Bank of East Asia V Tsien Wui Marble (FACV No. 21 of 1998)
Bank of East Asia V Tsien Wui Marble (FACV No. 21 of 1998)
21 of 1998
Between:
- and -
- and -
REMO RIVA
JAMES HAJIME KINOSHITA Third
Parties
HEINZ ARTHUR RUST
_____________________
JUDGMENT
Introduction
This case concerns the granite cladding to the new Bank of East
Asia head-quarters building at Des Voeux Road Central. The
development was completed at the beginning of 1983. The building
consists of a tower block 23-storeys high, standing on a podium of 5
storeys. The architects and structural engineers for the project were
Messrs. Palmer and Turner (“Palmer & Turner”) and the nominated
sub-contractors for the cladding were Tsien Wui Marble Factory Ltd
(“TW”).
Two factors render this a difficult case for this Court: (1) At trial,
because of admissions made on behalf of Palmer & Turner, the tort of
negligence was assumed to have been established; the ingredients
constituting the cause of action were not explored in depth in the courts
- 3 -
The Bank’s case against Palmer & Turner was, and is now, in
negligence alone, counsel for the Bank having conceded at trial that the
contractual claim was time-barred. Further, it was admitted at trial by
Palmer & Turner that they were in breach of their duty of care to the
Bank. The terms of their admissions will need examination later.
Subject to the defence based upon the Limitation Ordinance, Cap. 347, it
was conceded by Palmer & Turner that they were liable to the Bank for
damages; these were assessed by the trial judge in the sum of
$38,502,951.85. The history of this piece of litigation is fully set out in
Mr Justice Ching PJ’s judgment and needs no repetition.
Before this Court, the entire focus of the case, as far as Palmer
& Turner are concerned, is on the meaning of the words the date on
which the cause of action accrued as they appear in the relevant
provisions of the Limitation Ordinance. As the decision on this issue is
also relevant to TW it would be convenient to deal with the case against
Palmer & Turner first.
courts would obviously follow the way the English courts have
interpreted and applied the equivalent provisions of the English Acts,
there being no circumstances relevant to the two different jurisdictions
which might indicate that our courts could or should come to a different
conclusion, when the same words are being construed.
The key provision, for the purposes of this case, is section 4(1).
This is in terms identical to section 2(1) of the Limitation Act 1939. As
relevant it reads:
“(1) The following actions shall not be brought after the expiration of 6
years from the date on which the cause of action accrued, that is to say―
(a) actions founded on simple contract or on tort ….”
action ought not to be held to accrue until either the injured person has
discovered the injury or it would be possible for him to discover it if he
took such steps as were reasonable in the circumstances. The common
law ought never to produce a wholly unreasonable result, nor ought
existing authorities to be read so literally as to produce such a result in
circumstances never contemplated when they were decided.”
Pirelli
The next important event, which ultimately led the Hong Kong
legislature to enact sections 31 & 32 of the Limitation Ordinance, was the
decision of the House of Lords in Pirelli General Cable Works Ltd v.
Oscar Faber & Partners [1983] 2 AC 1. There, factory owners had
engaged consulting engineers to design a chimney for their factory. The
specification regarding the material for the inner lining of the chimney
was defective. The lining cracked under the impact of hot flue gases but
this went undetected. By the time the outer casing had also cracked for
the same reason and the damage was discovered, over 7 years had elapsed.
The House of Lords held, reversing the lower courts, that the cause of
action in tort accrued when the physical damage occurred, not when the
damage was discovered or should, with reasonable diligence, have been
discoverable. As the cause of action had accrued long before the crack
in the outer casing was discovered – and therefore even longer before the
proceedings were instituted – s.2(1) of the Limitation Act applied and the
action was time-barred.
“It seems to me that there is a true analogy between a plaintiff whose body
has, unknown to him, suffered injury by inhaling particles of dust and a
plaintiff whose house has unknown to him sustained injury because it was
built with inadequate foundations or of unsuitable materials ….”
“Section 31(1) This section applies to any action for damages for
negligence … where the earliest date on which the plaintiff or any person
in whom the cause of action was vested before him first had both―
(a) the knowledge required for bringing an action for damages
in respect of the relevant damage; and
(b) a right to bring the action,
(referred to in this section as the “date of knowledge”) falls after the date
on which the cause of action accrued.
(3) An action to which this section applies shall not be brought after
the expiration of the period applicable in accordance with subsection (4).
- 9 -
(6) …
“Cause of action”
What, then, was the Bank required to prove as against Palmer &
Turner to obtain judgment against them? Before the trial judge counsel
for Palmer & Turner made admissions in the following terms:
(i) Palmer and Turner owed the Bank a duty of care as alleged by it;
(ii) given the nature of the relationship between the Bank and Palmer
and Turner, their duty of care extended to not committing acts or
omissions which caused economic loss;
(iii) they knew or ought to have known that the damages and defects
pleaded might constitute a danger of physical injury to persons or
physical damage to properties in the vicinity of the bank building;
- 11 -
(iv) they knew or ought to have known that the damage might expose
the Bank to liability to third parties;
(v) they knew or ought to have known that the damage would require
remedial works;
(vii) Palmer and Turner breached its duty of care to the Bank to produce
or procure the design of a fixing system for the cladding that
provided adequately for the differential movement between the
cladding and the reinforced concrete structure of the Building; and
(viii) (subject to the defences and issues mentioned below) they are liable
to compensate the Bank for the costs of such method of remedying
the Damage as the Court should find was appropriate.
“In the varied web of affairs, the law must abstract some consequences as
relevant, not perhaps on grounds of pure logic but simply for practical
reasons.”
In summary, the judge found that it was the faulty design of the
cladding system which led eventually to the physical damage to the
granite slabs. When serious spalling and cracking started to appear, and
- 13 -
The view of the experts is that physical damage to the cladding system
started to occur within the first few years after 1982. From then, over the
years, the physical damage got worse until, at some uncertain time, risk of
injury to the public was unacceptable. There was a risk of whole panels
becoming dislodged. I accept this evidence. There is some evidence
that marks on the surface of the granite panels could be seen in 1984 and
1985, and one of these marks coincides in place with where damage was
later seen.
It was not until about June 1993 that the Bank became aware of
the possibility of serious defects in the cladding. A memorandum of the
Bank’s new property managers Messrs. Jones Lang Wootton dated
23 June 1993 made the following points:
(iv) The problem was not related to the Mass Transit Railway works in
the vicinity of the Bank building in the 1980s.
and sufficiently to have caused vertical cracking of the stone and scaling of
the surface of the stone.”
(i) The design failed to provide for the differential vertical movement
between the granite cladding and the reinforced concrete structure.
(ii) There were too few compression joints, and these were too narrow:
In particular the design failed to provide for compression joints of a
minimum width of 13 mm at every storey height in order to comply
with CP298:1972 (British Standard Code of Practice 298:1972
edition).
“The evidence leads me to believe that it was not until about the middle of
1993 that the defects were so obvious that any reasonable person would
have called in an expert, and, having done so, would have been aware of
defects and realised that a loss had been suffered. It is impossible to be
precise about when, on this basis, it can be said that the cause of action
accrued. It cannot be at the moment in time when the owner decides to
call in the expert. There must be a reasonable time gap to enable the
expert to examine the building and report his findings on the cause and
extent of the defects. It is only then that it can be said that what is
- 16 -
suspected is verified, and this ‘marks the moment when the market value
of the building is depreciated, and therefore the moment when the
economic loss occurs’.”
