Section - Iii (Volume - I)
Section - Iii (Volume - I)
(VOLUME - I)
CONTENTS
A. INTRODUCTION
D. SPARES
36.0 Spares
E. RISK DISTRIBUTION
37.0 Transfer of the Title
38.0 Insurance
39.0 Liability for Accidents and Damages
40.0 Delays by Owner or His Authorised Agents
41.0 Demurrage, Wharfage etc.
42.0 Force Majeure
43.0 Suspension of Work
44.0 Contractor's Default
45.0 Termination of Contract on Owner's initiative.
46,0 Frustration of Contract
47.0 Grafts and Commission etc.
F. RESOLUTION OF DISPUTES
48.0 Settlement of Disputes
49.0 Reconciliation of Accounts
50.0 Inspection and Tests
51.0 Consortium
52.0 Notices
SECTION-III - GCC
A. INTRODUCTION
1.1 ‘The Contract' means the Agreement entered into between Owner and
Contractor as per the Contract Agreement signed by the parties including all
attachments and appendices there to and all documents incorporated by
reference therein.
1.3 a) Contractor' shall mean the Bidder whose Bid will be accepted
by the Owner for the Award of the Works and shall include such successful
Bidder's Legal Representatives, Successors and Permitted Assigns.
1.4 ‘Sub- Contractor' shall mean the persons named in the contract for any part
of the works or any persons to whom any part of the contract has been sublet by
the Contractor with the consent in writing of the Owner and will include the legal
representatives, successors and permitted assigns of such persons.
1.5 Void
1.6 ‘Consulting Engineer’ shall mean any Firm or Persons duly appointed
as such from time to time by the Owner.
1.7 The terms ‘Equipments’ ‘Stores’ and ‘Materials’ shall mean and
include Equipment, Stores and Materials to be provided by the Contractor under
the Contract.
1.8 ‘Works’ shall mean and include supplying of equipment/ material in the
scope of the Contractor and extending all services, as per the specifications and
complete erection, testing and putting into satisfactory operation (including
Owner supplied equipments/ materials) including all transportation, handling,
unloading and storage at the site as defined in the contract.
1.9 'Specifications' shall mean the specifications and bidding document forming
a part of the contract and such other schedules and drawings as may be mutually
agreed upon.
1.10 ‘Site' shall mean and include the Land and other places on, into or through
which the works and the related facilities are to be erected or installed and any
adjacent land, paths, street or reservoir which may be allocated or used by the
Owner or Contractor in the performance of the contract.
1.11 The term 'Contract Price' shall mean the total price quoted by the
Contractor in his bid with additions and/or deletions as may be agreed and
incorporated in the letter of award/ letter of intent to award(as applicable), for the
entire scope of the works.
1.12 The term 'Equipment/Material Portion' of the Contract Price shall mean the
Total Value of the Equipments including Freight & Insurance with all types of
applicable Taxes such as CGST, SGST, IGST, UTGST, Duties, Cess if any, etc. The
Term ‘Erection Portion' of the Contract Price shall mean the Value of Field
Activities of the Works including Erection, Testing and Putting into Satisfactory
Operation including Successful Completion of Performance and Guarantee Tests
to be performed at Site by the Contractor including Cost of Insurances.
1.14 'Inspector' shall mean the Owner or any persons nominated by the
Owner from time to time, to inspect the equipment, stores or works under the
contract and/or the duly authorised representative of the Owner.
1.16 ‘Date of Contract' shall mean the date on which notice of award of contract/
letter of award/letter of intent (as applicable) to award has been issued.
1.17 'Month' shall mean the calendar month. 'Day' or 'Days' unless herein
otherwise expressly defined shall mean calendar day or days of 24 hours each. ‘A
Week' shall mean continuous period of seven (7) days.
1.18 ‘Writing' shall include any manuscript, type written, computer generated or
printed statement, under or over signature and/or seal, as the case may be.
1.21 'Start up' shall mean the time period required to bring the equipment
covered under the contract from an inactive condition, when construction is
essentially complete, to the state ready for trial operation. The start up period
shall include preliminary inspection and checkout of equipment and supporting
sub-system, initial operation of the complete equipment covered under the
contract to obtain necessary pre-trial operation data, perform calibration and
corrective action, shut down, inspection and adjustment prior to the trial
operation period.
