Critical Path Method Exercises: Based On The PMBOK®
Critical Path Method Exercises: Based On The PMBOK®
Exercise 1:
For the following table of information,
Start 0 days -
A 5 days Start
B 2 days Start
C 3 days A, B
D 5 days Start
E 6 days Start
F 4 days D, E
G 2 days C, F
H 5 days G
I 7 days G
J 3 days H
Finish 0 days I, J
Exercise 2:
1
E
2 3 5 3
A B C F
5
G
5 8 7 5
H I J K
3
N
8 2
L M
1. Perform a Forward Pass and a Backward Pass of the network diagram above
2. Which Activities has the same Early Finish as they have Late Finish?
Duration
Activity Dependency Float
(Days)
Start 0 -
A 8 Start
B 5 A
C 6 B, H
D 8 C
E 9 D, F
F 3 C, I
G 7 Start
H 8 G
I 9 H
J 5 I
K 2 J
L 3 J
Finish 0
Critical Path Method Exercise Solutions
Exercise 1 Solution:
1.
0 5 5
A
2 2 7
5 3 8 12 5 17 17 3 20
C H J
7 2 10 12 0 17 17 0 20
0 2 2
B
5 5 7
10 2 12
0 5 5 1 7 19
G
D
2
1 1 6 0
6 4 10 1 1 I
F
6 0 10 Early Early
0 6 6 Start Duration Finish
E Task Name
Late Late
0 0 6 Start Slack Finish
2. Network paths:
0 2 2 2 3 5 5 5 10 10 3 13
A B C F 25 5 30
0 0 2 2 0 5 5 0 10 22 12 25 G
25 0 30
0 5 5 5 8 13 13 7 20 20 5 25
H I J K
0 0 5 5 0 13 20 0 25 25 3 28
13 0 20
N
25 2 28
13 8 21 21 2 23
L M
15 4 23 23 4 25
Exercise 3 Solution:
1.
0 8 8 8 5 13 15 6 21 24 3 27
A B C F
2 2 10 10 2 15 15 0 21 26 2 29
29 2 31
K
36 7 38
7 8 15 15 9 24 24 5 29
0 7 7
G H I J
0 0 7 7 0
15 17 2 26 30 6 35
29 3 32
L
35 6 38
2. Network paths: