0% found this document useful (0 votes)
340 views11 pages

Inert Gas On Board Tankers - All You Need To Know!

This document provides information about inert gas systems on tankers. It discusses the sources and composition of inert gas, methods for replacing tank atmospheres through dilution or displacement, maintaining cargo tanks in a non-flammable condition, and inert gas system maintenance. Key points include that inert gas systems keep oxygen levels below 11% to prevent fires or explosions, sources include boiler flue gas or independent generators, and the gas typically contains 83% nitrogen and 12-14% carbon dioxide.

Uploaded by

Giorgi Kandelaki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
340 views11 pages

Inert Gas On Board Tankers - All You Need To Know!

This document provides information about inert gas systems on tankers. It discusses the sources and composition of inert gas, methods for replacing tank atmospheres through dilution or displacement, maintaining cargo tanks in a non-flammable condition, and inert gas system maintenance. Key points include that inert gas systems keep oxygen levels below 11% to prevent fires or explosions, sources include boiler flue gas or independent generators, and the gas typically contains 83% nitrogen and 12-14% carbon dioxide.

Uploaded by

Giorgi Kandelaki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 11

Inert Gas on board Tankers – All

you need to know!

General
Hydrocarbon gas normally encountered in petroleum tankers cannot burn in an
atmosphere containing less than approximately 11% oxygen by volume. One way to
provide protection against fire or explosion in the vapour space of cargo tanks is to keep
the oxygen level below that figure. This is usually achieved by using a fixed piping
arrangement to blow inert gas into each cargo tank in order to reduce the air content,
and oxygen content and render the tank atmosphere non-flammable.

Sources of Inert Gas


Possible sources of IG on tankers and combination carriers are:

1. Uptake gas from the ship’s main auxiliary boilers;


2. An independent IG Generator and
3. A gas turbine plant when equipped with an afterburner.

Composition and Quality of Inert Gas


The International Convention for the Safety of Life at Sea (SOLAS) as amended,
requires that IG systems be capable of delivering IG with an oxygen content of the IG
main not more than 5% by volume at any required rate of flow; and of maintaining a
positive pressure in the cargo tanks all times with an atmosphere having an oxygen
content of not more than 8% by volume except when it is necessary for the tank to be
gas free.

When using flue gas from a main or auxiliary boiler, an oxygen level of less than 5% can
generally be obtained, depending on the quality of combustion control and the load on
the boiler.
When an independent IG generator or a gas turbine plant with afterburner is fitted, the
oxygen content can be automatically controlled within finer limits, usually within the
range 1.5%-2.5% by volume.

Nitrogen N 83%

Carbon Dioxide CO2 12-14%

Oxygen O2 2-4%

Sulphur Dioxide SO2 50ppm

Carbon Monoxide CO Trace

Nitrogen Oxide NOx 200ppm

Water Vapour H2O Trace (High if not dried)

Ash and Soot (C) Traces

Density 1.044

In certain ports, the maximum oxygen content of IG in the cargo tanks may be set at 5%
to meet particular safety requirements, such as the operation of a vapour emission
control system. Where such a limitation is in place, the ship should be advised of the
requirements in the pre-arrival information exchange.

Efficient scrubbing of the gas is essential, particularly for the reduction of the sulphur
dioxide content. High levels of sulphur dioxide increase the acidic characteristic of the
IG, which is harmful to personnel, and may cause accelerated corrosion to the structure
of a ship.

The table provides an indication of the typical composition of inert gas generated
from boiler flue gas, expressed as a percentage by volume.
Read about..Inert gas asphyxiation

Methods of Replacing Tank Atmospheres


If the entire tank atmosphere could be replaced by an equal volume of inert gas, the
resulting tank atmosphere would have the same oxygen level as the incoming inert gas.
In practice, this is impossible to achieve and a volume of inert gas equal to several tank
volumes must be introduced into the tank before the desired result can be achieved.

