15.0 Colgrout Masonry Works Handbook
15.0 Colgrout Masonry Works Handbook
(Rajendra Pawar)
Director General,
Design, Training, Hydrology, Research and Safty
Maharashtra Engineering Research Institute, Nashik
II
LIST OF PWD HANDBOOK CHAPTERS
1.Materials.
2.Masonry.
3.Reinforced Concrete Construction.
4.Prestressed Concrete.
5.Plastering and Pointing.
6.Preparation of Projects and Engineering Geology.
7.Surveying.
8.Excavation.
9.Foundations.
10.Building.
11.Town Planning.
12.Roads.
13.C.D.Works and Bridges.
14.Ports and Harbours.
15.Runways and Air-strips.
16.Electrical Works Connected with Buildings.
17.Soil Mechanics.
18.Hydraulics.
19.Hydrology and Water Planning.
20.Masonry and Concrete Dams,
21.Earth and Composite Dams.
22.Instrumentation.
23.Spillways, Outlets, Gates and Hoists.
24.Canals.
25.Irrigation and Irrigation Management
26.Soil Survey of Irrigation Command, Land Drainage and Reclamation.
27.Hydro-power Scheme.
28.Construction of Tunnels.
29.Urban Water Supply.
30.Rural Water Supply.
31.Sanitary Engineering.
32.Construction Machinery.
33.Quality Control:
Part I : Cement Concrete, Part II : Earth Work
34.Labour Laws.
35.Rate Analysis.
36.Construction Planning.
37.Part-I -Land Acquisition Part-II- Valuation.
38.Mathematical Data and Miscellaneous Information.
39.Colgrout Masonry works.
40.Placement of concrete
41.Ready Mix Concrete
WRD1.Ferrocement Technology
WRD2.Colgrout Masonry Works
III
W.R.D. HANDBOOK CHAPTER NO. 02
INDEX
IV
15. Preparation of foundation .. .. .. 24
1. Colgrout masonry in contact with rock
foundation. .. .. .. 24
1. Cleaning of foundation .. .. 24
2. Bottom layer .. .. .. 25
2. Colgrout masonry in contact with fresh
colgrout masonry .. .. .. .. 26
3. Colgrout masonry in contact with old
colgrout masonry. .. .. .. 26
4. Colgrout masonry in contact with concrete. 26
16. Precautions to be taken during colgrout
construction .. .. .. .. 26
7 Work tests on materials, mortar and masonry 29
1. Tests on Materials .. .. .. .. 29
1. Cement .. .. .. .. .. 29
2. Sand .. .. .. .. .. 29
3. Stones .. .. .. .. .. 29
4. Fly ash .. .. .. .. .. 29
5. Chemical admixture .. .. .. 30
6. Water .. .. .. .. .. 30
2. Tests on Colgrout Mortar . 30
1. Flow meter tests .. .. .. .. 30
2. Use of RPM sensor .. .. .. 30
3. Weigh Batcher of RPM .. .. .. 30
4. Test on mortar cubes .. .. .. 30
1. Frequency of sampling of cubes. .. ... 30
2. Curing of cubes. .. .. .. .. 31
3. Tests. .. .. .. .. 31
4. Standard of acceptance .. .. .. 31
3. Tests on Colgrout Masonry 32
1. In-situ permeability .. .. .. .. 32
2. Non Destructive test by Ground Penetrating
Radar .. .. .. .. 33
3. Tests on drilled cores .. .. .. .. 33
1. Drilling and capping .. .. .. 33
2. Frequency of cores to be drilled. .. .. 35
3. Tests .. .. .. .. .. 35
1. Density .. .. .. .. 35
2. Permeability .. .. .. .. 35
3. Compressive strength .. .. .. 36
4. Split tensile strength .. .. .. 36
5. Modulus of Elasticity .. .. .. 36
4. Standard of acceptance .. .. .. 37
5. Calibration of equipments .. .. .. 37
8 Benefits of colgrout masonry .. .. .. 38
9 Guidelines for safe transportation of Colgrout 39
Masonry Cores .. .. .. .. .. .. ..
10 References .. .. .. .. .. 40
V
LIST OF TABLES
LIST OF PHOTOS
VI
1.0 INTRODUCTION
Uncoursed rubble masonry for dams and other massive structures was extensively
used till the closing of 20th century. However, the quality of conventional masonry is
deteriorating day by day and is not coming up to expected standards. The root cause of the
deteriorating quality of masonry is non-availability of good, experienced and or well
trained masons. With a view to keep pace with construction speed and to get expected
performance from masonry works, more advanced techniques were investigated.
Based on the experiments conducted at Maharashtra Engineering Research Institute,
Nashik as well as on few masonry dams in the state, WRD, Government of Maharashtra
vide Circular No. MISC/ 1094/ (160/90)/ MP/ Adm dated 17-02-1995 directed to use
colgrout masonry in upstream septum of masonry dams in lieu of UCR masonry (CM 1:3)
and M10 grade concrete. Since then over a period of 23 years, more than 50 gravity dams
have been constructed in colgrout masonry either in upstream septum or in full section. Its
use for modern structures is increasing steadily.