1.22 'Initial Operation' shall mean the first integral operation of the
complete equipment covered under the contract (including owner supplied) with
the sub-system and supporting equipment in service or available for service.
1.23 ‘Trial Operation', 'Reliability Test', ‘Trial Run', ‘Completion Test', shall
mean the extended period of time after the start up period. During this trial
operation period, the unit shall be operated over the full load range. The length of
trial operation shall be as determined by the engineer, unless otherwise specified
elsewhere in the contract.
1.24 'Performance and Guarantee Test 'shall mean all operational checks and
tests required to determine and demonstrate capacity, efficiency, and operating
characteristics as specified in the contract documents.
1.25 The term 'Final Acceptance/Taking Over' shall mean the Owner's written
acceptance of the works performed under the contract, after successful
commissioning/ completion of performance and guarantee tests, as specified in
the accompanying technical specification or other-wise agreed in the contract.
1.26 'Guarantee Period' / 'Maintenance Period' shall mean the period during
which the contractor shall remain liable for repair or replacement of any defective
part of the works performed under the contract.
1.27 'Latent Defects' shall mean such defects caused by faulty design, material
or workmanship which cannot be detected during inspection, testing etc. based
on the technology available for carrying out such tests.
1.29 'Codes' shall mean the following, but not limited to, including the latest
amendments, and/or replacements if any:
a. Indian Factory Act, 1948, and Rules and Regulations made thereunder.
b. Indian Explosive Act, 1884, and Rules and Regulations made thereunder.
c. Indian Petroleum Act, 1934, and Rules and Regulations made there under.
d. A.S.M.E. Test Codes.
e. A.I.E.E. Test Codes.
f. American Society of Materials Testing Codes.
g. Standards of the Indian Standards Institution.
h. Other Internationally approved Standards and/or Rules and Regulations
touching the subject Matter of the Contract.
1.30 Words imparting the Singular only shall also include the Plural and vice-
versa where the context so requires.
1.31 Words imparting 'Persons' shall include Firms, Companies, Corporation and
Associations or Bodies of individuals, whether incorporated or not.
1.33 "Tests on Completion": Means the Tests that are prescribed in the Bidding
Documents to be made before Materials are accepted by the Owner.
1.34 "Destination" : Means the location where the goods are specified to be
delivered and where they will be accepted by the Owner.
1.39 In addition to the above, the following definitions shall also apply:
2.0 Application:
These general conditions shall apply to the extent that they are not
superseded by provisions in other parts of the contract.
3.0 Standards:
The goods supplied under this contract shall conform to the standards mentioned
in the technical specification, and, when no applicable standard is mentioned, to
the authoritative standard appropriate to the goods and such standards shall be
the latest issued by the concerned institution.
5.1 The term contract documents shall mean and include the following which
shall be deemed to form an integral part of the Contract:
d) All the materials, literature, data and information of any sort given by the
contractor along with his bid, subject to the approval of the Owner.
e) Letter of award / Letter of Intent to award (as applicable) and any agreed
variations of the conditions of the documents and special terms and conditions of
contract, if any.
5.2 In the event of any conflict between the above mentioned documents, the
matter shall be referred to the engineer whose decision shall be considered as
final and binding upon the parties.
5.3 All the relevant information/ material furnished by the contractor such as
specifications of material/ equipment, design, literature, drawings or any other data
during the course of contract will become the property of the owner and owner will
have full rights to use the same elsewhere.
6.1 The Contractor shall not, without the Owner's prior written consent, disclose
the contract, or any provision thereof, or any specification, plan, drawing, pattern,
sample or information furnished by or on behalf of the Owner in connection
therewith, to any persons other than a person employed by the Contractor in the
performance of the contract. Disclosure to any such employed persons shall be
made in confidence and shall extend only so far, as may be necessary for purposes
of such performance.
6.2 The Contractor shall not, without the Owner's prior written consent, make use
of any document or information enumerated in various contract documents
except for purpose of performing the contract.
6.3 The Contractor shall not communicate or use in advertising, publicity, sales
releases or in any other medium, photographs or other reproduction of the works
under this contract, or descriptions of the site, dimensions, quantity, quality or
other information, concerning the works unless prior written permission has been
obtained from the Owner.
6.4 Any Document, other than the contract itself, enumerated in various contract
documents, shall remain the property of the Owner and shall be returned (in all
copies) to the Owner on completion of the contractor's performance under the
contract, if so required by the Owner.,
7.1 Not withstanding anything stated elsewhere in the Bid Documents, the Contract
to be entered into will be treated as a DIVISIBLE CONTRACT resulting into three
separate contracts, one for supply of goods, the second for erection and the third for
civil engineering works covering the Entire Scope of the Partial/Total Turnkey
Package.
All works contracts are normally ‘Divisible contracts’, wherein contract agreements
and DWA’s for each of the projects towards supply, erection and civil portion of the
contract are executed and issued separately. Hence cross fall breach is envisaged in
such type of contracts wherein breach in any one of the contract say either in
supply, erection or civil would be treated as breach in remaining contracts also
within the project/work that has been awarded. However in the package system of
tendering where two or more projects/works are proposed to be clubbed for the sake
of convenience for expediting the processing of tenders, the cross fall breach if any,
in a particular project/work is proposed to be restricted to that project/work itself
and is not allowed to get extended to other projects/works which have been included
in the same enquiry and are awarded separately.
7.2 In case where the Owner hands over his Equipment/Material to the Contractor
for executing, then the Contractor shall at the time of taking delivery of the
equipment/ dispatch documents be required to execute an Indemnity Bond in
favour of the Owner in the form acceptable to KPTCL for keeping the
equipment/material in safe custody and to utilise the same exclusively for the
purposes of the said contract. Samples of proforma for the indemnity bond is
enclosed as Annexure-VIII & IX.
8.1 The Contract, shall in all respects be constructed and governed according to
Indian Laws
8.2 The Courts of Bangalore shall have exclusive jurisdiction in all matters
arising under this Contract.
9.1 The Contract, unless otherwise agreed to, shall be signed within 15 days of
the acceptance of the Letter of Award/ Letter of Intent to Award, at the Office of
the Owner i.e. at the concerned O/o SEE, Transmission Circle, KPTCL, on a date
and time to be mutually agreed to. The Contractor shall provide for signing of the
contract, performance guarantee, appropriate power of attorney and other
requisite materials. In case the contract is to be signed beyond the stipulated
time, the bid security submitted with the proposal shall be extended accordingly.
9.2 The agreements shall be signed in original and the contractor shall be
provided with one photo copy and the Owner will retain the original.
9.3 The Contractor shall provide free of cost to the Owner, the engineering
data, drawings and descriptive materials submitted with the bid, in at least three
(3) copies to form a part of the contract immediately after issue of letter of award/
letter of intent to award(as applicable).
9.4 Subsequent to signing of the contract, the Contractor at his own cost shall
provide the Owner with at least fifteen (15) bounded true copies of DWA within
thirty (30) days after issue of DWA.
10.1 The failure of either party to enforce at any time any of the provisions of this
contract or any rights in respect thereto or to exercise any option therein
provided, shall in no way be construed to be a waiver of such provisions, rights or
options or in any way to affect the validity of the contract. The exercise by either
party of any of its rights herein shall not preclude or prejudice either party from
exercising the same or any other right it may have under the Contract.
11.1 Unless otherwise terminated under the provisions of any other relevant
clause, this contract shall be deemed to have been completed on the expiry of the
guarantee period as provided for under the clause 15.0 entitled ‘Guarantee' in
Section-III, Volume-I of GCC.
12.1 The time and the date of completion of the contract as stipulated in the
contract by the owner with or without modifications, if any, and so incorporated
in the letter of award/letter of intent to award (as applicable), shall be deemed to
be the essence of the contract. The Contractor shall so organise his resources and
perform his work as to complete it not later than the date agreed to.
The Contract shall be considered as having come into force from the date of
Letter of Award.
14.0 Penalty:
If the Contractor fails to successfully complete the commissioning within the time
fixed under the contract, the Contractor shall pay to the Owner as Penalty, a sum
specified for each specified period of delay. The details of such penalty are
brought out in the accompanying special conditions of contract (SCC). Equipment
and materials will be deemed to have been delivered only when all its
components, parts are also delivered. If certain components are not delivered in
time, the equipment and materials will be considered as delayed until such time
the missing parts are also delivered. The total amount of Penalty for delay under
the contract will be subject to a maximum 10% of the contract price.
14.2.2 The total amount of Penalty for delay under the contract will be
subject to a maximum of Ten percent (10%) of the value of contract unless
otherwise specifically mentioned in Special Conditions of Contract.
Note: The total penalty levied shall not exceed the total contract value.
15.0 Guarantee:
15.1 The Contractor shall Guarantee that the equipment supplied by him will be
new, unused and in accordance with the contract documents and free from
defects in material and workmanship for a period of 42 (Forty Two) months in
respect of Control and Relay panels, Isolators, Battery Set & Circuit Breakers and
12 (twelve) Months for rest of the project commencing immediately upon the
satisfactory commissioning. The Contractor's liability shall be limited to the
replacement of any defective parts in the equipment of his own manufacture or
those of his sub-contractors, under normal use and arising solely from faulty
design, materials and/or workmanship provided always that such defective parts
are repairable at the site and are not in the meantime essential in the commercial
use of the equipment. Such replaced/ defective parts shall be returned to the
Contractor unless otherwise arranged. No repairs or replacement shall normally
be carried out by the engineer, when the equipment is under the supervision of
the Contractor's Supervisory Engineer.
15.2 In the event of any emergency, as per the judgment of the Engineer, where
in the delay would cause serious loss or damages, repairs or adjustment may be
made by the engineer or a third party chosen by the engineer without advance
notice to the contractor and the cost of such work shall be paid by the contractor.
In the event of such action being taken by the Engineer, the Contractor will be
notified promptly and he shall assist wherever possible in making necessary
corrections. This shall not relieve the Contractor of his liabilities under the Terms
and Conditions of the Contract.
15.3 If it, becomes necessary for the Contractor to replace or renew any defective
portions of the works, the provision of this clause shall apply to portion of the
works so replaced or renewed until the expiry of 42 (Forty Two) months in respect
of Control and Relay panels, Isolators, Battery Set & Circuit Breakers and 12
(twelve) Months for rest of the project from the date of such replacement or
renewal. If any defects are not remedied within a reasonable time, the Engineer
may proceed to do the Work at the Contractor’s risk and cost but without
prejudice to any other rights, which the Owner may have against the Contractor
in respect of such defects.
15.4 The repaired or new parts will be furnished and erected free of cost by the
Contractor. If any repair is carried out on his behalf at the Site, the Contractor
shall bear the cost of such repairs.
15.5 The cost of any special or general overhaul rendered necessary during the
maintenance period due to defects in the equipment or defective work carried out
by the Contractor, the same shall be borne by the Contractor.
15.6 The acceptance of the Equipment by the Engineer shall in no way relieve the
Contractor of his obligations under this clause.
15.7 In case of those defective parts which are not repairable at Site but are
essential for the Commercial Operation of the Equipment, the Contractor and the
Engineer shall mutually agree to a program of replacement or renewal which will
minimise interruption to the maximum extent, in the Operation of the Equipment.
15.8 In respect of goods supplied by Vendor to the Contractor where a
longer guarantee (more than 12 months) is provided by such Vendor, the Owner
shall be entitled to the benefit of such longer guarantees.
a) If the Owner has not used the equipment according to generally approved
industrial practice and in accordance with the conditions of operation specified
and in accordance with operating manuals, if any.
The Contractor shall be liable and pay all types of applicable Taxes such as CGST,
SGST, IGST, UTGST, Duties, Levies, Cess if any, lawfully assessed against the
Owner or the Contractor in pursuance of the Contract. In addition the Contractor
shall be responsible for Payment of all Indian Duties, Levies and all Taxes, cess if
any lawfully assessed against the Contractor for his Personal Income and
Property.
17.1 If during the performance of the contract, the engineer shall decide and
inform in writing to the Contractor that the Contractor has manufactured any
equipment, material or part of equipment unsound and imperfect or has
furnished any equipment inferior to the quality specified, the Contractor on
receiving details of such defects or deficiencies shall at his own expense within
seven (7) days of his receiving the notice, or otherwise, within such time, as may
be reasonably necessary for making it good, proceed to alter, reconstruct or
remove such work and furnish fresh equipment/ materials up to the standards of
the specifications. In case the Contractor fails to do so, the Engineer may on
giving the Contractor seven (7) days notice in writing of his intentions to do so,
proceed to remove the portion of the works so complained of and at the cost of the
Contractor perform all such work or furnish such equipment/ material provided
that nothing in this clause shall be deemed to deprive the Owner of or affect any
rights under the contract which the Owner may otherwise have in respect of such
defects and deficiencies.
17.2 The Contractor's full and extreme liability under this clause shall be satisfied
by the payment to the Owner of the extra cost, of such replacement procured
including erection as provided for in the contract, such extra cost being the
ascertained difference between the price paid by the Owner for such replacements
and the contract price by portion for such defective equipment/ material/ works
and repayments of any sum paid by the Owner to the Contractor in respect of
such defective equipment/ material should the owner not so replace the defective
equipment/materials, the Contractor's extreme liability under this clause shall be
limited to repayment of all sums paid by the owner under the contract for such
defective equipment /materials.
Royalties and fees for patents covering materials, articles, apparatus, devices,
equipment or processes used in the works shall be deemed to have been included
in the contract price. The Contractor shall satisfy, all demands that may be made
at any time for such royalties or fees and he alone shall be liable for any damages
or claims for patent infringements and shall keep the Owner indemnified in that
regard. The Contractor shall, at his own cost and expense, defend all suits or
proceedings that may be instituted for alleged infringement of any patents
involved in the works, and, in case of an award of damages, the Contractor shall
pay for such award. In the event of any suit or other proceedings instituted
against the Owner, the same shall be defended at the cost and expense of
Contractor who shall also satisfy/comply with any decree, order or award made
against the Owner. But it shall be understood that no such machine, plant, work,
material or thing has been used by the Owner for any purpose or manner other
than that for which they have been furnished and installed by the Contractor and
specified under these specifications. Final payment to the Contractor by the
Owner will not be made while any such suit or claim remains unsettled. In the
event any apparatus or equipment, or any part thereof furnished by the
Contractor, is in such suit or proceedings held to constitute infringement, and its
use is enjoined, the Contractor shall at his option and at his own expense, either
procure for the Owner, the right to continue the use by Owner of said apparatus,
equipment or part thereof, replace it with non infringing apparatus or equipment
or modify it, so that it becomes non-infringing.
The final payment by the Owner in pursuance of the contract shall mean the
release of the Contractor from all his liabilities under the contract. Such final
payment shall be made only at the end of the guarantee/ warranty period, and till
such time as the contractual liabilities and responsibilities of the Contractor, shall
prevail. All other payments made under the contract shall be treated as on
account payments.
21.0 Engineer's Decision:
21.1 In respect of all matters which are left to the decision of the Engineer
including the granting or with-holding of the Certificates, the Engineer shall, if
required to do so by the Contractor, give in writing a decision thereon.
21.2 If, in the opinion of the Contractor, a decision made by the Engineer is not in
accordance with the meaning and intent of the contract, the Contractor may file
with the Engineer, within fifteen (15) days after receipt of the decision, a written
objection to the decision. Failure to file an objection within the allotted time will
be considered as an acceptance of the Engineer's decision and the decision shall
become final and binding.
21.3 It is the intent of the agreement that there shall be no delay in the execution
of the works and the decision of the Engineer as rendered shall be promptly
observed.
22.2 In the event of Engineer requiring any variation, a reasonable and proper
notice shall be given to the Contractor to enable him to work his arrangement
accordingly, and in cases where goods or materials are already prepared or any
design, drawings or pattern made or work done requires to be altered, a
reasonable and agreed sum in respect thereof shall be paid to the Contractor.