The replacement of a tank atmosphere by inert gas can be achieved by either inerting
or purging. In each of this methods, one of two distinct processes, dilution or
displacement, will predominate.

Dilution takes place when the incoming inert gas mixes with the original tank
atmosphere to form a homogeneous mixture throughout the tank so that, as the process
continues, the concentration of the original gas decreases progressively. It is important
that the incoming inert gas has sufficient entry velocity to penetrate to the bottom of the
tank. To ensure this, a limit must be placed on the number of tanks that can be inerted
simultaneously. Where this limit is not clearly stipulated in the operations manual, only
one tank should be inerted or purged at a time when using the dilution method. Below is
a representation of Dilution method onboard.

Displacement depends on the fact that inert gas is slightly lighter than hydrocarbon gas so that,
while the inert gas enters at the top of the tank, the heavier hydrocarbon gas escapes from the
bottom through suitable piping. When using this method, it is important that the inert gas has a
very low velocity to enable a stable horizontal interface to be developed between the incoming
and escaping gas. However, in practice, some dilution inevitably takes place owing to the
turbulence caused by the inert gas flow. Displacement generally allows several tanks to be
inerted or purged simultaneously. Below is a representation of Displacement method achieved
onboard.
Whichever method is employed, and whether inerting or purging it is vital that oxygen or
gas measurements are taken at several heights and horizontal positions within the tank
to check the efficiency of the operation. A mixture of inert gas and petroleum gas, when
vented and mixed with air, can become flammable. The normal safety precautions are
taken when petroleum gas is vented from a tank, therefore, should not be relaxed.

*Read about Flammability Diagram

Inert Gas Operations


Tankers using the inert gas system should maintain their cargo tanks in a non-
flammable condition at all times. It follows that:

 Tanks should be kept in an inert condition at all times, except when it is


necessary for them to be gas free for inspection or work. The oxygen content
should not be more than 8% by volume and the atmosphere should be maintained
at a positive pressure.
 The atmosphere within the tank should make the transition from the inert
condition to the gas-free condition without passing through the flammable
condition. In practice, this means that, before any tank is gas freed, it should be
purged with inert gas until the hydrocarbon content of the tank atmosphere is
below the critical dilution line. Check Flammability Diagram (Line GA)
 When a ship is in a gas-free condition before arrival at a loading port, the tanks
must be inerted prior to loading.

In order to maintain cargo tanks in a non-flammable condition, the inert gas plant will be
required to:

 Inert empty cargo tanks


 Be in operation, or be ready for immediate operation, during cargo discharge,
deballasting, COW and tank cleaning
 Purge tanks prior to gas freeing
 Top up the pressure in the cargo tanks when necessary during other stages of
the voyage
It must be emphasised that the protection provided by an inert gas system depends on
the proper operation and maintenance of the entire system.

Inert Gas System Maintenance


There should be close co-operation between the deck and engine departments to
ensure proper maintenance and operation of the inert gas system. It is particularly
important to ensure that non-return barriers function correctly, especially the deck water
seal or block and bleed valves so that there is no possibility of petroleum gas or liquid
petroleum passing back to the machinery spaces. To demonstrate that the inert gas
plant is fully operational and in good working order, a record of inspection of the inert
gas plant, including defects and their rectification, should be maintained on board.

Degradation of Inert gas Quality


Tanker personnel should be alert to the possible degradation of inert gas quality within
tanks as a result of air being drawn into the tanks due to inappropriate operation of the
inert gas or cargo systems. For instance:

 Not topping up the inert gas promptly if the pressure in the system falls, due to
temperature changes at night.
 Prolonged opening of tank apertures for tank gauging, sampling and dipping.

When water is drained from a non-inerted tank, air will be entered into the drainings
delivered to the slop tank and may ultimately enter into inerted tank atmospheres. The
volume of air entrained in this manner can be particularly high if an eductor is used on
recirculation to the slop tank. Therefore, when liquid is to be drained to the slop tank,
the inert gas quality in all tanks should be closely monitored.