The present method of mixing mortar or concrete is not perfect, as every particle of
the cement in the mix does not get thoroughly mixed with water during very short mixing
time like 3 minutes or so. The cement particles are very fine (normal fineness of the
cement available in the market is 3000 to 4000 cm2/gm). Furthermore these innumerable
tiny cement particles are covered with micro air films or micro air bubbles, which are
attached to cement particles with surface tension. Unless the surface tension is broken air
bubbles will not get dispelled and the cement particles will not come fully in contact with
water.
To secure this objective, mix the two essential components, cement and water in a
mixer with 1500 to 2000 rpm. In this mixer, due to very fast movement of water molecule
and cement particles, the surface tension is broken, air bubbles are removed and cement
water solution gets converted into “Colloidal Cement” wherein maximum gel formation
takes place. This colloidal cement when mixed with sand, the resultant grout is called
“Colgrout or Colloidal Grout”. This colgrout is then introduced or injected in preplaced
aggregate, or masonry forming “Colcrete or Colgrout Masonry”.
1
2.0 TERMINOLOGY
2.1 Fine Aggregate - Natural sand or sand prepared from crushed stone, gravel or such
inert materials.
2.2 Bedding plane – The planes which separate the different layers of stone and are at
right angles to the pressure which acts on the stone mass during its formation in
nature
2.3 Bond – An interlocking arrangement of structural units in the masonry to ensure
stability.
2.4 Bond stone – Selected long stones used to hold the masonry together transversally.
2.5 Coefficient of permeability - The rate of flow of water under laminar flow
conditions through a unit cross sectional area of porous medium under a unit
hydraulic gradient and at a standard temperature of 270 C.
2.6 Colgrout double drum mixer - The mixer used for preparing colgrout mortar
2.7 Colgrout flow meter – Flow meter used for measuring the flow of colgrout mortar.
2.8 Colgrout masonry - Resultant masonry by injection of colgrout mortar in pre-
packed stones.
2.9 Colgrout mortar or Colloidal grout - A homogeneous mixture of cement, fine
aggregate and water and admixture, if any, mixed at high speed in colgrout double
drum mixer.
2.10 Exit pipe of mixer - The outlet for releasing the colgrout mortar from second drum
of colgrout mixer.
2.11 Form work – A temporary erection of timber or steel framing with boarded platform
at levels suitable for construction in stages.
2.12 Grout – Mixture of cement, sand and water used for filling the voids.
2.13 Colgrouting – Inserting colloidal grout with some suitable pressure to fill up voids,
if any, in the pre-packed stones.
2.14 Hammer dressing - Rough surfacing to a stone by means of a Spall hammer.
2.15 Hardening - The physical and chemical changes observed in mortar/ masonry due to
effect of setting of cement and loss of water.
2.16 Homogeneous masonry - Masonry which has no voids.
2.17 Interstice – Void or space between adjacent placed stones.
2.18 Laitance – An extremely fine film of material of little hardness which may form on
the surface of freshly laid masonry.
2
2.19 Lugeon - It is the water loss in litres per minute per meter depth of the hole under a
pressure of ten atmosphere maintained for ten minutes in a drilled hole of 46 to
76mm diameter.
2.20 Natural sand - A fine aggregate produced by natural disintegration of rock and
which has been deposited by streams or glacial agencies.
2.21 Natural stone - Lump of igneous rock.
2.22 Pozzolana - An essentially siliceous material which in itself possessing no
cementitious properties, in finely divided form and in the presence of water, react
with calcium hydroxide at ordinary temperature to form compounds possessing
cementitious properties.
2.23 Stretcher stone (Pin header) - Selected long stones embedded vertically in the
interior of masonry to form a bond between successive courses.
2.24 Sand - A fine aggregate which is either natural sand or crushed stone sand or crushed
gravel sand.
2.25 Setting - The physical and chemical changes observed in mortar/ masonry mainly
due to the hydration of constituents of mortar or due to the interaction of some of
constituents or a combination of both the types of reactions.
2.26 Slurry – Paste of cement and water.
2.27 Workability - The working consistency of a mortar as judged by the worker from its
behavior during application such as its easy spreading without separation of water or
segregation of the solid material of the mix.
2.28 Quoins – Dressed stones used for corners.
3
3.0 MATERIALS
3.1 Cement
Ordinary Portland cement, Portland slag cement, Portland Pozzolana
cement and Super sulphated cement used for stone masonry works in dams and other
massive structures shall comply with the requirements of IS: 269-1976 (Revision
2015), IS: 455–1976 (Revision 2015), IS: 1489 –2015 and IS: 6909 – 1990
(Reaffirmed 2016) respectively. Special cements may also be specified for use in
dam masonry.
3.2 Sand
3.2.1 Natural river sand - The sand shall conform to IS: 2116 – 1980 (Reaffirmed 2017)
and IS: 383-1970 (Reaffirmed 2002)
a) Quality The sand shall be of hard, dense, durable, and uncoated by gritty material
derived from rock fragments. Sand shall not contain harmful impurities such as
iron pyrites, alkalis, salts, coal or other organic impurities, mica, shale or other
laminated materials, soft fragments, sea shells in such a quantity as to affect
adversely the strength and durability of mortar.
The maximum percentage of deleterious materials in sand as delivered for use in
mortar shall not exceed the following values:
Table no. 1: Deleterious substances in sand
Maximum permissible
Sr. limit by weight
Deleterious substances
No. Natural Crushed
sand sand
1 Materialfinerthan 3% 15%
75micron IS sieve
2 Shale 1% --
3 Coal & Lignite 1% 1%
4 Clay lumps 1% 1%
5 Cinders and clinkers 0.5% --
6 Total % of all above 5% 2%
deleterious materials. ( excluding
75 micron
materials)
4
Note: The sum of percentages of all deleterious substances shall not exceed 5%
by weight for both sands and percentage of coal & lignite and clay lumps shall
not exceed 2% for crushed sand.
Sand shall be free from injurious amounts of organic impurities. If the impurities
are beyond the acceptable limits, the sand shall be washed or otherwise cleaned to
the entire satisfaction. Such sand may be used, provided that, when tested for the
effect of organic impurities on the strength of mortar, the relative strength at 7
and 28 days, reported in accordance with clause 7 of IS: 2386 (Part VI) – 1963
(Reaffirmed 2016), shall not be less than 95%.
b) Mechanical analysis: Sand shall be well graded and passing through 4.75mm
sieve, oversize shall not exceed 5% and no fraction shall exceed 35%. Fineness
Modulus shall be within 2.6 to 3.0. If the sand quarried happens to be coarser, the
sand will have to be corrected before use by necessary sieving or by adding
missing sizes in requisite quantity. The missing sizes can, also, be obtained by
crushing of stones after necessary tests.
The sand shall be well graded and when tested as per IS: 2386 (Part I)-1963
(Reaffirmed 2016), shall conform the following limits of gradation of IS: 2116 –
1980 (Reaffirmed 2017)
Table no. 2: Required gradation of sand and Fineness Modulus.
Percentage passing on the
Sieve size
sieve by weight
4.75 mm 100
2.36 mm 90 - 100
1.18 mm 70 - 100
600 micron 40 - 100
300 micron 5 - 70
150 micron 0 - 15
For crushed sand, the permissible limit on 150 micron IS sieve is 20%. This does
not affect the 5% allowance permitted to other sieves.
5
The gradation shown in table above is indicative only. The best gradation will be
determined after experiments and tests. The various sizes of particles of which
the sand is composed shall be uniformly distributed throughout the mass.
3.2.3 Storage
Arrangements shall be made to store the sand in a way that would protect it
from being contaminated with dust, organic matter or other deleterious substances.
Varying amount of moisture in sand contribute to lack of uniformity in mortar
consistency. Efforts should be made to ensure uniform and stable moisture content
in the sand as batched. Stock pile drainage may take 48 hours to reduce moisture in
sand to uniform and stable amount. It is desirable to maintain three stockpiles for
sand – one receiving wet sand, second under drainage and third for use in
construction.
3.3 Stone
3.3.1 Stone for masonry
a) Quality: Common types of stone used for colgrout masonry are trap and Basalt.
Stones shall conform to the properties laid down in IS 1121 to 1126 and IS:
8605 – 1977 (Reaffirmed 2013). Stones shall be hard, dense, durable, tough,
sound and clean. They should be free from decay, weathered faces, soft seams,
adhering coatings, sand holes, veins, flaws, cracks, stains and other defects.
Stones shall have, as far as possible, uniform colour and texture. Stones not
uniform in colour, texture and/or with stains may be permitted after proper tests.
6
b) Size: The size of stones shall normally vary from 0.05 to 0.01 m3. The stone
shall be taken from quarries approved from geological and engineering
considerations. No stone shall weigh less than 25 kg. The stone used in the
hearting shall be roughly cubical in shape. No stone weighing between 75kg
and 150kg shall be less than 225 mm and no stone weighing between 25kg to
75kg shall be less than 150 mm in any direction.
c) Spalls: Spalls with the minimum dimension of 200 mm to 100 mm shall be
used to wedge in to the interstices of stones. They shall not, normally, exceed
10 percent of the volume of colgrout masonry.
7
3.3.3 Stones for Uncoursed Face Work
The stones for uncoursed face work shall be selected stones meeting the
requirement of stones for coursed face work masonry (refer 3.3.2) except that the
stones shall be hammer dressed. The stones shall be nearly rectangular.
3.4 Water
Water used for mixing mortar, grout and also washing stones and curing
masonry shall conform to the requirements of IS: 456 – 2000 (Reaffirmed 2016),
due considerations being given to seasonal variation. It shall be reasonably clean and
free from objectionable quantities of silt, organic matter, alkali, salts and other
injurious materials. Turbidity of water for mixing mortar shall not be more than
2000 parts per million.
8
Fly ash is used as an admixture/part cement replacement to improve the
properties of mortar. It reduces water requirement, improves the workability and
improve strength at later days due to pozzolanic property. Construction cost can be
reduced by part replacement of cement by fly ash. Fly ash shall be collected as per
IS: 6491 – 1972 (Reaffirmed 2016), tested in accordance with IS: 1727 – 1967
(Reaffirmed 2013) and shall conform to the following limits of physical and
chemical requirements for use in mortar/ concrete as laid down in IS: 3812 (Part I)
– 2013 (Reaffirmed 2017).
Table no 3 : Physical and chemical requirements of fly ash
Sr. Properties Permissible limits
no.
