The document provides calculations for the duration of various construction activities. It calculates durations for excavating the foundation, laying reinforcing bars, pouring concrete, installing formworks and rebar for columns and beams, and pouring concrete on the ground and second floors. Most activities took between 1 to 5 days to complete based on crew size and production rates.

Uploaded by

kennysaweg
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
174 views

Duration Computaion

The document provides calculations for the duration of various construction activities. It calculates durations for excavating the foundation, laying reinforcing bars, pouring concrete, installing formworks and rebar for columns and beams, and pouring concrete on the ground and second floors. Most activities took between 1 to 5 days to complete based on crew size and production rates.

Uploaded by

kennysaweg
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10

COMPUTATION OF DURATION

EXCAVATION OF FOUNDATION
depth = 2m
volume = area x depth 112.00 m3
production rate = 120.00 m3/day
duration= quantity/production rate 2.09 days
3.00 days

LAYOUT OF REINFORCING BARS

For founddation F-1


length= 6.00 m
weight= 1.58 kgs
no of bars= 114.00 pcs
total weight of bars for F1= 1080.72 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.46 days
For foundation F-2
length= 6.00 m
weight= 1.58 m
no of bars= 114.00 pcs.
total weight of steel for F-2= 1080.72 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 1.12 days
TOTAL DURATIION FOR FOUNDATION: 5.00 days

POURING OF CONCRETE
Volume = Area of foundation x depth x no.of footing
F-1 6.00 m2
F-2 2.40 m2
depth for all foundation= 2.00 m2
Total Volume= 16.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day
GROUND FLOOR
INSTALLATION OF FORMWORKS FOR COLUMNS
perimeter= 1.80 m
height= 3.00 m
total surface area of columns= 54.00 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 5.00 days

INSTALLATION OF REBAR FOR COLUMNS


Number of main reinforcement for columns= 10.00 pcs
length for main reinforcement= 3.00 m
total length for each column= 30.00 m
total length for 10 columns= 300.00 m
mass for main reinforcement= 741.00 kgs
Number of ties for each column= 34.00 pcs
length of each stirrup= 1.08 m
total length for each column= 36.72 m
total length for 10 columns= 367.20 m
mass for stirrups= 227.66 kgs
TOTAL MASS OF REBAR FOR COLUMNS= 968.66 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days

POURING OF CONCRETE FOR COLUMNS


Area= 0.16 m2
height= 3.00 m
volume for 1 column= 0.48 m3
total volume for 10 columns= 4.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day

INSTALLATION OF REBAR FOR TIE BEAMS


depth= 0.40 m
width= 0.30 m
length of main reinforcement= 6.00 m
number of main reinf. per beam= 83.00 pcs
total length of reinforcement of beam= 498.00 m
total mass for reinforcement= 786.84 kgs
length of each stirrup= 1.12 m
number of stirrups= 192.00 pcs
total length of stirrups= 215.04 m
total mass for stirrups= 133.32 kgs
TOTAL MASS OF REBAR FOR TIE BEAMS= 920.16 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days
INSTALLATION OF FORMWORKS FOR TIE BEAMS
perimeter of formworks= 2.30 m
total area for formworks= 28.67 m2
production rate= 1.50 m2/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 days

INSTALLATION OF SLAB ON GRADE


number of bars (longitudinal)(6m length) 50.00 pcs
total length for longitudinal bars= 300.00 m
number of bars (transverse)(6m length) 50.00 pcs
total length for transverse bars= 300.00 m
total length= 600.00 m
total mass= 372.00 kgs
production rate= 185.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.00 days

FORMWORKS FOR SLABS


perimeter= 41.60 m
thickness of slab= 0.12 m
area for formworks= 28.67 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 day

POURING OF CONCRETE FOR BEAM AND SLAB


area of slab= 59.47 m2
thickness of slab= 0.12 m2
volume for slab= 6.96 m3
area for beam= 0.12 m2
total length of beam= 56.70 m
volume for tie beam= 6.80 m3
total volume of concrete= 13.76 m3
production rate= 5.20 m3/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 2.00 day
SECOND FLOOR
INSTALLATION OF FORMWORKS FOR COLUMNS
perimeter= 1.80 m
height= 3.00 m
total surface area of columns= 54.00 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 5.00 days