Application to Cargo Tank Operations


Before the Inert gas system Is put Into service,  the tests required by the operations
manual or manufacturer’s Instructions should be carried out. The feed oxygen analyser
and recorder should be tested and proved to be In good order. Portable oxygen and
hydrocarbon meters should also be prepared and tested.

 Inerting of  Empty Tanks


When Inerting empty tanks that are gas free, for example following a dry docking or tank
entry, inert gas should be introduced into the distribution system while venting the air in
the tank to the atmosphere. This operation should continue until the oxygen content
throughout the tank is not more than 8% by volume. Thereafter, the oxygen level will not
increase if a  positive pressure is maintained by using the Inert gas system to introduce
additional inert gas when necessary. If the tank is not gas free, the precautions against
static electricity should be taken until the oxygen content of the tank has been reduced
to 8% by volume. When all tanks have been inerted, they should be kept common with
the inert gas main and the system pressurised with a minimum positive pressure of at
least 1 DO mm water gauge. If Individual tanks have to be segregated from a common
line (e.g for product Integrity}, the segregated tanks should be provided with an
alternative means of maintaining an inert gas blanket.

Loading Cargo or Ballast into Tanks in an


Inert Condition
When loading cargo or ballast, the Inert gas plant should be shut down and the tanks
vented through the appropriate venting system. On completion of loading or ballasting,
and when all ullaging is completed, the tanks should be closed and the Inert gas system
restarted and re-pressurised. The system should then be shut down and all safety
isolating valves secured. Local regulations may prohibit venting after crude oil washing.

Discharge of  Cargo or Ballast from Tanks


in an Inert Condition
The Inert gas supply must be maintained throughout cargo or ballast discharge
operations to prevent air entering the tanks. If a satisfactory positive inert gas pressure
can be safely maintained without a continuous supply of Inert gas, then it’s acceptable
to re-circulate or stop the supply of Inert gas provided that the Inert gas plant is kept
ready for immediate operation. If on arrival in port the inert gas has to be de-pressurised
in order to measure or sample the cargo, it may be difficult, because of the low boiler
load, to re-pressurise with an Inert gas having sufficiently low oxygen content. In this
situation, it may be necessary to create a load on the boiler by using the main cargo
pumps to circulate the cargo around the ship’s pipelines until the Inert gas quality Is
satisfactory. Great care is necessary to ensure that the pumping arrangements used for
circulating cargo do not give rise to an overflow. Throughout the discharge of cargo,
particularly when the boiler load is low or fluctuating, the oxygen content of the Inert gas
supply must be carefully monitored. Additionally, both the oxygen content and pressure
of the Inert gas main should be continuously recorded during discharge, for action to be
taken in the event of failure of the Inert gas plant during discharge from Inerted tanks. If
hand dipping of a tank Is necessary, pressure may be reduced while dipping ports are
open, but care must be taken not to allow a vacuum to develop since this would pull air
Into the tank. To prevent this, It may be necessary to reduce the cargo pumping rate,
and discharge should be stopped immediately if there is a danger of the tanks coming
under vacuum.

Loaded Passage
A positive pressure of Inert gas should be maintained in the ullage space at all times
during the loaded passage In order to prevent the possible ingress of air. If the pressure
falls below the low-pressure alarm level, it will be necessary to start the Inert gas plant
to restore an adequate pressure in the system. Loss of pressure is normally associated
with leakages from tank openings and falling air and sea temperatures. In the latter
cases, It is all the more important to ensure that the tanks are gas tight. Gas leaks are
usually easily detected by their noise and every effort must be made to eliminate leaks
at tank hatches, ullage lids, tank washing machine openings, valves etc. Leaks that
cannot be eliminated should be marked and recorded for sealing during the next ballast
passage or at another suitable opportunity. Certain all products, principally aviation
turbine kerosene and diesel oil, can absorb oxygen during the refining and storage
process. This oxygen can later be liberated into an oxygen deficient atmosphere such
as the ullage space of an Inerted cargo tank. Although the recorded Incidence of
oxygen liberation is low, cargo tank oxygen levels should be monitored so that any
necessary precautionary measures can be taken prior to the commencement of
discharge.