Evidently, the Judge below considered that the defects in the design
were such that physical damage was likely to be brought about. On this
basis, I consider that the point of time at which the Plaintiff suffered
economic loss by reason of the defective design was the date when it
acquired and paid for the building with the defective design. For the
purposes of this case I take that to be the date of practical completion
namely 7th March 1983.”
- 19 -
Mayo JA said that one of the core issues was whether the court
should “continue to follow United Kingdom law in limitation or whether
it should develop along similar lines to Commonwealth countries such as
New Zealand, Australia and Canada”. It is not clear what Mayo JA
meant by “United Kingdom law on limitation”, for there has been much
upheaval in the United Kingdom in this area of the law in recent years:
Cooke P’s judgment in the New Zealand Court of Appeal in Invercargill
[1994] 3 NZLR 513 at 519 line 35 to 522 line 5 gives a clear review of
this development.
Here, Palmer & Turner accepted at trial that the plan they passed
was “defective” in that it failed to provide adequately for the differential
movement between the cladding and the structure of the building: See
paragraph (vii) of the admissions referred to earlier. This led eventually
to the spalling and cracking of some of the slabs, exposing the Bank to
the risk of endangering others. Formulated in this way, the physical
damage was an ingredient of the cause of action against the architects.
What the Court of Appeal accepted was something quite radical in this
field of law: The court should unhook the ingredient of physical damage
from the cause of action, viewing the case as one of pure economic loss.
The difficulty facing the Court of Appeal was this: Both parties were
urging this radical approach with opposing results. The defendants
submitted that, adopting this approach, the cause of action accrued the
moment the Bank acted upon the “advice” of the architects (in 1982),
whilst the plaintiff urged that it accrued when diminution in the market
value of the building was reasonably discoverable (in 1993).
The notion that the discipline of law might have required the
court to have regard to the statutory scheme governing limitation periods
- 21 -
First principles
however recognized that if the builder was not liable for damages for
negligence in building the house, the council could not be liable for
passing the bad work. So Dutton involved more than the council’s
liability for breach of bye-laws, and extended the scope of Donoghue v.
Stevenson to cover economic loss flowing from structural damage to the
house.
“If the latent defect causes actual physical damage to the structure of the
house then I can see no reason in principle why such damage should not
give rise to a cause of action ….” (emphasis added).
“In the present case the claim is not for a purely economic loss. Instead,
the evidence demonstrates, first, that the defect referable to the foundations
caused actual physical damage to the building; and, second, that the
element of depreciation in the claim by [the plaintiffs] is an associated
effect of that damage.”
independent contractor who failed to spot the errors in the design. The
trial judge found that the extensive damage to the walls and pipes caused
by subsidence posed an imminent danger to the safety and health of the
plaintiff and, following Anns, awarded damages of £35,000, being the
diminution in the market value of the house. On appeal the Court of
Appeal took it for granted that the cause of action was based on the
“ordinary common law duty of care” (see p.408-G). The question was
whether the council was under a duty to avoid pure economic loss
suffered by the house owner who had bought it from the builders. The
Court of Appeal, following Anns, upheld the judge. In the House of
Lords the council’s appeal was allowed: The House applied the practice
statement of 1966 (Practice Statement (Judicial Precedent) [1966] 1
WLR 1234) and departed from Anns: If liability is to be cast upon
builders for the economic loss suffered by subsequent owners (with
whom they have no contractual relationship) as a result of their negligent
acts, this could only proceed along the Hedley Byrne principle of reliance.
“Defects in a building are physical defects and the cost of their rectification
is consequential on their existence….”
From what is said above, it can be seen that when Mayo JA said
he was continuing to follow United Kingdom law on limitation, rather
than Canadian or Australian law, he was in fact turning his face against
the orthodox English view as established by Pirelli and Ketteman and was
embarking on a new adventure, following the lead indicated by Lord
Keith’s dictum in Murphy at p.466D-G. There is no established
authority in support of this approach. The Canadian and Australian
authorities reject the Murphy approach, treating Anns (which looks to
physical damage resulting in imminent danger to health and safety) as
good law.
- 30 -
damage. He did not follow Pirelli, saying that Pirelli had been
“re-interpreted” by Murphy and by Invercargill, and held that the date for
the accrual of the cause of action was not, as the House of Lords had held
in Pirelli, when physical damage first occurred but only when “the
defects [were] so obvious that any reasonable person would have called
in an expert and, having done so, would have been aware of defects and
realised that a loss had been suffered”.
In reversing the trial judge the Court of Appeal held that the
Bank’s cause of action for economic loss accrued when “the construction
of the building was completed” (per Mayo JA) or when the Bank
“acquired and paid for the building with the defective design” (per
Rogers JA). Leong JA agreed with both, but gave no reasoned judgment
of his own. Because of this approach, the Court of Appeal in its turn did
not fully consider the evidence as to when physical damage first occurred.
Rogers JA said:
That was, in effect, the sum total of the evidence, bearing upon
the time issue, considered by Rogers JA. His conclusion, concurred in
by Leong JA, was as follows:
essential finding. It marks the time when the cause of action first
accrued on Pirelli principles.
Alternative dates
to fail. The trial judge was criticized by the Court of Appeal for
concentrating on physical damage to the building rather than the
economic loss to the Bank caused by the defective design. But the
reality on the ground reflects the judge’s approach. There was evidence
to the effect that a slab had to be replaced in 1991, another in 1992. Had
an expert been brought in then, he would have seen that something was
seriously amiss. But that was some 8 or 9 years after the completion of
the building. Any suggestion that the Bank had, in 1982 when the
building was first completed, incurred serious economic loss running into
tens of millions of dollars would have been dismissed as absurd.
Rogers JA, it will be recalled, did not think that the cladding was
“doomed to failure” from the very beginning. When the problems really
first emerged some ten years later the focus of every professional person
concerned – Jones Lang Wootton the property managers, Mr Douglas
Collins director of P&T Architects and Engineers Ltd, CDC Inc.
consultants to TW, Binnie Consultants Ltd acting for the Bank – was on
the cladding and not the drawings. In a report to TW dated 7 October
1993 CDC Inc. said that they had not seen any “design or as-built
drawings”, and yet they considered themselves in a position to render
professional advice. It is therefore not surprising that the judge’s focus
should have been on the physical damage: the cracking and spalling of
the granite slabs: this was the matter of concern to the parties and this
eventually led to the entire cladding being replaced.
Further, this point needs emphasis: The case against Palmer &
Turner proceeded on admissions: It was admitted that the architects knew
or ought to have known that the defects as pleaded might constitute
danger of physical injury to persons or properties in the vicinity of the
Bank building. The duty owed to the Bank, as admitted by them, was a
- 35 -
There was yet another factor. The stainless steel hooks which
secured the granite slabs to the reinforced concrete structure were not
wholly recessed into the slabs but intruded into the space between the
slabs, thus prevented the slabs from moving within the expansion joints
by the designed amount. There were no contemporaneous drawings
produced at the trial showing such a design for the mountings: It is not
clear from Rogers JA’s judgment, when he referred to the “purchaser”
inspecting the drawings, what precise drawings he had in mind. The
fact that parts of the steel hooks intruded into the space between the slabs
was, of course, not apparent: This was hidden by the mastic which sealed
the joints.