INSTALLATION OF REBAR FOR COLUMNS


Number of main reinforcement for columns= 10.00 pcs
length for main reinforcement= 3.00 m
total length for each column= 30.00 m
total length for 10 columns= 300.00 m
mass for main reinforcement= 741.00 kgs
Number of ties for each column= 34.00 pcs
length of each stirrup= 1.08 m
total length for each column= 36.72 m
total length for 10 columns= 367.20 m
mass for stirrups= 227.66 kgs
TOTAL MASS OF REBAR FOR COLUMNS= 968.66 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days

POURING OF CONCRETE FOR COLUMNS


Area= 0.16 m2
height= 3.00 m
volume for 1 column= 0.48 m3
total volume for 10 columns= 4.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day

INSTALLATION OF REBAR FOR BEAMS


depth= 0.40 m
width= 0.30 m
length of main reinforcement= 6.00 m
number of main reinf. per beam= 83.00 pcs
total length of reinforcement of beam= 498.00 m
total mass for reinforcement= 786.84 kgs
length of each stirrup= 1.12 m
number of stirrups= 192.00 pcs
total length of stirrups= 215.04 m
total mass for stirrups= 133.32 kgs
TOTAL MASS OF REBAR FOR TIE BEAMS= 920.16 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days
INSTALLATION OF FORMWORKS FOR TIE BEAMS
perimeter of formworks= 2.30 m
total area for formworks= 28.67 m2
production rate= 1.50 m2/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 days

INSTALLATION OF SLAB ON GRADE


number of bars (longitudinal)(6m length) 50.00 pcs
total length for longitudinal bars= 300.00 m
number of bars (transverse)(6m length) 50.00 pcs
total length for transverse bars= 300.00 m
total length= 600.00 m
total mass= 372.00 kgs
production rate= 185.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.00 days

FORMWORKS FOR SLABS


perimeter= 41.60 m
thickness of slab= 0.12 m
area for formworks= 28.67 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 day

POURING OF CONCRETE FOR BEAM AND SLAB


area of slab= 59.47 m2
thickness of slab= 0.12 m2
volume for slab= 6.96 m3
area for beam= 0.12 m2
total length of beam= 56.70 m
volume for tie beam= 6.80 m3
total volume of concrete= 13.76 m3
production rate= 5.20 m3/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 2.00 day
THIRD FLOOR
INSTALLATION OF FORMWORKS FOR COLUMNS
perimeter= 1.80 m
height= 3.00 m
total surface area of columns= 54.00 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 5.00 days

INSTALLATION OF REBAR FOR COLUMNS


Number of main reinforcement for columns= 10.00 pcs
length for main reinforcement= 3.00 m
total length for each column= 30.00 m
total length for 10 columns= 300.00 m
mass for main reinforcement= 741.00 kgs
Number of ties for each column= 34.00 pcs
length of each stirrup= 1.08 m
total length for each column= 36.72 m
total length for 10 columns= 367.20 m
mass for stirrups= 227.66 kgs
TOTAL MASS OF REBAR FOR COLUMNS= 968.66 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days

POURING OF CONCRETE FOR COLUMNS


Area= 0.16 m2
height= 3.00 m
volume for 1 column= 0.48 m3
total volume for 10 columns= 4.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day

INSTALLATION OF REBAR FOR BEAMS


depth= 0.40 m
width= 0.30 m
length of main reinforcement= 6.00 m
number of main reinf. per beam= 83.00 pcs
total length of reinforcement of beam= 498.00 m
total mass for reinforcement= 786.84 kgs
length of each stirrup= 1.12 m
number of stirrups= 192.00 pcs
total length of stirrups= 215.04 m
total mass for stirrups= 133.32 kgs
TOTAL MASS OF REBAR FOR TIE BEAMS= 920.16 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days
INSTALLATION OF FORMWORKS FOR TIE BEAMS
perimeter of formworks= 2.30 m
total area for formworks= 28.67 m2
production rate= 1.50 m2/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 days