Static Electricity Precautions


In normal operations, the presence of Inert gas prevents the existence of flammable gas
mixtures inside cargo tanks. Hazards due to static electricity may arise, however; mainly
in the case of a failure of the Inert gas system. To avoid these hazards, the following
procedures are recommended:

  If the Inert gas plant breaks down during discharge, operations should be
suspended. If air has entered the tank, no dipping, ullaging, sampling or other
equipment should be introduced into the tank until at least 30 minutes have
elapsed since the injection of inert gas ceased. After this period, equipment may
be introduced provided that all metallic components are securely earthed. This
requirement for earthing should be applied until a period of five hours has elapsed
since the Injection of Inert gas ceased.
  During any necessary re-inerting of a tank following a failure and repair of the
Inert gas system, or during Initial Inerting of a non-gas free tank, no dipping,
ullaging, sampling or other equipment should be inserted until the tank is in an
Inert condition, as established by monitoring the gas vented from the tank being
Inerted. However, should It be necessary to Introduce a gas sampling system Into
the tank to establish its condition, at least 30 minutes should elapse after stopping
the injection of Inert gas before inserting the sampling system. Metallic
components of the sampling system should be electrically continuous and
securely earthed.

Purging
When it Is required to gas free a tank after washing, the tank should first be purged with
Inert gas to reduce the hydrocarbon content to 2% or less by volume. This is to ensure
that, during the subsequent gas freeing operation, no portion of the tank atmosphere Is
brought within the flammable range. The hydrocarbon content must be measured with
an appropriate meter designed to measure the percentage of hydrocarbon gas in an
oxygen deficient atmosphere. The usual flammable gas Indicator Is not suitable for this
purpose. If the dilution method of purging Is used, It should be carried out with the inert
gas system set for maximum capacity to give maximum turbulence within the tank. If the
displacement method Is used, the gas Inlet velocity should be lower to prevent undue
turbulence.

Gas Freeing
Before starting gas freeing, the tank should be isolated from other tanks by means of
closing valves or blanking off associated pipelines. When either portable fans or fixed
fans connected to the cargo pipeline system are used to introduce air into the tank, the
Inert gas inlet should be isolated. If the Inert gas system fan Is employed to draw air into
the tank, both the line back to the Inert gas source and the Inert gas Inlet into each tank
that Is being kept Inerted should be isolated.

Preparation for Tank Entry


To ensure the dilution of the toxic components of Inert gas to below their Threshold
Limit Values (TLVs), gas freeing should continue until lasts with an oxygen analyser
show a steady oxygen reading of 20.9% by volume and tests with a flammable gas
Indicator show not more than 1% LFL. If the presence of a toxic gas such as benzene or
hydrogen sulphide is suspected, gas freeing should be continued until tests Indicate that
its concentration Is below its TLV-TWA. Positive fresh air ventilation should be
maintained throughout the period that personnel are In a tank, and frequent tests should
be made of both oxygen and hydrocarbon content of the tank atmosphere. When other
tanks in an Inert condition are either adjacent or Interconnected (e.g. by a pipeline) to
the tank being entered, personnel should be alert to the possibility of Inert gas leaking
Into the gas free tank through, for example, bulkhead fractures or defective valves. The
risk of this occurring can be minimised by maintaining a small but positive inert gas
pressure. When a gas free tank is re-connected to the inert gas main, it should
immediately be re-inerted.