- 37 -
CP 298
It seems possible that the cladding panels would not have experienced the
observed degree of cracking and distress if only one or two of the
variations from the code listed above were present. However, it seems
that the combination of all four variations placed too severe a strain on the
- 38 -
(a) The differential movements between the cladding and the structure
due to drying shrinkage and creep;
What is set out above is, in effect, the sum total of the evidence
bearing upon the question as to when real and substantial damage to the
cladding first occurred. The only safe thing to say about this evidence is
that it is inconclusive as regards the question when the damage to the
cladding first occurred. Rogers JA said it was more than 6 years before
1 July 1991. Leong JA agreed with him. Mayo JA made no finding.
- 42 -
But, as has been mentioned earlier, the evidential basis for Rogers JA’s
finding was somewhat meagre. In my judgment the evidence showed no
more than that the first damage occurred round about the time indicated
in Rogers JA’s judgment, and if the burden of proof fell on the plaintiff to
show that it occurred after 1 July 1985, then the Bank fails on Pirelli
principles. It is, perhaps, of some significance that after the limitation
issue was raised in the Defence, the Bank did not assert a date for the first
physical damage in its Reply.
Burden of proof
At first sight the argument that the defendant carries that burden
is attractive: It is for a plaintiff to plead and prove the elements of his
cause of action; if the accruing of the cause of action in time is no part of
the cause of action, the plaintiff need not allege or prove it. The Bank
relies for this proposition on the judgment of the Victorian Full Court in
Pullen v. Gutteridge [1993] 1 VR 27. But, as I see it, this argument
misses the essential point of the statutory scheme for the limitation of
actions, which is to prevent stale claims from being brought.
your pecuniary loss has occurred quite recently, say, less than 6 years
before you issued your writ, you prove it. The matter is well put in
McGee’s Limitation Periods (3rd ed.) p.349:
“Unless the defect is very gross, it may never lead to any damage at all to
the building.”
“Counsel for the appellants submitted that the fault of his clients in
advising on the design of the chimney was analogous to that of a solicitor
who gives negligent advice on law, which results in the client suffering
damage and a right of action accruing when the client acts on the advice ….
It is not necessary for the present purpose to decide whether that
submission is well founded, but as at present advised, I do not think it is.”
where the plaintiff’s claim is for economic loss, the cause of action
accrues when the physical damage becomes apparent to a reasonable
claimant; powerful support, Mr Mauleverer argues, is to be found for this
proposition in Invercargill where the Privy Council (following Murphy at
p.467-468) adopted a passage in Deane J’s judgment in Sutherland Shire
Council v. Heyman (1985) 157 CLR 424 at 503-505. There the High
Court of Australia was dealing with a case of damage to a house from
inadequate footings; at p.503 Deane J said that the plaintiffs’ claim as
crystallised was not in respect of damage to the fabric of the house or to
other property caused by collapse or subsidence of the house, it was for
“the loss … represented by the actual inadequacy of the foundations, that
is to say … for the cost of remedying a structural defect in their property
which already existed at the time when they acquired it …”. Deane J
then looked at two possibilities for determining when the cause of action
accrued: (i) when the plaintiffs acquired the house, paying a higher price
in ignorance of the inadequacy of the foundations, thus in effect suffering
a loss or detriment at that time or (ii) when the inadequacy of the
foundations were first known or manifest. Deane J considered the latter
appropriate: only then did economic loss in the form of actual diminution
of the market value of the house occur. In adopting this approach Lord
Lloyd of Berwick in Invercargill said (at p.648-F):
“the cause of action accrues when the cracks become so bad, or the defects
so obvious, that any reasonable homeowner would call in an expert.
Since the defects would then be obvious to a potential buyer, or his expert,
that marks the moment when the market value of the building is
depreciated, and therefore the moment when the economic loss occurs.
Their Lordships do not think it is possible to define the moment more
accurately. The measure of the loss will then be the cost of repairs, if it is
reasonable to repair, or the depreciation in the market value if it is not: see
Ruxley Electronics and Construction Ltd. v. Forsyth [1996] 1 A.C. 344.”
- 47 -
Governing principles
of the Limitation Ordinance: (i) time runs against the claimant from the
date when his cause of action accrues; (ii) his cause of action accrues
when he suffers damage (in a real and substantial sense, more than what
might be regarded as negligible) arising from the defendant’s negligence.
This applies right across the board.
(i) The time when the Bank relied upon the professional
services rendered by Palmer & Turner in relation to the
design: What Mr Thomas calls an action for “modern
negligence without physical damage of the Hedley Byrne
kind”;
time: Even though in the negligent solicitors and valuers type of case this
generally happens. Upon the (unusual) facts of this case, it did not
happen here.
“But the mere fact that an enactment shows that Parliament must have
thought that the law was one thing does not preclude the courts from
deciding that the law was in fact something different.”
- 50 -
Invercargill
tort against TW. The action was already time-barred when the 1991
amendments came into effect. For the sake of completeness, I would
deal briefly with the point on which the judge found in favour of TW
(affirmed by the Court of Appeal) that the design of the cladding was
done by Mr Ragaglini as an independent contractor and TW was not in
law liable for his failure.
“I am left in no doubt at all that under the contract the parties contemplated
that TW would be responsible for designing the system of fixing the
granite panels to the concrete, and that this system included making proper
allowance for movement.”
against TW was time-barred when the writ against TW was issued in June
1994.
Conclusion
Some years ago The Bank of East Asia Limited redeveloped its
head office into a building of 23 stories. It has what is known as a dry
hung granite cladding. Large panels of it were mounted on anchors
which were in turn attached to the building. The sub-contract for the
design of the system and for the execution of the work was let to Tsien
Wui Marble Factory Limited. Payments were to be made by stages
upon certification by the architects. Tsien Wui submitted their first
invoice in August 1981 which appears to have been paid sometime before
21 November 1981. The architects and structural engineers for the
redevelopment as a whole were Palmer & Turner who passed the plans
produced by Tsien Wui. The cladding was completed in July 1982.
The occupation permit was issued in November 1982 and the building as
a whole was completed in March 1983 but the completion of the building
and the issue of the occupation permit does not appear to have any
relevance to the date of completion of the cladding. The cladding failed
- 58 -
“The successful Tenderer will be expected to guarantee the fixing for the
life of the building bearing in mind the typhoon conditions in Hong Kong.”
The claim in negligence against Palmer & Turner was that they
had negligently passed the plans for the cladding. Various admissions
were made by them at trial. They were,
“(i) Palmer and Turner owed the Bank a duty of care as alleged by it;
(ii) given the nature of the relationship between the Bank and Palmer
and Turner, their duty of care extended to not committing acts or
omissions which caused economic loss;
(iii) they knew or ought to have known that the damage and defects
pleaded might constitute a danger of physical injury to persons or
physical damage to properties in the vicinity of the bank building;
(iv) they knew or ought to have known that the damage might expose
the Bank to liability to third parties;
(v) they knew or ought to have known that the damage would require
remedial works;
(vii) Palmer & Turner breached its duty of care to the Bank to produce
or procure the design of a fixing system for the cladding that
provided adequately for the differential movement between the
- 60 -
(viii) (subject to the defences and issues mentioned below) they are liable
to compensate the Bank for the costs of such method of remedying
the Damage as the Court should find was appropriate.”
“The following actions shall not be brought after the expiration of 6 years
from the date on which the cause of action accrued, that is to say –
(a) actions founded on simple contract or on tort.”
The Court of Appeal held that the burden is in fact on the plaintiff and I
agree. A plaintiff need not plead in the Statement of Claim that the
action has been brought within time. That would be to jump the stile
before coming to it. Once the matter has been raised in the Defence,
however, the burden is on the plaintiff although the evidential burden may
change from time to time in the course of the trial. See Cartledge v. E.