Physical properties
1 Fineness > 3200 cm2 /g
2 Lime Reactivity > 40 kg/cm2
3 Cement reactivity > 80% of cement
mortar
Chemical contents
4 Silicon Di-oxide (SiO2 ) Min. 35%
5 Magnesium Oxide (MgO) Max. 5%
6 Sulphur Tri-oxide (SO3 ) Max. 5%
7 Silicon Di-oxide( SiO2 ) + Min. 70%
Aluminum Oxide(Al2 O3)
+ Iron Oxide( Fe2 O3 )
8 Loss on Ignition Max. 5%
9 Sodium Oxide (Na2 O) Max. 1.5%
9
Part replacement of cement by fly ash in colgrout masonry shall be used only
with Ordinary Portland Cement and not with Portland Slag cement or Portland
Pozzolana cement or Super sulphated cement as they already contains pozzolana.
In colgrout application, fly ash shall be mixed by weight with cement and
water in first drum of colgrout mixer. Fly ash colgrout masonry must be cured for
longer period, improper curing damages the masonry.
3.6 Admixture
The admixture including pozzolana, air entraining agents, wetting agents, etc.
shall be used only under specific authorization and wherever so permitted;
proportions and methods of use shall be specified by engineer-in-charge. The
chemical admixture shall be tested as per IS: 6925 - 1973 (Reaffirmed 2013) for
chloride ion content and as per IS: 9103 – 1999 (Reaffirmed 2013) for relative
density and pH value and conform to IS: 9103 – 1999 (Reaffirmed 2013).
Materials permitted as admixtures shall have established merit for improving
any specific quality of the mortar without causing deleterious effects. They are aids
to help modify good mixes and good construction practices to achieve certain
specific requirements.
Exact proportion of admixture to be added shall be ascertained by carrying out
mortar mix design.
10
4.0 EQUIPMENTS AND TOOLS
4.1 Equipments
4.1.1 Colgrout mixer
Photo no.1: Colgrout double drum mixer – side and top view.
Double Drum Mixer consists of two mixing units and a power unit mounted on
a suitable chassis. Each mixing unit consists of a hopper tank connected by means of
a trap to a casting similar to that of a centrifugal pump.
The first mixing unit produces water + cement slurry which transferred to the
second unit where sand is added to produce a Cement + Water + sand grout. In the
body of the cement mixing unit, a solid rotor disk rotates at the speed of 1500 to
2000 rpm in close proximity to the stator. This rotor produces a pumping action
which induces water + cement slurry to pass at high speed through the narrow gap
between the rotor and the stator. It also causes a rapid circulation through the hopper
tank where a strong vortex is formed and it serves to transfer the slurry to the other
mixing unit.
The rotor in the sand mixing unit is in the form of a star designed for wetting
the sand with the cement + water slurry and also for discharging the colgrout at a
suitable pressure through a hose. Means are provided in each hopper tank to cause
the cement or sand to fall evenly in to the vortex which ensures that materials may
be charged rapidly. Water is gauged by a separate water measuring tank or meter.
The water/cement ratio is under definite control, allowance being made for moisture
in the sand.
11
Whilst the sand being added to one mix of cement slurry in the second mixing
unit, following cement + water mix is being made in the first unit. The mixer is,
therefore, in semi-continuous batch operation. The complete mixing cycle takes
from 60 to 90 seconds, depending upon the method of charging. No improvement in
mixing efficiency will be gained by increasing the mixing time. The standard models
deal with a mixed volume of either 4 cu. ft. (0.11 cum) or 8 cu. ft. (0.22 cum).
12
4.2 Construction Tools
The tools used by mason for construction of colgrout masonry are as below:-
(1) Trowel – This is used for spreading mortar and is similar to the bricklayer’s trowel.
(2) Square – This is made of flat iron and each arm is about 50 cm long. It is used in
setting out right angles.
(3) Bevel – This is made of two blades of iron slotted and fastened with thumbscrew.
(4) Spirit level – This is used for checking the horizontality of masonry courses.
(5) Plumb rule and bob- This is similar to a bricklayer’s plumb rule and is used to
check the verticality of walls.
(6) Mallet - This is a wooden headed hammer and is used for driving wooden headed
chisels.
(7) Iron hammer – This is used for carving stones.
(8) Pick – This has a long head pointed at both ends. This is used for rough dressing of
granites.
(9) Spalling hammer – This is a heavy hammer used for rough dressing of stones in
the quarry.
(10) Chisels – They are used with mallets and with hammers. They have got different
shape and have pointed heads.
(11) Claw tool - This has an edge with a number of teeth from 3 mm to 9 mm width and
is used for dressing the surface of stones.
(12) Pitching tool- This has a long edge with a thick head and is used for reducing the
size of stones.
(13) Jumpers- These are sued for boring holes.
(14) Wood handled chisels – These are sued for dressing soft stones.
(15) Wedge and feathers - These are small conical wedges and curved plates. They are
used for cutting the stones after they have been bored with a jumper.
(16) Gads – These are small iron wedges for splitting of stones.
(17) Saws – These may be double saw, a framed saw or a hand saw. They are used for
cutting stones with hands.
(18) Mason’s hammer - This is a medium hammer used for dressing of stones used by
masons at pre-packing the stones.
13
5.0 COLGROUT MORTAR
14
All materials forming the mortar should be measured by mass except for water
which may be measured by mass or by equivalent volume. Where weigh-batching is
not possible, due consideration to bulkage of sand and its water content shall be
given. It is normally be regulated in accordance with IS:2386(Part III)-2016 as
under:
The proportion of cement and sand for colgrout mortar is recommended as 1:3.
The real criterion governing the mix will be the strength specified and actual
proportion of the ingredients to give the requisite strength and impermeability.
Mortar mix tests shall be carried out in the project laboratory well in advance.
Table no. 5 : Water cement ratio and water requirements for trial mortar mix.
Cement : sand Water/Cement Water for 50 kg
proportion ratio cement in litres
1:2 0.62 – 0.70 31 - 35
1:3 0.76 – 0.84 38 - 47
Moisture content of sand shall be taken in account while fixing the quantity of
water. The moisture content of sand shall be tested in accordance with IS:2386 (Part
III)-1963 (Reaffirmed 2016). The surface water carried by the sand is normally as
below:
15
Table no. 6 : Moisture content of sand
Sand Approximate quantity of water
% by mass Litre/m3
Very wet sand 7.5 120
Moderately wet sand 5.0 80
Moist sand 2.5 40
16
h) Total time for complete cycle of mixing: The total mixing time for the
complete cycle shall normally be 60 to 90 sec. The mixing time shall be
increased at the discretion of the engineer-in-charge when operation fails to
produce the required colloidal ness or uniformity of composition within the
batch and batch to batch.
17
6.0 COLGROUT MASONRY
6.1 Monolith
The dam shall be longitudinally divided into monoliths of suitable sizes as
shown in the drawing or as directed by the engineer-in-charge. Smooth joints shall
be provided between two adjacent monoliths. For this purpose, the vertical surface
of the monoliths constructed first shall not have a face projection above 15mm and
should be provided with smooth plaster in cement mortar 1:3 of minimum thickness
of 20mm. The difference in level of masonry lifts should not, normally, be more
than 1.5 m.
18
The area of compartments shall not be more than 25 to 30 sqm and height not
exceeding 1.0m. Compartments shall be in staggered manner. At each lift, position
of wall compartment shall be changed so that compartment of consecutive lift shall
not be overlapped. For Upstream & Downstream faces of the dam utmost care shall
be taken. Face work may be in wall compartment fashion or in colgrout masonry
using shuttering.
19
6.3.1 Pointing to face work
The face work shall be struck neatly and smoothen off with a trowel before the
mortar takes the final set.
All pointing shall be finished with cement sand mortar 1:3 or richer mix. The
sand shall be fine, passing through 600-micron IS sieve (see IS: 460 – 1985
(Reaffirmed 2013) and conforming in all respects to IS: 2116 – 1980 (Reaffirmed
2017).
The joints in masonry to be pointed shall be raked square, for a minimum
depth of two times the thickness of the joint within 24 hours of laying masonry. In
special circumstances, this period may be released to 48 hours. The refilling and
pointing shall be done within three days of raking of the joints so as to ensure good
adhesion between the two mortars.
The joints shall be finished neat, defined, regular and of uniform width. The
joints may be filled either flush or raised as required. The surface pointed should be
kept wet for 21 days after pointing is completed.
20
6.4.2 Removal of formwork
Removal of forms shall never be started until colgrout is thoroughly set and
hardened adequately to sustain its own weight and live load, if any. Heavy load shall
not be permitted until after the colgrout masonry has reached its final set. In normal
circumstances, shuttering shall be struck on expiry of 48 hours from injection of
colgrout mortar. Where formwork is used, all faces of masonry shall be smooth and
sound, free from voids and air holes when formwork is struck. Any roughness or
irregularity on the exposed surface shall immediately filled up while masonry is
green, with cement mortar 1 :1½, properly trawled and finished. Such patching of
surface shall be carried only with permission of engineer-in-charge.
21
Photo no. 4: Laying of stones in compartment
Headers - Adequate headers shall be provided for proper horizontal and vertical
bond with next surrounding layers. The minimum number of headers shall be
more than one per 4 sqm area to be bonded.
Stretcher stones (pin headers) - A row of vertical pin headers shall be erected
at about 2m centre to centre both ways so that there is at least one vertical stone
for every 4 sqm area or as directed by the engineer-in-charge for the bond with
next lift.
b) Spalls: Stone spalls of 200mm to 100mm size shall be wedged in to the
interstices between the adjacent stones whenever necessary to avoid thick beds
or joints and to achieve maximum density. Use of chips shall be restricted to the
filling of interstices only. There shall be a good collection of chips within easy
reach of each mason to enable proper selection for laying and they should be
kept continuously replenished.
c) Layers: The thickness of layer shall normally be 35 cm. Such layers shall be
continued to be arranged till the predetermined height of the compartment or
panel is reached.
22
d) Placing of G.I. Pipes: 75mm diameter perforated GI pipes shall be placed at
1.5m center to center ( or at least one pipe per 2.15 sqm area) or as directed by
engineer-in-charge and about 25mm above the bottom while pre-packing the
stones. Pipes shall be withdrawn simultaneously as colgrouting of each hole is
in progress.
