02 - Contractual Issues
02 - Contractual Issues
Rizwan Farooqui
Presentation Outline
þ Acceptance/Withdrawal of Bids
þ Chronology of Bid Procedure
þ Award of Contract
þ Contract Agreement
þ Time Extensions
þ Change Orders
þ Value Engineering
þ Liquidated Damages
þ Acceptance and Final Payment
Rizwan Farooqui
Rizwan Farooqui
Written notice
Notice to to proceed
bidders Bid
opening Formal
Contract
Rizwan Farooqui
Rizwan Farooqui
Contract Agreement
Contracts
Rizwan Farooqui
Construction Contracts
Unit price
Contractor
Design-build
Lump sum fixed price plus escalation
Design-Manage -Build (Turnkey)
Target cost incentive contracts
Rizwan Farooqui
Contract Documents
þ Agreement
þ General/Supplementary Conditions
þ Any Addenda
Rizwan Farooqui
Rizwan Farooqui
General Conditions
þ Definition of contract documents
þ Document precedent
þ Duties and responsibilities of the parties
þ Duties and responsibilities of the design professional
þ Subcontractors
þ Separate contractors
þ Time aspects of the contract
þ Payments and completion
þ Insurance and bonds
þ Change in the work
þ Arbitration and termination of the contract
þ Miscellaneous provisions
Rizwan Farooqui
Rizwan Farooqui
Specifications
Rizwan Farooqui
þ Defines the way in which the project will be executed and the
way disputes/conflicts will be solved.
Rizwan Farooqui
FIDIC Contracts
Rizwan Farooqui
Rizwan Farooqui
Rizwan Farooqui
þCulture
þPolitics
þLaw and Order
þCurrency
Rizwan Farooqui
Time Extensions
Delay sources:
• Design problems
• Owner Modification
• Weather
• Strike
• Late delivery
• others
Rizwan Farooqui
Rizwan Farooqui
Changed Conditions
Due to:
• Inadequate information provided from the sub-
surface investigation.
• A condition may not be detected during design, and
the assumption is that it does not exist in real life.
• Variation in wind pattern.
• If the owner accepts the changed condition, the
extended scope of work represented will be included
in the contract as a change order.
• If the owner rejects the changed condition claim, the
validity of the claim must be established by litigation
or arbitration.
Rizwan Farooqui
Rizwan Farooqui
Rizwan Farooqui
Rizwan Farooqui
Liquidated Damages
Rizwan Farooqui
Rizwan Farooqui
Rizwan Farooqui
Legal Issues
Construction Disputes
If a construction dispute
cannot be resolved through
negotiation and compromise
between the disputants, it is
necessary to resolve the
disagreement by a third
party.
Rizwan Farooqui
þ Negotiation
þ Administrative Boards
þ Litigation
þ Arbitration
þ Mediation
Rizwan Farooqui
Legal Issues
Construction Claims
Claim is a request by the contractor for recompense for
some loss or expense that he or she has suffered, or an
attempt to avoid the requirement to pay liquidated and
ascertained damages.
Rizwan Farooqui
þ Contractual Claims
- Payment and Security
- Changes in the Scope of Work
- Construction Delays
þ Ex-Contractual Claims
Rizwan Farooqui
Legal Issues
þ Supporting information.
þ Significant documents.
þ Accurate record.
Rizwan Farooqui
Rizwan Farooqui