Jopling & Sons Ltd [1963] AC 758 at 784, London Congregational Union
v. Harriss [1988] 1 AER 15 and most recently Crocker v. British Coal
Corporation [1995] 29 BMLR 159. In the present case the point was
taken in the Defences but the Reply contented itself with a denial without
- 62 -
any particulars as to when the cause of action was said to have accrued.
It may be that in the Courts below this omission caused or contributed to
some lack of focus on the damage necessary to perfect the cause of action
in tort and the date upon which such damage occurred.
“The Courts have expressed at least three differing reasons supporting the
existence of statutes of limitation, namely (1) that long dormant claims
have more of cruelty than justice in them; (2) that a defendant might have
lost the evidence to disprove a stale claim; and (3) that persons with good
causes of action should pursue them with reasonable diligence.”
“In the great majority of cases these rules work well, because the claimant
knows of his injury or damage at about the time he suffers it, and if he does
- 63 -
not take action within the generous time limits provided he has only
himself to blame.”
begins to run from the accrual of the cause of action in respect of the first
conversion. In R.B. Policies at Lloyd’s v. Butler [1950] 1 KB 76 a motor
car was stolen by an unidentified thief and was then sold to an innocent
purchaser. The plaintiff’s claim against the purchaser would have
seemed to be irresistible but more than six years had elapsed since the
theft. The fact that the plaintiff could not have taken proceedings
against an unknown thief did not assist him. The action was held to be
time barred. In Cartledge v. Jopling the plaintiffs had contracted
pneumoconiosis. It was held that the cause of action accrued when
more than negligible damage had been suffered even though the plaintiffs
did not know and could not have known of it. However hard these cases
may be, it is not for the Courts effectively to allow extensions when the
legislature has not done so. To borrow the words of Sir Thomas
Bingham MR in Spencer-Ward v. Humberts (unreported, English Court of
Appeal, 6 July 1994) said in another connection,
1886 the House of Lords decided the appeal in The Darley Main Colliery
Company v. Mitchell [1886] 11 App. Cas. 127. There the mining
operations of the lessees of coal had caused subsidence under the
plaintiff’s land. Compensation was paid and the lessees ceased their
operations. Years later further works by others on land adjoining that of
the lessees caused a further subsidence which would not have occurred
but for the previous removal of support. It was held that the second
subsidence created a fresh cause of action so that the action was within
time. In the course of his speech Lord Halsbury said at page 132,
“A house that has received a shock may not at once shew all the damage
done to it, but it is damaged none the less then to the extent that it is
damaged, and the fact that the damage only manifests itself later on by
stages does not alter the fact that the damage is there; and so of the more
complex mechanism of the human frame, the damage is done in a railway
accident, the whole machinery is injured, though it may escape the eye or
even the consciousness of the sufferer at the time; the later stages of
suffering are but the manifestations of the original damage done, and
consequent upon the injury originally sustained.”
“The cause of action accrued when it” that is to say the damage “reached a
stage, whether then known or unknown, at which a judge could properly
give damages for the harm that had been done.”
the time, the only impediment in the Limitation Act which compelled
them to hold that discovery or discoverability was irrelevant was section
26 of the Act which is in the same terms as section 26 of the Ordinance.
That section provides that where (1) the action is based upon the fraud of
the defendant or (2) any fact relevant to the plaintiff’s right of action has
been deliberately concealed from him by the defendant or (3) the action is
for relief from the consequences of a mistake, time does not begin to run
until the plaintiff has discovered or could with reasonable diligence have
discovered the fraud, concealment or mistake as the case may be. The
section proceeds upon the assumption that a cause of action has in fact
accrued even though the plaintiff is ignorant of it and could not
reasonably have discovered the necessary facts. It does not postpone the
date of accrual of the cause of action. In appropriate circumstances it
simply postpones the date from which time is to run.
“But the present question depends on statute, the Limitation Act, 1939,
and section 26 of that Act appears to me to make it impossible to reach the
result which I have indicated. That section makes special provisions
where fraud or mistake is involved: it provides that time shall not begin to
run until the fraud has been or could with reasonable diligence have been
discovered. Fraud here has been given a wide interpretation, but
obviously it could not be extended to cover this case. The necessary
implication from that section is that, where fraud or mistake is not
involved, time begins to run whether or not the damage could be
discovered.”
- 67 -
“To postpone the date in such a case as the present would, in my opinion,
necessarily require the insertion of some words qualifying the statutory
formula. My Lords, the well-established principles of the interpretation
of statutes by the courts of this country forbid such an insertion; and more
particularly so having regard to the express provision in section 26 of the
same Act for postponing the date of the accrual of the cause of action in
cases involving fraud or mistake to the date when the fraud or mistake was,
or could with reasonable diligence, have been discovered.”
“Nor can his knowledge of the state of his lungs be the deciding factor. It
would be impossible to hold that while the X-ray photographs are being
taken he cannot yet have suffered any damage to his body, but that
immediately the result of them is told to him, he has from that moment
suffered damage.”
Once relevant damage has been sustained, one of the necessary elements
of an action in tort exists. The discovery, or discoverability, of it does
not cause or amount to damage. It does neither more nor less than to
provide the evidence for the plaintiff to prove his damage or the extent of
it. Absent legislation, ignorance of the damage or the inability to
discover it cannot assist any more than ignorance of or the inability to
discover the identity of a tortfeasor can assist. It was aptly put by
Mr Recorder Moxon-Browne QC in Western Challenge Housing Ltd v.
Percy Thomas Partnership and Others [1995] Construction Industry Law
- 68 -
Provisions are then made to ascertain the date of knowledge. The whole
section is made subject to section 30 which gives the Court a discretion to
extend the time in certain circumstances. Section 32, which provides a
long-stop of 15 years, applies to all actions in negligence except for those
within section 27. The section and section 30 apply only to cases of
personal injury. These sections therefore have no application to cases of
pure economic loss or to damage caused to buildings. Section 27 did
not purport to overturn the ratio decidendi of Cartledge v. Jopling.
Subsection (2) removes the application of section 4(a) but section 27(4)(a)
provides that time begins to run from the date of the accrual of the cause
of action while cutting down the period from six to three years.
Cartledge v. Jopling was therefore not reversed by the section insofar as
the date of accrual of the action was concerned. Subsection (4)(b) then
provides, in effect, an extension of a further three years from the date of
the plaintiff’s knowledge if that date is later than the date of accrual of the
- 69 -
“Special time limit for negligence actions where facts relevant to cause of
action are not known at date of accrual.”
“… where the earliest date on which the plaintiff … first had both –
(a) the knowledge required for bringing an action for damages in
respect of the relevant damage; and
(b) a right to bring such an action
… falls after the date on which the cause of action accrued.”
Subsections (5), (6) and (7) deal with ‘the knowledge required for
bringing an action for damages in respect of the relevant damage’ and
subsections (3) and (4) provide that no action to which section 31 applies
shall be brought after a period of either
“(a) 6 years from the date on which the cause of action accrued; or
(b) 3 years from the date of knowledge, if that period expires later than
the period mentioned in paragraph (a).”