6.13 Curing
Curing is the process of preventing the loss of moisture from the masonry
whilst maintaining a satisfactory temperature regime. The curing also prevents the
development of high temperature gradient within the masonry. Exposed surface of
the masonry shall be cured after 4 to 12 hours of construction. All colgrout masonry
as it progresses, shall be kept continuously moist on the entire surface for a
minimum period of 21 days from the date of its being laid. Masonry shall, on no
account, be allowed to present dry surface during curing period. Should the mortar
perish i.e. become dry or powdery through neglect of watering, the relevant work
shall be demolished and rebuilt.
Curing is, particularly, important when pozzolana, slag or supersulphated
cement is used as their hydration period is longer.
b) Bottom layer
Immediately prior to placing a layer of masonry, the foundation shall be wetted for
24 hours. Foundation shall be coated with brush by thick cement slurry (1 cement :
2 or 3 water by volume) just few minutes before laying the masonry. The slurry
shall be spread only on a small area of about 1.0 m2 at a time. A layer of mortar 50
to 75mm thick, shall be spread over the slurry and worked into all irregularities of
the rock surface by trowels, bars or brushes. The composition of this mortar shall
be same as used in colgrout masonry work. The first course of stones shall be
carefully interlocked and pressed into the mortar so as to force the mortar around
the corners. The layer of mortar shall be made thicker, if required, to suit stones of
sizes larger than 0.06cum. The voids of this stone packing shall be filled with
smaller stones and chips. The colgrout mortar shall be filled by means of nozzles
or any other approved method as directed by engineer-in-charge.
25
6.15.2 Colgrout masonry in contact with fresh colgrout masonry
Surface of masonry shall be treated as follows before laying fresh masonry
over it. Loose stones, if any, shall be removed. Mortar joints shall be scraped with
iron rods and the exposed faces of stone shall be wire brushed. The surface shall be
cleaned with air-water jet. The water collected in the depressions of masonry shall
be removed by sponge or cloth. Older surface shall be coated with brush by thick
cement slurry (1 cement: 2 or 3 water by volume) just few minutes before laying
the next lift.
26
iii. Maximum size of sand shall be less than 4.75mm having fineness modulus
within 2.6 to 3.0. If necessary, sand shall be get screened. Sand shall be weigh
batched. Moisture content shall be determined and accordingly water content
shall be fixed for every shift.
iv. Cement shall be weigh batched. It shall be used within 3 months from the date
of manufacturing; else fresh mortar mix design shall be done to get required
properties of mortar.
v. Water shall be volume batched and conform to IS: 456-2016.
vi. Area of masonry wall compartment shall be of 25 to 30 sqm with height not
exceeding 1.0m so that construction can be completed in one working shift
only. At each lift, position of wall compartment shall be changed so that
compartment of consecutive lift shall not be overlapped.
vii. Only double drum colgrout mixer should be used for preparing colgrout
mortar. The speed of mixer should be 1500 to 2000rpm and it shall be checked
frequently. This is the special important phenomenon in preparation of
colgrout mortar. Mixer shall be rotated until the colloidal state is reached
viii. The mixer shall be placed 2.0m and above height above the level of
compartment. The delivery pipe of the mixer shall be straight and have
uniform slope towards compartment. Sagging of pipe is avoided; else it
reduces the delivery pressure of mortar.
ix. The mortar of requisite flow should be permitted to pass in the compartment.
x. At the start of the work, mixer shall be wetted and first load shall be made of
cement slurry only for priming and lubricating the mixer and delivery pipe.
xi. At the end of work, the mixer and delivery pipe shall be cleaned by cement
slurry which carried the sand particles adhered and then washed by the water.
The cement slurry may be passed in the compartment, but the waste water
should be taken outside the construction area.
xii. If chocked, the delivery pipe shall be cleaned by forcing water and these waste
contents should be passed outside of the construction area.
xiii. The insertion of mortar in the compartment shall proceed from one end in
direct sequence so as to achieve uniform height of the mortar in all perforated
GI pipes in any section of colgrouted masonry and pipes shall be withdrawn as
hole is getting filled up.
27
xiv. Care should be taken to avoid any type of activity on the top of fresh masonry
constructed at least for 24 hrs.
xv. All colgrout masonry as it progresses shall be kept continuously moist on the
entire surface for a minimum period of 21 days from the date of its being laid.
Masonry shall, on no account, be allowed to present dry surface during the
curing period.
xvi. Samples of the materials shall be collected and tested regularly as per
respective Indian standards. Mortar tests shall be regularly carried out and
review of results shall be taken periodically.
28
7.0 WORK TESTS ON MATERIALS, MORTAR AND MASONRY.
7.1 Tests on materials
7.1.1 Cement
One sample per 50 ton cement shall be collected for testing in accordance
with IS: 3535 – 1986 (Reaffirmed 2013). Ordinary Portland cement, Portland slag
cement, Portland pozzolana cement and Super sulphated cement shall be tested in
accordance with IS: 4031 - 1996 (Reaffirmed 2016) and shall conforms to IS:8112-
2013 for 43 grade and IS:12269-2013 for 53 grade, IS: 456 – 2000 (Reaffirmed
2016), IS:1489-2015 and IS: 6909 – 1990 (Reaffirmed 2016) respectively.