Pressure/Vacuum Breakers
Every Inert gas system Is required to be fitted with one or more pressure/vacuum
breakers or other approved devices. These are designed to protect the cargo tanks
against excessive pressure or vacuum and must, therefore, he kept in good working
order by regular maintenance in accordance with the manufacturer’s Instructions. When
these breakers are liquid filled, it Is important to ensure that the correct fluid Is used and
the correct level is maintained. The level can normally only be checked when there is no
pressure in the Inert gas main line. Evaporation, condensation and possible ingress of
sea water should be taken Into consideration when checking the liquid condition and
level. In heavy weather, the pressure surge caused by the motion of the liquid in the
cargo tanks may cause the liquid in the pressure/vacuum breaker to be blown out. This
may be more liable to happen on combination carriers than on tankers.
Read about Deck Water Seals

IGS Requirement Table (DNV)

IG Systems – Amendments & New Requirements


The IMO’S Maritime Safety Committee (MSC) has worked closely on the matter
and following their 93rd session have introduced new requirements and amendments
to the IG Systems;
These amendments:
 Apply to oil and chemical tankers constructed on or after 1st January 2016.
 Do not apply retrospectively to existing tankers constructed before 1st
January 2016.
 Have been included in SOLAS Ch.II-2, the IBC code and the FSS code Ch.15

In General:
 The fitting of a fixed inert gas system will be required for tankers of 8,000
tonnes deadweight (dwt) and over, constructed (keel laid) on or after 1 January
2016. Previously, this applied only to tankers of 20,000 tonnes dwt and over.
 Tankers 8,000 dwt and over, carrying low-flashpoint cargoes, and constructed
(keel laid) on or after 1 January 2016, must be provided with a fixed inert gas
system complying with Chapter 15 of the amended FSS Code (or an equivalent
system – subject to acceptance by the flag administration).
 The existing clause in SOLAS Regulation II-2/4.5.5.2 for waiving the
requirements for a fixed inert gas system still applies to all gas carriers, but for
chemical tankers, it now only applies to those constructed before 1 January 2016.
This means that chemical tankers constructed (keel laid) on or after 1 January
2016, and carrying flammable cargoes such as those listed in the IBC Code
chapters 17 and 18, will be required to have a fixed inert gas system, regardless
of cargo tank size and tank washing machine capacities.
 The amendments also require the oxygen content supplied to the cargo tanks by
the inert gas system to be reduced to 5%. The earlier limit was 8%.

Amendments for Oil tankers:


Tankers fitted with exhaust gas type inerting system will require inerting to be carried
out during loading, on the voyage, during unloading, tank cleaning and for purging prior
to gas freeing with air.

Amendments for Chemical Tankers:


 In the case of chemical tankers, it is accepted that inert gas need only be applied
before commencing the unloading. This is in order to reduce cargo handling time.
However, nitrogen will be the only accepted inert gas medium.
 The exemption for existing chemical tankers – having cargo tank volumes not
exceeding 3000 m3 and having tank cleaning machine throughput not exceeding
17.5 m3/h per nozzle and total throughput not exceeding 110 m3/h per tank, does
not apply to new chemical tankers constructed on or after 1st January 2016.
 However, the previous exemption for chemical tankers related to inert gas
capacity still exists. When carrying flammable chemicals it is, therefore,
acceptable that the unloading rate is reduced to 80% of the inert gas system
capacity.
 A new paragraph is inserted in Chapter 8 of IBC code under “Cargo tank purging”
which reads as “… before gas-freeing, the cargo tanks shall be purged with inert
gas through outlet pipes with a cross-sectional area such that an exit velocity of at
least 20 m/s can be maintained when any three tanks are being simultaneously
supplied with inert gas. The outlets shall extend not less than 2 m above the deck
level. Purging shall continue until the concentration of hydrocarbon or other
flammable vapours in the cargo tanks has been reduced to less than 2% by
volume. This is now in line with the oil tanker requirements.
 In case the chemical tanker is carrying oxygen dependent inhibitor and the tank
is required to be inerted, then the inert gas should not be used before loading or
during the voyage. Instead, the inert gas should be introduced in the tanks before
commencing unloading. The minimum level of oxygen required is mentioned in the
cargo manufacturer certificate and should be taken into account.

You might also like