- 71 -
Again, section 31 did not reverse the decision in Pirelli so far as the date
of the accrual of the cause of action was concerned. Section 38A(2)
contains transitional provisions which, so far as is relevant, provide that
nothing in section 31 is to affect any action commenced before 1 July
1991 (subsection (2)(a)), or to enable any action which was barred by the
Ordinance before that date to be brought (subsection (2)(b)). Otherwise
section 31 is to have effect in relation to causes of action accruing both on
or after that date. Section 31 therefore has no application in the present
case if the Bank’s cause of action was time barred before 1 July 1991, but
its existence and the existence of sections 26 and 27 and their provisions
must clearly be taken into account in construing section 4(1)(a) just as the
existence and provisions of section 26 had to be taken into account by the
House of Lords in Cartledge v. Jopling and the existence and provisions
of sections 26 and 27 had to be taken into account in Pirelli.
insisted that that was the relevant date at which compensation was to be
assessed. The Corporation insisted on the date of the notice to treat and
called in aid subsequent Acts which clearly proceeded upon that basis by
providing for a period after the date of the notice to treat as being the
relevant period for assessment. In relation to those subsequent Acts,
Lord Reid said at page 898,
“These provisions do show that Parliament (or the draftsman) must have
thought the law was that compensation was assessable on the basis of the
value as at the date of the notice to treat. But the mere fact that an
enactment shows that Parliament must have thought that the law was one
thing does not preclude the courts from deciding that the law was in fact
something different …. No doubt the position would be different if the
provisions of the enactment were such that they were only workable if the
law was as Parliament supposed it to be. But, in my view, all that can be
said here is that these enactments would have a narrower scope if the law
was found to be that compensation must be assessed at a later date than
that of the notice to treat. I do not think that that is sufficient to preclude
your Lordships from re-examining the whole matter.” (Emphasis
supplied)
In De Lasala v. De Lasala [1979] HKLR 214 the appeal was to the Privy
Council from Hong Kong on a question of the interpretation of an
Ordinance relating to matrimonial finance. With an exception irrelevant
to the appeal the wording of the sections in that Ordinance was identical
to that of the sections of the Statute in England. A short while before the
hearing the House of Lords had decided precisely the same point in
Minton v. Minton [1979] 2 WLR 31. In giving the advice of the Board,
Lord Diplock referred to the common membership between the Board
and the House of Lords and said that the Board would be unlikely to
diverge from a decision in its alternate capacity. He referred to Trimble
v. Hill, Robins and others and then said at page 220,
“Different considerations, in their Lordships’ view, apply to decisions of
the House of Lords on the interpretation of recent legislation that is
common to Hong Kong and England. Here there is no question of
divergent development of the law. The legislature in Hong Kong has
chosen to develop that branch of the law on the same lines as it has been
- 74 -
developed in England, and, for that purpose, to adopt the same legislation
as is in force in England and falls to be interpreted according to the English
canons of construction. What their Lordships have already said about the
common membership of the Judicial Committee of the Privy Council and
the Appellate Committee of the House of Lords applies a fortiori to the
decisions of the House of Lords on the interpretation of recent English
statutes that have been adopted as the Law of Hong Kong. Since the
House of Lords as such is not a constituent part of the judicial system of
Hong Kong it may be that in juristic theory it would be more correct to say
that the authority of its decision on any question of law, even the
interpretation of recent common legislation, can be persuasive only : but
looked at realistically its decisions on such a question will have the same
practical effect as if they were strictly binding, and courts in Hong Kong
would be well advised to treat them as being so.”
This must be right. It cannot be right that the binding nature or the
correctness of a decision so far as Hong Kong as a Colony was concerned
should depend upon the accident of whether the appeal was contested in
the House of Lords or in the Privy Council when there were no local
circumstances which required that a decision of the House of Lords must
be disapplied here.
“It is regrettable that there should be any divergence between English and
New Zealand Law on a point of fundamental principle. Whether the
Pirelli case … should still be regarded as good law in England is not for
their Lordships to say. What is clear is that it is not good law in New
Zealand.”
the best solution or a solution better than that laid down by the House of
Lords, at least when that solution runs contrary to logic and to other
provisions in the relevant Ordinance.
“… the cause of action accrues when the cracks become so bad, or the
defects so obvious, that any reasonable homeowner would call in an expert.
Since the defects would then be so obvious to a potential buyer, or his
expert, that marks the moment when the economic loss occurs. Their
Lordships do not think it is possible to define the moment more accurately.
The measure of the loss will then be the cost of repairs if it is reasonable to
repair, or the depreciation in the market value if it is not; see Ruxley
Electronics and Construction Ltd v. Forsyth [1996] 1 AC 344.
I would not be so bold as to say that this is not the law in New Zealand.
Having regard to the fact that the decision was one in the Privy Council
on appeal from that jurisdiction, it clearly is. I do say that it is not and
cannot be the law in either Hong Kong or England for reasons I have
already given. It is as contrary to the logic of and the decision in
- 77 -
by whom a defect must be known before it can be said that the market
value of a building has been depreciated. The vast majority of people in
Hong Kong live in flats between which and commercial or other
buildings no distinction is made in this respect by legislation. Flats are
usually sold “as is” with questions being raised only as to such matters as
title and encumbrances. Surveys are not usually performed. An owner
who knows of a serious latent defect and who sells “as is” without
disclosing it would therefore not be caught by the provisions of section 26.
On the other hand, in the unlikely event of a purchaser obtaining a survey
report which discloses the defect the purchaser would very likely simply
break off negotiations without telling the vendor why. The market value
would then have been depreciated so far as that prospective purchaser is
concerned, without the knowledge of the owner. Quite apart from this in
the case of a house, damage may be discovered accidentally such as when
a workman goes into the upper spaces of a house and notices serious
cracking. Whether he chooses to say anything or not about this
fortuitous discovery presents a lottery upon a lottery. A question then
also arises as to the qualifications of any person who should, by chance or
design, have noticed any damage or defect. In the present case, a
member of the management company, Hong Kong Land, drew up a report
in 1989. Findlay J found that the contents of that report were, if
anything, reassuring. No doubt the author of the report found nothing
alarming, but he was not a cladding expert. By contrast the
overwhelming preponderance of the evidence of the cladding experts was
that an expert would have recognised that that damage required further
investigation. This evidence immediately takes the case out of the ambit
of Invercargill where the damage by way of defects was undiscovered.
More importantly, however, it does not seem right that the accrual of a
cause of action should depend upon whether the damage is seen and
- 79 -
“The laws previously in force in Hong Kong, that is, the common law,
rules of equity, ordinances, subordinate legislation and customary law shall
be maintained, except for any that contravene this law, and subject to any
amendment by the legislature of the Hong Kong Special Administrative
Region.”
inspector, and thereby the council, owed a duty to the plaintiff. Thirdly,
we are not concerned with cases of subsequent purchasers. The sole
question with which we are concerned is the date at which any relevant
damage occurred. That, however, means that we must first decide what
damage is relevant. It would be impossible to deal with all of the cases
which have been decided in England or, indeed, in other common law
jurisdictions. To attempt to do so would be to burden this already
over-lengthy judgment to an intolerable degree. Nevertheless a brief
review of the major decisions is necessary. I shall deal chronologically
with the decisions relating to the application of Donoghue v. Stevenson
[1932] AC 562 and of Hedley Byrne & Co. Ltd v. Heller & Partners Ltd
[1964] AC 465 and the question of the relevance of physical damage
when the claim is one for pure economic loss.
“That is a very important decision, but I do not think that it has any direct
bearing on this case. That decision may encourage us to develop existing
lines of authority, but it cannot entitle us to disregard them. Apart
altogether from authority, I would think that the law must treat negligent
words differently from negligent acts.”
“In logic I can see no essential reason for distinguishing injury which is
caused by a reliance upon words from injury which is caused by a reliance
upon the safety of the staging to a ship or by a reliance upon the safety for
use of the contents of a bottle of hair wash or a bottle of some consumable
liquid.”
In the end all of their Lordships agreed that, as the headnote accurately
states,
See also Yuen Kun Yeu v. A.G. of Hong Kong [1988] 1 AC 175. I may
add here that some argument was advanced before us to the effect that in
the presence of a contract no separate tortious duty of care can exist.
