Topic 2 Capital Budgeting PDF
Topic 2 Capital Budgeting PDF
Chapter 10
Capital Budgeting
Techniques
n
CFt
NPV CF0 (10.1)
t 1 (1 r )
t
n
CFt
(1 r ) t
PI t 1 (10.2)
CF0
EVA project cash flow – cost of capital invested capital
$120,000 – $100,000 $20,000
Again, we are looking for the discount rate that makes the
NPV of project A’s cash flows equal to zero. One way to
solve this equation is to use a trial-and-error approach, trying
different values for the IRR until reaching a solution.
Likewise, the IRR for project B is the discount rate that
makes the NPV of that project’s cash flows equal zero.
Copyright © 2019 Pearson Education, Ltd. All Rights Reserved.
Example 10.8
Figure 10.3 uses timelines to depict the
framework for finding the IRRs for Bennett’s
projects A and B. We can see in the figure that
the IRR is the unknown discount rate that
causes the NPV to equal $0.
Calculator use To find the IRR using the
preprogrammed function in a financial calculator,
the keystrokes for each project are the same as
those shown on slides 31 and 32 for the NPV
calculation, except that you don’t enter a value
for I/Y or compute NPV. Instead, once the cash
flows have been entered, you push CPT and
IRR as shown here.
Copyright © 2019 Pearson Education, Ltd. All Rights Reserved.
Example 10.8
Comparing the IRRs of projects A and B given in Figure 10.3
to Bennett Company’s 10% cost of capital, we can see that
both projects are acceptable because the return on each
project is greater than the cost of capital:
IRRA = 19.9% > 10.0%
IRRB = 21.7% > 10.0%
Comparing the two projects’ IRRs, Bennett’s managers rank
project B over project A because project B delivers a higher
IRR (IRRB = 21.7% > IRRA = 19.9%). If these projects are
mutually exclusive, meaning that Bennett can choose one
project or the other but not both, the IRR decision technique
would recommend project B.
Copyright © 2019 Pearson Education, Ltd. All Rights Reserved.
Example 10.8
Spreadsheet use The internal rate of return also can be
calculated as shown on the following Excel spreadsheet.
The net present values for projects A and B at the 10% cost
of capital are $110,710 and $109,244, respectively (from
Figure 10.2). Because the IRR is the discount rate for which
net present value equals zero, the IRRs (from Figure 10.3) of
19.9% for project A and 21.7% for project B result in $0
NPVs. Table 10.4 summarizes the three sets of coordinates
for each of the projects.