22.3 In any case in which the Contractor has received instructions from the
Engineer as to the requirement of carrying out the alterations or additions or
substitute which either then or later on, will, in the opinion of the Contractor,
involve a Claim for additional payment, the Contractor shall immediately and in
no case later than thirty (30) days, after receipt of the instructions aforesaid and
before carrying out the instructions, advise the Engineer to that effect. But the
Engineer shall not become liable for the payment of any charges in respect of
any such variations, unless the instructions for the performance of the same shall
be confirmed in writing by the Engineer.
22.4 VOID.
22.6 Not withstanding anything stated above in this clause, the Engineer shall
have the full power to instruct the Contractor, in writing, during the execution of
the contract to vary the quantities of the items or groups of items in accordance
with the provision of clause entitled 'Change of Quantity’ in clause 24 of Section
GCC of this volume - I. The Contractor shall carry out such variations and the
contract price shall be adjusted in accordance with clause 24 of section GCC.
23.1 Deleted.
23.2 For components/ equipment procured by the Contractor for the purposes of
the contract, after obtaining the written approval of the Owner, the Contractor's
purchase specifications and enquiries shall call for quality plans to be submitted
by the suppliers along with their proposals. The quality plans called for from the
vendors shall set out, during the various stages of manufacture and installation,
the quality practices and procedures followed by the vendor's quality control
organization, the relevant reference documents/ standard used, acceptance level,
inspection documentation raised, etc. Such quality plans of the successful
vendors shall be discussed and finalised in consultation with the Engineer and
shall form a part of the purchase order/contract between the Contractor and the
Vendor. Within 3 weeks of the release of the purchase orders/ contracts for such
bought out items/ components, a copy of the same without price details but
together with detailed purchase specifications, quality plans and delivery
conditions shall be furnished to the Engineer by the Contractor.
During the execution of the contract, the Owner reserves the right to increase the
quantities of items under the contract with a ceiling limit of 25% for each of
the individual items without any change in unit rate or other terms and
condition of the contract.
For quantities exceeding 25%, of the tendered quantity of an item in the
DWA, the Contractor shall be paid at the rate entered in the Schedules of
rates (applicable for the area of the work and prevailing SR at the time of
award of contract) plus the overall percentage of the original tendered rates
over the updated estimate cost prevalent at the time of award of contract or
the unit rate quoted by the bidder as the case may be, whichever is lower
without any ceiling limit.
In case of overall percentage on updated estimate cost being minus, then for
quantities exceeding 25%, of the tendered quantity of an item in the DWA,
the contractor shall be paid at the Schedules of rates (applicable for the area
of the work and prevailing SR at the time of award of contract).
Further, the Owner reserves the right to order excess quantity not exceeding 10%
of the value of the total contract price with in one year after completion of the
contract and the Contractor shall supply the same, if ordered, at the same unit
rates of the contract. The Contractor shall make use of the materials available
with the Owner as and when the Contractor is asked to do so by the Owner and
the cost of those materials will not be paid to the Contractor.
24.3 The contract price shall accordingly be adjusted based on the unit
rates/FORD price available in the contract for the change in quantities as above.
The base unit rates, as identified in the contract shall however remain constant
during the currency of the contract, except as provided for in clause 33.0 below.
25.1 The Contractor, wherever applicable, shall after proper painting, pack and
crate all equipment in such a manner as to protect them from deterioration and
damage during rail and road transportation to the site and storage at the site till
the time of erection. The Contractor shall be held responsible for all damages due
to improper packing.
25.2 The Contractor shall notify the Owner of the date of each shipment from his
works, and the expected date of arrival at the Site for the information of the
Owner.
25.3 The Contractor shall also give all shipping information concerning the
weight, size and content of each packing including any other information the
Owner may require.
25.4 The following documents shall be sent by registered post to the Owner within
3 days from the date of shipment, to enable the Owner to make progressive
payments to the Contractor.
25.5 The Contractor shall prepare detailed packing list of all packages and
containers, bundles and loose material forming each and every consignment
dispatched to site. The Contractor shall further be responsible for making all
necessary arrangements for loading, unloading and other handling right from his
works up to the site and also till the, equipment is erected, tested and
commissioned. He shall be solely responsible for proper storage and safe custody
of all equipment.