The overwhelming preponderance of authority is, quite rightly, contrary
to this.
- 82 -
“ I think that the main conclusions to be drawn from the cases is that
whether a cause of action is for personal or physical damage or for
financial or other economic loss it arises when damage is suffered and not
when the damage is discovered. When damage is suffered is always a
- 83 -
question of fact.
Diplock LJ decided the case on the basis that the claim was founded in
contract alone. However obiter the passage cited above may have been,
it is of interest especially when Cartledge v. Jopling and Hedley Byrne
were cited in argument. Donoghue v. Stevenson was not cited.
Dorset Yacht Co. Ltd v. Home Office [1970] AC 1004 dealt with
the question of whether the Home Office could be liable for damage done
by escaping Borstal boys. It was held that it did owe a duty of care to
owners of property which might be damaged by the boys. At 1061 in
the course of his speech, after referring to the well known words of Lord
Atkin at page 580 of the report of Donoghue v. Stevenson, Lord Diplock
said,
It follows from this that although Hedley Byrne was a development from
Donoghue v. Stevenson it is the former and not the latter which applies to
- 85 -
“The cause of action accrues, not at the time of the negligent making or
passing of the foundations, nor at the time when the latest owner bought
the house, but at the time when the house began to sink and the cracks
appeared. That was the first time that any damage was sustained.”
“… when building work is badly done … the cause of action does not
accrue, and time does not begin to run, until such time as the plaintiff
discovers that it has done damage, or ought, with reasonable diligence, to
have discovered it.”
I note the following points. First, the date of accrual of the cause of
action is tied to when the house began to sink and the cracks ‘appeared’.
That is to say, when physical damage appeared. That is to be contrasted
with the speech of Lord Fraser at page 19 in Pirelli which I set out later in
this judgment, where he was at pains not to use the word ‘appeared’.
Secondly, time does not begin to run until the plaintiff discovers that it
has done damage or ought, with reasonable diligence, to have discovered
it, ‘it’ presumably referring to the damage which has been done. On the
face of it, this relates only to the plaintiff’s knowledge and is subject to
some of the difficulties I have already mentioned. There seems also to
have been an equation between the appearance or occurrence of the
- 87 -
“There is no proper analogy between this situation and the type of situation
exemplified in Cartledge v. Jopling … where a plaintiff due to the
negligence of the defendants suffers physical bodily injury which at the
outset and for many years thereafter may be clinically unobservable. In
those circumstances clearly damage is done to the plaintiff and the cause of
action accrues from the moment of the first injury albeit undetected and
undetectable. That is not so where the negligence has caused
unobservable damage not to the plaintiff’s body but to his house. He can
get rid of his house before any damage is suffered. Not so with his body.”
This was disapproved in Pirelli where Lord Fraser said, at page 16,
“My Lords, I find myself with the utmost respect unable to agree with that
argument. It seems to me that there is a true analogy between the plaintiff
whose body has, unknown to him, suffered injury by inhaling particles of
dust, and a plaintiff whose house has unknown to him sustained injury
because it was built with inadequate foundations or of unsuitable materials.
Just as the owner of the house may sell the house before the damage is
discovered, and may suffer no financial loss, so the man with the injured
body may die before pneumoconiosis becomes apparent, and he also may
suffer no financial loss. But in both cases they have a damaged article
when, but for the defendant’s negligence, they would have had a sound
one.”
“When does the cause of action arise? We can leave aside cases of
personal injury or damage to other property as presenting no difficulty. It
is only the damage for the house which requires consideration. In my
respectful opinion the Court of Appeal was right when, in
Sparham-Souter … it abjured the view that the cause of action arose
immediately upon delivery, i.e., conveyance of the defective house. It can
only arise when the state of the building is such that there is present or
imminent danger to the health or safety of persons occupying it ….”
“If it could be proved that the building suffered damage prior to February
1966 which endangered the safety of its occupants or visitors
Mrs. O’Shea’s claim would be statute-barred. It seems to me, however,
that since in fact no damage manifested itself until February 1970 it may
be very difficult to prove that damage had in fact occurred four years
previously. In the unlikely event of the defendants overcoming this
difficulty, the fact that the damage went undetected for four years would
not prevent the statute running from the date when the damage first
occurred : see Cartledge v. E. Jopling & Sons Ltd. [1963] A.C. 758. In
such circumstances Mrs. O’Shea could not have recovered damages
because her cause of action would have accrued more than six years before
the issue of the writ. Section 2(1) of the Limitation Act 1939 bars any
action in tort after the expiration of six years (amended by the Law Reform
(Limitation of Actions, etc.) Act 1954 to three years in actions for damages
for personal injuries) from the date when the cause of action accrued ….
I do not think that if and when this action comes to be tried, the defendants
should be prevented from attempting to prove that the claim by
Mrs. O’Shea is statute-barred. A building may be able to stand
undamaged on defective foundations for years and then perhaps eight years
or so later damage may occur. Whether it is possible to prove that
damage to the building had occurred four years before it manifested itself
is another matter, but it can only be decided by evidence.”
- 89 -
“… where the relationship between the parties was sufficiently close, the
scope of the duty of care in delict or tort owed by a person doing work was
not limited to a duty to avoid causing foreseeable harm to persons or to
property other than the subject-matter of the work by negligent acts or
omissions, but extended to a duty to avoid causing pure economic loss
consequential on defects in the work and (per Lord Fraser of Tullybelton,
Lord Russell of Killowen and Lord Roskill) to avoid defects in the work
itself ….”
“I would hold that the cause of action accrued … when damage, in the
form of cracks near the top of the chimney, must have come into existence.
I avoid saying that cracks ‘appeared’ because that might seem to imply that
they had been observed at that time ….”
This may be contrasted with the passage cited above from Lord
Denning’s judgment in Sparham-Souter and with the decision in
- 90 -
“Liability of the builders in tort, however, for the plaintiffs’ loss of the
value of the house is one which I would now question for reasons I will
later explain. My own short extempore judgment, which treats the issue
of the builder’s liability in damages and the fundamental question raised by
Stamp L.J. in Dutton v. Bognor Regis Urban District Council … as settled
by the speech of Lord Wilberforce in Anns v. Merton London Borough
Council … was, I now think, unsound.
“It has further, until the present case, never been doubted, so far as I know,
that the relevant property for the purpose of the wider principle on which
the decision in Donoghue v. Stevenson was based, was property other than
the very property which gave rise to the danger of physical damage
concerned.”
“… there are two important considerations which ought to limit the scope
of the duty of care which it is common ground was owed by the appellants
to the respondents on the assumed facts of the present case. The first
consideration is that, in Donoghue v. Stevenson itself and in all the
numerous cases in which the principle of that decision has been applied to
different but analogous factual situations, it has always been either stated
expressly, or taken for granted, that an essential ingredient in the cause of
action relied on was the existence of danger, or the threat of danger, of
physical damage to persons or their property, excluding for this purpose the
very piece of property from the defective condition of which such danger,
or threat of danger, arises.”
His Lordship concluded this part of his speech at page 206 with the
words,
“If the same principle applies in the field of real property to the liability of
the builder of a permanent structure which is dangerously defective, that
liability can only arise if the defect remains hidden until the defective
structure causes personal injury or damage to property other than the
structure itself. If the defect is discovered before any damage is done, the
loss sustained by the owner of the structure, who has to repair or demolish
it to avoid a potential source of danger to third parties, would seem to be
purely economic …. I do not find it necessary for the purpose of deciding
the present appeal to express any concluded view as to how far, if at all, the
ratio decidendi of Anns v. Merton London Borough Council … involves a
departure from this principle establishing a new cause of action in
negligence against a builder when the only damage alleged to have been
suffered by the plaintiff is a discovery of a defect in the very structure
which the builder erected.”