7.1.2 Sand
Sand samples from the work site shall be collected in accordance with IS:
2430 – 1986 (Reaffirmed 2014) and shall be tested as per IS: 2250 –1981
(Reaffirmed 2015) and IS:2386 (Part I to VII)-1963 (Reaffirmed 2016) regularly to
test its quality. One sample of every 500 cum of colgrout masonry or one sample in a
week whichever is earlier shall be tested. If sand is measured by volume, bulkage of
sand shall be tested per shift.
7.1.3 Stones
Samples of stone from approved quarry or new quarry shall be tested for
compressive strength in accordance with IS: 1121 (Part-I) -1974 (Reaffirmed 2017).
The compressive strength shall be conducted with the load parallel to the bedding
plane and also perpendicular to the bedding plane. The stone samples shall also be
tested for water absorption in accordance with IS: 1124 –1974 (Reaffirmed 2017),
and for soundness in accordance with IS: 1126 – 2013 to ensure suitability of stones
for masonry.
29
7.1.5 Chemical Admixture
Chemical admixture shall be tested as per IS: 6925 - 1973 (Reaffirmed 2013)
for its chloride content for each drum of admixture to be used at site.
7.1.6 Water
Water shall be tested in accordance with IS: 456 – 2000 (Reaffirmed 2016) per
season or as directed by the engineer-in-charge.
30
7.2.4.2 Curing of cubes: Cube moulds shall be placed in 90% relative humid
environment or under wet gunny bags in a closed room for 24 hours. Then cube
moulds are de-moulded. Cubes are submerged in clean water and keep there until
just prior to testing. Renew the water every 7 days and maintained the temperature
at 270C±20C. The curing tank shall be in closed room, away from sunlight.
7.2.4.3 Tests: Cubes shall be tested in surface saturated dry condition. They should
neither tested in wet condition nor allow becoming dry. Test for compressive
strength and permeability at 28 days shall be conducted as per IS: 2250 –1981
(Reaffirmed 2015) and IS: 3085 - 1965(Reaffirmed 2016) respectively. Record of
test results shall be kept in separate register. Where specimen of different sizes is
used such as 15cmx30cm cylinder, necessary correlation shall be applied.
7.2.4.4 Standard of Acceptance
Permeability
Permeability of mortar as used on work shall not give a coefficient of permeability
greater than 2.5 x 10-8 mm/sec when tested as per IS: 3085 - 1965(Reaffirmed
2016).
31
7.3 Tests on Colgrout Masonry
7.3.1 In-situ permeability
32
These holes shall be subjected to a water loss to determine lugeon value.
Notwithstanding the test pressures specified for lugeon value, the actual test
pressure should not be so high as to cause disturbance to masonry. Then assuming
a linear variation of water loss with respect to pressure applied, the water loss in
lugeon value may be interpreted. The details of procedure and test equipment
reference may be made to IS:5529 (Part 2)-2006 (Reaffirmed 2015).
When a colgrout masonry septum is used on the upstream face of a
conventional masonry dam, the upstream hole for water loss test shall be drilled at
the center of the septum in each monolith.
Standard of impermeability shall be a water loss not more than 2.5 lugeons.
If the test results indicate water loss greater than the specified values, grouting
should do as a remedial measure and confirmatory tests carried out. Grouting
pressure should be kept such that it does not damage the constructed masonry.
33
Photo no. 6 : Drilling core by drilling machine at site
Capping of cores: Both end surfaces of the core shall be capped before testing.
The capped surfaces shall be made plain with smooth finish. The capping shall
done with rich mortar 1:2 or M20 grade concrete. Caps shall be made as thin as
possible and shall not flow or fracture before failure of specimen to be tested. The
capped surface shall be cured for at least 14 days. The capped surfaces shall be
right angles to the axis of the specimen. The plainness of the caps shall be checked
by means of a straight edge and feeler gauge making a minimum of three
measurements on different diameters. Height of core shall not be less than 90cm
after capping.
Procedure of capping:
a) Erect the core on plain platform.
b) Make core exactly vertical by using plumb-bob and wedges.
c) Strip of 18 gauge GI sheet is rapped around the top end of core. Adjust the
strip to have the requisite cap cover over the rough surface of core and
tightened it by a movable circular ring.
d) Top of GI sheet is made perfectly horizontal by spirit level and straight edge
making of minimum of three measurements on different diameters.
e) Finish the top surface in rich mortar 1:2 or concrete of M20 grade. The
plainness of cap shall be checked by means of a straight edge and spirit level,
making a minimum of three measurements on different diameters. Cap shall
be made as thin and smooth as practicable.
f) Cure the surface for 14 days and then capping is carried out for other end
surface.
34
Necessity: Cap preparation is required to fit the faces of core in the jaws of
compression testing machine without any gap and to exert the even pressure at any
point on the core face while applying load for ultimate crushing of the core.
7.3.3.2 Frequency of cores to be drilled One core upto and for every 10,000 cum of
colgrout masonry constructed during the season must be taken.
7.3.3.3 Tests: There is no specific Indian Standard available for testing of colgrout
masonry. Therefore, usual tests done on concrete as per IS: 516-1959 (re-affirmed
in 1999) are also performed on colgrout masonry.