INSTALLATION OF SLAB ON GRADE


number of bars (longitudinal)(6m length) 50.00 pcs
total length for longitudinal bars= 300.00 m
number of bars (transverse)(6m length) 50.00 pcs
total length for transverse bars= 300.00 m
total length= 600.00 m
total mass= 372.00 kgs
production rate= 185.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.00 days

FORMWORKS FOR SLABS


perimeter= 41.60 m
thickness of slab= 0.12 m
area for formworks= 28.67 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 day

POURING OF CONCRETE FOR BEAM AND SLAB


area of slab= 59.47 m2
thickness of slab= 0.12 m2
volume for slab= 6.96 m3
area for beam= 0.12 m2
total length of beam= 56.70 m
volume for tie beam= 6.80 m3
total volume of concrete= 13.76 m3
production rate= 5.20 m3/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 2.00 day
FOURTH FLOOR
INSTALLATION OF FORMWORKS FOR COLUMNS
perimeter= 1.80 m
height= 3.00 m
total surface area of columns= 54.00 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 5.00 days

INSTALLATION OF REBAR FOR COLUMNS


Number of main reinforcement for columns= 10.00 pcs
length for main reinforcement= 3.00 m
total length for each column= 30.00 m
total length for 10 columns= 300.00 m
mass for main reinforcement= 741.00 kgs
Number of ties for each column= 34.00 pcs
length of each stirrup= 1.08 m
total length for each column= 36.72 m
total length for 10 columns= 367.20 m
mass for stirrups= 227.66 kgs
TOTAL MASS OF REBAR FOR COLUMNS= 968.66 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days

POURING OF CONCRETE FOR COLUMNS


Area= 0.16 m2
height= 3.00 m
volume for 1 column= 0.48 m3
total volume for 10 columns= 4.80 m3
production rate= 5.20 m3/day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 1.00 day

INSTALLATION OF REBAR FOR BEAMS


depth= 0.40 m
width= 0.30 m
length of main reinforcement= 6.00 m
number of main reinf. per beam= 83.00 pcs
total length of reinforcement of beam= 498.00 m
total mass for reinforcement= 786.84 kgs
length of each stirrup= 1.12 m
number of stirrups= 192.00 pcs
total length of stirrups= 215.04 m
total mass for stirrups= 133.32 kgs
TOTAL MASS OF REBAR FOR TIE BEAMS= 920.16 kgs
production rate= 225.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 5.00 days
INSTALLATION OF FORMWORKS FOR TIE BEAMS
perimeter of formworks= 2.30 m
total area for formworks= 28.67 m2
production rate= 1.50 m2/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 days

INSTALLATION OF SLAB ON GRADE


number of bars (longitudinal)(6m length) 50.00 pcs
total length for longitudinal bars= 300.00 m
number of bars (transverse)(6m length) 50.00 pcs
total length for transverse bars= 300.00 m
total length= 600.00 m
total mass= 372.00 kgs
production rate= 185.00 kgs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 3.00 days

FORMWORKS FOR SLABS


perimeter= 41.60 m
thickness of slab= 0.12 m
area for formworks= 28.67 m2
production rate= 1.50 sq.m/day
crew mix= 7.00
work schedule= 8.00 hrs/day
duration= 3.00 day

POURING OF CONCRETE FOR BEAM AND SLAB


area of slab= 59.47 m2
thickness of slab= 0.12 m2
volume for slab= 6.96 m3
area for beam= 0.12 m2
total length of beam= 56.70 m
volume for tie beam= 6.80 m3
total volume of concrete= 13.76 m3
production rate= 5.20 m3/day
crew mix= 8.00
work schedule= 8.00 hrs/day
duration= 2.00 day
MASONRY WORKS WITH PLASTERING
height= 3.00 m
area to be installed of CHB= 604.38 m2
no of CHB/m2= 13.00 pcs
total number of CHB to be installed= 7554.75 pcs
production rate= 250.00 pcs/day
crew mix= 8.00
work schedule= 8.00 hrs/day
Total duration= 31.00 days

FINISHING WORKS
area to be layouted by tiles= 410.51 m2
production rate= 4.75 sq.m/man-day
crew mix= 6.00
work schedule= 8.00 hrs/day
duration= 15.00 days