- 93 -
Upon any reading, this reversed the decision of at least Junior Books.
The effect on the decision in Anns was more problematical.
“Here, once the first cracks appear, the structure as a whole is seen to be
defective and the nature of the defect is known. Even if, contrary to my
view, the initial damage could be regarded as damage to other property
caused by a latent defect, once the defect is known the situation of the
building owner is analogous to that of the car owner who discovers that the
car has faulty brakes. He may have a house which, until repairs are
effected, is unfit for habitation, but, subject to the reservation I have
expressed with respect to ruinous buildings at or near a boundary of the
owner’s property, the building no longer represents a source of danger and
as it deteriorates will only damage itself.”
See also Lord Keith at page 462. Thirdly, the exception to which Lord
Bridge referred in the passage cited above was first mentioned by him
earlier at page 475. He said,
This is founded in good common sense and comes within the principles
of Donoghue v. Stevenson although questions may arise as to whether the
possibility of damage to other persons visiting the property should be
relevant as opposed to those simply passing by. Such a building would
present a danger of damage to persons or to property other than itself and
it would be absurd if the law were to hold that an owner must be forced to
wait until such damage occurs before he can seek redress. Finally, and I
think most importantly, the damage sued upon was recognised to be pure
economic damage. Lord Keith at page 466 also held that the damage in
Anns, Junior Books and Pirelli was also pure economic damage within
Hedley Byrne. The rest of their Lordships agreed.
- 95 -
The logic behind the speeches in Murphy that the damage, and
therefore the claim, was for pure economic loss has important
consequences. First, the claim does not fall within the principles of
Donoghue v. Stevenson. It falls under Hedley Byrne. Secondly, in
these circumstances physical damage is not necessary to the accrual of
the cause of action. As it was put by Lord Roskill in Junior Books at
page 546, the plaintiff had suffered ‘damage to the pocket’. At page 536
of Hedley Byrne itself Lord Pearce, discussing the application of the
principles of Donoghue v. Stevenson, said of their Lordships’ speeches in
that case,
“But they were certainly not purporting to deal with such issues as, for
instance, how far economic loss alone, without some physical or material
damage to support it, can afford a cause of action in negligence by act.
See Morrison Steamship Co. Ltd v. Greystoke Castle (Cargo Owners),
where it was held that it could do so.”
In the House of Lords, Lord Oliver at page 484 dealt with Anns in the
following way,
“The case has always been regarded as important in that it established that,
in certain circumstances, a duty of care may exist in respect of words as
well as deeds, and further that liability may arise in negligence in respect
of pure economic loss which is not parasitic upon physical damage.”
the case of D.W. Moore where solicitors negligently drafted the covenants
in an agreement. Bingham LJ at page 280 said,
The decision does not seem to take account of the fact that no actual
damage might ever occur but it illustrates that the act or omission would
have been the same in contract as it was in tort. The compensation for
duty breached and the quantum of damages would have been exactly the
same.
irrelevant since any later date of the occurrence of the cracks would have
put the accrual of the cause of action beyond the permitted period of
limitation. I would also note here that the decision in Pirelli does not
provide that the damage necessary for the accrual of a cause of action
occurs only when the physical damage has become manifest. In this
respect I must differ, although with the greatest of diffidence, from the
passage of the judgment of Lord Oliver in Murphy set out earlier. There
his Lordship said that it would make no sense to accord a remedy when
the defective nature of the structure had manifested itself by some
physical symptom but to deny it where the defect had been brought to
light, for instance, by a survey. With respect, Pirelli does not go so far.
The importance of the results of a survey is that it shows that damage
exists not that it is shown. Far from excluding that, Pirelli proceeds
upon the basis of Cartledge v. Jopling that damage exists whether or not
it is discovered or discoverable.
(2) The cause of action was for economic loss but in default
of clear evidence as to when that economic loss occurred
the occurrence of physical damage may be taken as the
date of the accrual of that cause. On that, the Bank also
failed.
(“BEA”).
Findlay J held that TW had not given any guarantee, and that no
tortious liability on its part had arisen. Accordingly he dismissed the
claim against TW and, in consequence, the third party proceedings which
TW had brought against the P & T partners. He held that the claim in
tort against the P & T partners was within time. Accordingly he gave
judgment for BEA against the P & T partners for damages in the sum of
$38,502,951.85 as claimed, being satisfied that that sum represented
BEA’s loss, and awarded interest on that sum at the judgment rate from
the date of judgment to the date of payment.
(2) If both TW and the P & T partners are liable, what is the
position in regard to contribution as between themselves?
The cladding
Mr Ragaglini
negligence.
This case has nothing to do with any third party claim (eg one
by the owner of a vehicle damaged by a falling fragment of cladding as it
was driven past the building) in which it is sought to argue that TW is
vicariously liable for Mr Ragaglini’s negligence. If there had been such
a claim, that argument might well have succeeded on the basis that TW
were undertaking an extra hazardous operation abutting a highway.
- 110 -
LIMITATION
Section 31
Pausing here, one sees that subsection (1) thereof provides that
s.31 does not apply to actions for damages for negligence to which s.27
applies. Section 27 applies to personal injury cases. And, it is also to
be noted, s.27(2) provides that s.4 shall not apply to an action to which
s.27 applies.
Longstop
Section 38(A)
(i) the cause of action did not accrue until after 1 July 1985;
and
(ii) BEA did not have the knowledge referred to in s.31 (“the
requisite knowledge”) before 20 June 1991, the action
having been commenced on the third anniversary of that
date.
And even if the action against the P & T partners is not within time under
s.4(1), it will nevertheless be within time by virtue of s.31 if:
(i) the cause of action did not accrue until after 1 July 1985;
and
- 114 -
(ii) BEA did not have the requisite knowledge before 25 May
1993, the action having been commenced on the third
anniversary of that date.
Economic loss
being latent. And those findings of fact were supported by the Court of
Appeal, so that they come to us as concurrent findings of fact. In any
event, the arguments advanced on behalf of the respondent are flawed for
this reason. There is a world of difference between, on the one hand,
seeing what the width of a gap is and, on the other hand, realising that
such width is insufficient. For all these reasons, I proceed on the basis
that this is a case of latent defects.
But he did “not accept that any reasonable owner seeing these
marks would have concluded that there were defects in the cladding
justifying the calling in of an expert”. And as to knowledge, his
findings of fact, which the Court of Appeal supported and therefore come
to this Court as concurrent findings of fact, are these:
“ There is evidence that, in about March 1993, there was some cause
for the Bank to believe that all was not well with the cladding. This is
probably why Bolton Construction conducted a site investigation in May
1993. Outside the contemporaneous documents, this evidence, and,
indeed, generally the oral evidence, is, understandably with the lapse of
time, vague. The limitation point is a defence, and it is for the
defendants to establish it.
The evidence leads me to believe that it was not until about the
middle of 1993 that the defects so obvious that any reasonable person
would have called in an expert, and, having done so, would have been
aware of defects and realised that a loss had been suffered. It is
impossible to be precise about when, on this basis, it can be said that the
cause of action accrued. It cannot be at the moment in time when the
owner decides to call in the expert. There must be a reasonable time gap
to enable the expert to examine the building and report his findings on the
cause and extent of the defects. It is only then that it can be said that
what is suspected is verified, and this ‘marks the moment when the market
value of the building is depreciated, and therefore the moment when the
economic loss occurs’. This, in my judgment, must have been after 24
May 1993. So, in my view, the writs against TW and P & T were issued
within three years of the cause of action accruing to BEA.”