7.3.3.3.1 Density - Density is obtained by measuring the volume of core and weighing the
core. The density shall be more than 2.40 gm/cc.
35
7.3.3.3.3 Compressive strength - Compressive strength is obtained by ultimate crushing
of core on 2000 Ton capacity Compression Testing Machine. This is the only
machine available in central India at M.E.R.I., Nashik. It is fully automatic and
computerized.
Photo no. 8: 2000 ton compression testing machine, control panel and computer
system at M.E.R.I., Nashik
7.3.3.3.4 Split tensile strength - The core is placed centrally with its axis horizontal on
2000 ton Compression Testing Machine and load is applied till the core splits
along the diameter. The split tensile strength is computed using following
formula;
7.3.3.3.5 Modulus of Elasticity (E) - Elasticity test is carried out after knowing
compressive strength of the core. Two Elasticity rings are fixed to the core at
60cm apart and equidistant from the edges of the core by screw arrangement.
Batty dial gauges are fixed on each of the two vertical arms which in turn are
fixed to the top ring at diametrically opposite points on the core. The movable
arm of the gauges rested on another small attachment fixed to the bottom ring
36
suitably. Procedure of elasticity test shall be as per IS: 516 – 1959 (Reaffirmed
2013) for concrete. The deformation of the core while gradually loading and
unloading is measured at an interval of 50 ton up to 40% of compressive strength
load. The average of two dial gauge readings is taken at each loading. Graph of
stress against strain is plotted and slope of line graph gives elasticity value.
b) Permeability value shall not be more than 0.5 lit/min/ m2 (2.5 lugeons) as per
IS:11216 -1985 (Reaffirmed 2013) .
c) Compressive strength shall not be less than 90 kg/cm2 for L/D ratio as 2.
d) Modulus of elasticity shall be comparable to that of concrete. It shall be 1.4 to
5.0 x 105 kg/cm2 as per IS: 516 – 1959 (Reaffirmed 2013).
7.3.5 Calibration of equipments – Periodical calibration of all the testing and measuring
instruments / equipments, shall be carried out.
37
8.0 BENEFITS OF COLGROUT MASONRY
8.3 Man power required is less as compared to the conventional masonry works.
8.4 Masonry being homogeneous and dense, permeability is very less. Thus, this
impermeability further reduces the cost of grouting and maintenance due to
seepage and leaching of materials.
38
9.0 GUIDELINES FOR SAFE TRANSPORTATION OF
COLGROUT MASONRY CORES
9.3 Measures during transportation of colgrout core from dam body to MERI,
Nashik
Colgrout cores are required to be transported from dam body to MERI, Nashik by
means of Trucks. For safety of colgrout cores, during transportation, the drilled cores
are kept above sand to avoid any damage. The cores while transporting, are required to
be arranged in horizontal axis position and sufficient distance (minimum 500 mm)
should be kept between two cores.
39
10.0 REFERENCES
40
21. IS: 2386 – 1963 (Reaffirmed 2016) - Methods of test for aggregates for concrete.
Part I- Particle size and shape.
Part II - Estimation of deleterious materials & Organic impurities.
Part III - Specific gravity, density, voids, absorption and bulking.
Part IV - Mechanical properties.
Part V - Soundness.
Part VI - Measuring mortar making properties of fine aggregate.
Part VII - Alkali-Aggregate reactivity.
22. IS: 2430 – 1986 (Reaffirmed 2014) - Methods for sampling of aggregates for concrete.
23. IS: 3085 - 1965(Reaffirmed 2016) – Method of tests for permeability of cement mortar
and concrete.
24. IS: 3535 - 1986(Reaffirmed 2013) – Methods of sampling hydraulic cement.
25. IS: 3812 (Part I) – 2013 (Reaffirmed 2017) - Specifications for Fly-ash for use as
pozzolana.
26. IS: 4031 - 1996 (Reaffirmed 2016) – Methods of physical tests for hydraulic cement.
27. IS: 4032 – 1985 (Reaffirmed 2014) – Methods of chemical analysis of hydraulic
cement.
28. IS:5529 (Part 2)-2006 (Reaffirmed 2015) – Code of practice for in-situ permeability
tests: Part- Test on bedrock.
29. IS: 6491 – 1972 (Reaffirmed 2016) - Methods of sampling of fly ash.
30. IS: 6909 – 1990 (Reaffirmed 2016) – Specification for Portland Super Sulphated
cement.
31. IS: 6925 - 1973 (Reaffirmed 2013)- Method of test for determination of water soluble
chlorides in concrete Admixture.
32. IS: 8112 - 2013 – Specification for Ordinary Portland Cement of 43 grade.
33. IS: 8605 – 1977 (Reaffirmed 2013) – Code of practice for construction of masonry in
dams.
34. IS: 9103 – 1999 (Reaffirmed 2013) – Specifications for concrete admixtures.
35. IS:11155-1994(Reaffirmed 2015) – Code of Practice for construction of spillways and
similar overflow structures.
36. IS:11216 -1985 (Reaffirmed 2013) – Code of practice for permeability test for
masonry during and after construction.
37. IS: 12269 - 2013 – Specifications for Ordinary Portland Cement of 53 grade.
41