26.0 Co-Operation with other Contractors and Consulting Engineers:
The Contractor shall agree to cooperate with the Owner's other Contractors and
consulting engineers and freely exchange with them such technical information as
is necessary to obtain the most efficient and economical design and to avoid
unnecessary duplication of efforts. The Engineer shall be provided with three
copies of all correspondence addressed by the Contractor to other Contractors
and Consulting Engineers of the Owner in respect of such exchange of technical
information.
Neither the inspection by the Owner or the Engineer or any of their officials,
employees, or agents, nor any order by the Owner or the Engineer for payment of
money or any payment for or acceptance of the whole or any part of the works by
the Owner or the Engineer, nor any extension of time, nor any possession taken
by the Engineer shall operate as a waiver of any provision of the contract, or of
any power herein reserved to the Owner or any right to damages herein provided
nor shall any waiver of any breach in the contract be held to be a waiver of any
other or subsequent breach.
No interim payment certificate of the Engineer, nor any Sum paid on account by
the Owner, nor any extension of time for execution of the works granted by the
Engineer shall affect or prejudice the rights of the Owner against the Contractor
or relieve the Contractor of his obligation for the due performance of the contract,
or be interpreted as approval of the works done or of the equipment furnished and
no certificate shall create liability for the Owner to pay for alterations,
amendments, variations or additional works not ordered, in writing, by the
Engineer or discharge the liability of the Contractor for the payment of damages
whether due, ascertained, or certified or not or any Sum against the payment of
which he is bound to indemnify the Owner, nor shall any such certificate nor the
acceptance by him of any sum paid on account or otherwise affect or prejudice
the rights of Owner against the Contractor.
29.1 VOID
29.2 VOID
29.3 VOID
During various stages of the work in pursuance of the contract, the Contractor
shall at his own cost submit periodic progress reports as may be reasonably
required by the Engineer with such materials as, charts, net works, photographs,
test certificates, etc. Such progress reports shall be in the form and size as may
be required by the Engineer and shall be submitted in at least Three (3) copies.
32.2 The Successful Bidder to whom the contract is awarded, shall be required to
furnish the contract performance guarantee in the form of a bank guarantee in
favour of the Owner as contract performance guarantee for faithful
performance of the contract in accordance with the Terms and Conditions
specified in the contract. The guarantee amount shall be equal to Ten percent
(10%) of the contract price OR Ten percent (10%) of the updated estimate cost if
the contract price is less than the updated estimate cost of the tender and the
guarantee shall be valid till expiry of 90 days after the end of the warranty period,
as referred to in clause 15.0, section-III, General Conditions of Contract GCC,
Volume-I.
a) The Contractor shall guarantee the successful and satisfactory operation of the
equipment supplied under the contract, as per the specifications and documents.
33.0 VOID
34.0 Payment:
34.1 The payment to the contractor for the performance of the works under the
contract will be made by the Owner as per the guidelines and conditions specified
herein and as per the payment terms stipulated vide clause no. 8.0 of Section –V,
Special Conditions of Contract- SCC, Volume-I. All payment made during the
contract shall be on account payments only. The final payment will be made on
completion of all works and on fulfillment by the Contractor of all his liabilities
under the contract.
The Contractor shall prepare and ‘Submit to the Engineer for approval a
break up of the contract price. This contract price break-up shall be inter-linked
with the agreed detailed activity chart of the Contractor setting forth his starting
and completion dates for the various key phases of Works prepared as per
condition in Clause 12.0 of Section-III, General terms & Conditions-GCC,
Volume-I. Any payment under the contract shall be made only after the
Contractor’s Price break-up is approved by the Engineer.
All costs, damages or expenses which the Owner may have paid, under the
contract for which the Contractor is liable, will be claimed by the Owner. All such
claims shall be billed by the Owner to the Contractor regularly as and when they
fall due. Such bills shall be supported by appropriate and certified vouchers or
explanations, to enable the Contractor to properly identify such claims. Such
claims shall be paid by the Contractor within thirty (30) days of the receipt of the
corresponding bills and if not paid by the Contractor within the said period, the
Owner may then deduct the amount, from any amount due or becoming due by
him to the Contractor under the contract or may be recovered by actions of Law
or otherwise.,
D. SPARES
36.0 SPARES:
36.1 All the spares for the equipment under the contract will, strictly confirm to
the specifications and documents and will be identical to the corresponding main
equipment /components supplied under the contract, and shall be fully
interchangeable.
