: 22/08/08

Permit to Dig / Drill

Project/Station BT CITY FIBRE LA Ref


Expiry
Start Date Date
To be completed by the ‘competent person’
Section 1 Application responsible for the works being undertaken.

Description of the works – circle Classification;

Dslam stand civils PCP stand civils Blockage(s)

Mole Plough Box Building Duct Work

Other: ____________________________________________________________

Estimate Number/Client Reference: _____________________________________

Yes No

Are current issue drawings showing location, type and status (eg live / dead)
Of all known services in the area of the dig/drill available?

Drawing reference number

Has a visual survey of the location of the dig/drill been carried out?

Is there an approved method statement in place, confirming the location of the dig/drill?

What is the method statement number

Is there an approved cable locating device available on site?

Is the cable location device calibrated?

What is the calibration date?

Are all operatives conversant with safe drilling/digging practices?

Is there competent supervision available for the works?

I hereby declare that the above precautions will be put into effect before the works commence.
Name......................................................... Signature................................................................

Date.......................................................... Time.......................................................................

Section 2 Issue Authorisation can only be completed by the


KN ‘Authorised Person.’
Yes No

Has a CAT scan been carried out?

Have all known services been marked up?

Details of trail holes required_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _

____________________________ _________________________

Details of precautions needed to execute the works (eg PPE, fencing, shoring)_ _ _ _ _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_____________________________________________________

I am satisfied that the precautions identified above are satisfactory for the works to be undertaken.

Work may proceed Work may not proceed

Additional Action Required.

Name......................................................... Signature................................................................

Date.......................................................... Time.......................................................................

Section 3 Clearance All permits must be cleared by the KN


‘Competent Person.’

I hereby confirm that the work to which this permit related is now complete. All persons and materials are
now clear. The site has been left in a safe condition (physical / visible edge protection, warning notices,
securely fixed marking cover.)

Name......................................................... Signature................................................................

Date.......................................................... Time.......................................................................

Section 4 Cancellation All permits must be cancelled by the KN


‘Competent Person.’

I am satisfied that the work has been left in a safe condition. The permit is hereby cancelled.

Name......................................................... Signature................................................................

Date.......................................................... Time.......................................................................