The argument for TW and for the P & T partners is that the loss
in the present case was suffered when the building was completed and
paid for in 1982, so that the cause of action accrued then and became
time-barred in 1988.
- 117 -
The other three law lords hearing the appeal in Nykredit agreed
with Lord Nicholls of Birkenhead and Lord Hoffmann.
“… the basic comparison called for is between (a) the amount of money
lent by the plaintiff, which he would still have had in the absence of the
loan transaction, plus interest at a proper rate, and (b) the value of the
rights acquired, namely the borrower’s covenant and the true value of the
overvalued property.”
“ For what, then, is the valuer liable? The valuer is liable for the
adverse consequences, flowing from entering into the transaction, which
are attributable to the deficiency in the valuation. This principle of
liability, easier to formulate than to apply, has next to be translated into
practical terms. As to this, the basic comparison remains in point, as the
means of identifying whether the lender has suffered any loss in
consequence of entering into the transaction. If he has not, then
currently he has no cause of action against the valuer. The deficiency in
security has, in practice, caused him no damage. However, if the basic
comparison throws up a loss, then it is necessary to inquire further and see
what part of the loss is the consequence of the deficiency in the security.”
Thus the cause of action may accrue at the time of the defendant’s
negligence, or it may accrue only at a later stage because measurable,
relevant loss was first sustained at that later stage.
“In the present case the borrower’s covenant was worthless. The
borrower defaulted at once, and the amount lent (£2.45m.) at all times
exceeded the true value of the property (£2.1m.). Thus the cause of
action arose at the time of the transaction (12 March 1990) or thereabouts.
By December 1990 the bank had sustained its full allowable loss of £1.4m.
I would award simple interest on that amount from 12 December 1990
until judgment at the agreed rate of 0.4 per cent above LIBOR (London
Inter-bank Offered Rate).”
limitation period set by s.4. That is the function of s.31 where it applies,
subject to the s.32 longstop. Rather it is a question of recognizing that
the economic loss in building defects cases occurs when the market value
of the building is diminished upon the defects ceasing to be latent and
becoming known to the market as represented by reasonable people in the
marketplace. That is when the building will, absent reasonable repairs,
be depreciated: as an asset and also in terms of the potential proceeds of a
possible sale. I think that one has to look at the matter along such lines
if the term “economic loss” is to have substance and real meaning.
Otherwise it would be difficult to see how the term gets beyond being a
mere label. Put in Nykredit terms, I would say that the depreciation
marks the onset of “measurable” loss and when the building owner
becomes “financially worse off”.
I should mention that counsel adverted to, but did not address
us on, the decision of the House of Lords in Ruxley Electronics &
Construction Ltd v. Forsyth [1996] 1 AC 344. This is understandable.
As far as the proper basis for compensation is concerned, cases like the
- 121 -
present one are very different from cases like Ruxley. Cases of
economic loss flowing from the depreciation of a building are, by
definition, very different from cases like Ruxley where the property was
not depreciated. There the householder received a pool with a diving
area only 6 feet deep even though the contract specified a diving area
7 feet 6 inches deep. But the shortfall did not render the pool unsuitable
for diving or adversely affect the value of the property.
I do not think that there can be any doubt that any layman
would condemn as an absurdity, injustice and mockery the notion of
someone having something which lawyers call a “cause of action” but
which secretly comes about and just as secretly goes away before the
victim of a legal wrong can go to a court for a remedy. And there is a
large collection of statements by eminent judges to like effect. It is true
that that notion has nevertheless go into the common law as something
which can sometimes happen. And it is likewise true that this is
recognized in statute law in the course of providing some relief against
the notion’s rigours. But, as one sees from Nykredit for example, it is
not always the case that measurable loss occurs as soon as the wrong is
done. That the notion in question is embedded in some situations is one
thing. To extend it to all or any other situations is another thing.
“But the mere fact that an enactment shows that Parliament must have
thought that the law was one thing does not preclude the courts from
deciding that the law was in fact something different. This has been
stated in a number of cases including Inland Revenue Commissioners v.
Dowdall, O’Mahoney & Co. Ltd [1952] AC 401. No doubt the decision
would be different if the provisions of the enactment were such that they
would only be workable if the law was as Parliament supposed it to be.
- 124 -
But, in my view, all that can be said here is that these enactments would
have a narrower scope if the law was found to be that compensation must
be assessed at a date later than that of the notice to treat. I do not think
that that is sufficient to preclude your Lordships from re-examining the
whole matter.”
Lord Upjohn said (at p.908 G-H) that he agreed with Lord Reid,
Lord Morris of Borth-y-Gest and Lord Donovan.
“It is a trite observation that Parliament does not change the existing law
simply by betraying a mistaken view of it. It would be a very different
state of affairs if Parliament in effect said that some existing practice
should be treated as being and as always having been the law, and then
proceeded to enact some new provisions on that basis. Parliament would
not, I suppose, normally be so explicit as regards the existing practice, and
the courts would have to decide whether the language of the new
provisions necessarily imported the translation into law of the practice.
In the present case I am clear that this cannot be said to be the effect of the
provisions relied upon by the appellants.”
For those reasons, I am of the view that both actions are within
time under s.4(1), and that it is unnecessary further to consider s.31.
For the reasons given above, TW and the P & T partners are
both responsible for the damage suffered by BEA, and are therefore
jointly and severally liable in tort to BEA for such damage. What
remains to be done is to apportion such responsibility between them
under the Civil Liability (Contribution) Ordinance, Cap. 377. On the
material to hand, I do not see how this Court can confidently draw any
distinction between TW and the P & T partners’ share of such
responsibility. As I see it, the only apportionment which this Court is in
a position to make is a 50:50 apportionment.
P & T partners and, doing so, make a 50:50 apportionment between them.
This is how I would deal with contribution between TW and the P & T
partners.
CONCLUSION
It is not only in the foregoing respect that the law is less than
Article 18 of the Basic Law as part of the Law of the Hong Kong Special
- 127 -
(Tang Siu Man v HKSAR [1998]1 HKC 371 at 393A-B, 405I). It may be
thought, however, that this Court would not depart from the law as it
provisions of the Limitation Ordinance (Cap. 347), i.e. ss 4(1), 31, 32 and
enacting them, whether that was mistaken or not, that matters. What
the 1991 Amendments in some detail in the foregoing regard. I agree for
the reasons they have given that those provisions are sufficiently
particular, Hong Kong lacks anything like the longstanding legal regime
approach in Pirelli General Cable Works Ltd v Oscar Faber & Partners
any event with the analysis, reasoning and conclusion of Ching PJ leading
amenable to the legislative than the judicial process. The former might
legislation in the first place, and moreover, that the present legislation
Ching PJ, seems not only the most appropriate, but also to best accord
first occurred.
As to when that date occurred in the present case, there are two
competing alternatives. One possibility, for which the defendants
contended, is the date when the bank accepted and paid for its new
headquarters building. At that date the bank acquired a building which
was substandard because of an inherent defect in its design.
Unbeknown to the bank, the building was intrinsically less valuable than
it should have been. When the defect came to light, a substantial
amount of money would have to be spent on making good the defect.
I also recognise that this approach does not fit happily with the
scheme underlying section 31 of the Limitation Ordinance, Cap. 347, and
the corresponding provisions in the Latent Damage Act 1986.