36.2 All the mandatory spares covered under the contract shall be procured along
with the main equipment as a continuous operation and the delivery of the spares
will be effected along with the main equipment in a phased manner and the
delivery would be completed by the respective dates for the various categories of
equipment as per the agreed activity chart.
36.3 The quality plan and the inspection requirement finalized for the main
equipment will also be applicable for the corresponding spares.
36.4 The Contractor will provide the Owner with the manufacturing drawing,
catalogues, assembly drawings and any other document required by the Owner so
as to enable the Owner to identify the recommended spares. Such details will be
furnished to the Owner as soon as they are prepared but in any case not later
than six months prior to commencement of manufacture of the corresponding
main equipment.
36.5 The Contractor will provide the Owner with all the addresses and particulars
of his sub-suppliers while placing the order on vendors for items/
components/equipment, covered under the contract and will further ensure with
his vendors that the owner if so desires, will have the right to place order (s) for
spares directly on them on mutually agreed terms, based on offers of such
Vendors.
36.6.1The Contractor shall warrant that all spares supplied will be new and in
accordance with contract documents and will be free from defects in design,
materials and workmanship and shall further guarantees as under:
a) For any item of spares ordered or to be ordered by the owner for 3 years
operational requirement of the plant which are manufactured as a continuous
operation together with the corresponding main equipment / component, the
warranty, will be 12 months from the scheduled date of commercial operation of
the last unit of main equipment under the contract. In case of any failure in the
original component / equipments due to faulty designs, materials and
workmanship, the corresponding spares parts, if any, supplied will be replaced
without any extra cost to the Owner unless a joint examination and analysis by
the Owner and the Contractor of such spare parts prove that the defect found in
the original part that failed, can safely be assumed not to be present in spare
parts. Such replaced spare parts will have the same warranty as applicable to the
replacement made for the defective original part component provided that such
replacement for the original equipment and the spare replaced are again
manufactured together. The discarded spare parts will become the property of the
Contractor as soon as they have been replaced by the Contractor.
b) For the item of spares ordered / to be ordered by the Owner for 3 years
operation requirements of the equipment, which with the written approval of the
Owner, are not manufactured as a continuous operation together with the
manufacture of the corresponding main equipment / component, will be
warranted for 6000 hrs of trouble free operation, if used within a period of 18
months (reckoned from the date of delivery at Site) However, if such spare parts
are put to use after 18 months of the delivery, at site then the guarantee of such
spares will stand valid till the expiry of 36 months from the scheduled date of the
completion of commissioning of the last unit of equipment -or 6000 hrs of trouble
free operation after such spares are put in service, whichever is earlier.
For items of spares that may be ordered by the Owner to cover requirements
beyond 3 years of initial operation of the plant, the warranty will be till the expiry
of 6000 hrs of trouble free operation if used with in a period of 18 months from
the date of delivery at site. For items of spares that may be used after 18 months
from the date of delivery at site, the warranty period will be 12 months from the
date they are put to use or 6000 hrs of trouble free operation, whichever is earlier.
36.6.2 The warranty of spares that are not used within 18 months from
the respective dates of the delivery at site covered in para (b) & (c) above will,
however, be subject to the condition that all such spares have been stored
/maintained / preserved in accordance with Contractor’s standard recommended
practice, if any, and the same have been furnished to the Owner.
36.7 Void.
36.8 In addition to the mandatory spares, if the Owner further identifies certain
particular items of spares, the Contractor will submit the prices and delivery
quotations for such spares within 30 days of receipt of such request with validity
period for 6 months for consideration by the Owner and placement of order for
additional spares, if Owner so desires.
36.9 The Contractor shall guarantee the long term availability of spares to the
owner for the full life of the equipment covered under the contract. The Contractor
shall guarantee that before going out of production of spare parts of the
equipment, he shall give the Owner at least twelve (12) months advance notice so
that the latter may order his bulk requirement of spares, if he so desires. The
same provision will also be applicable to sub- contractor of any spares by the
Contractor or his Sub-Contractors. Further, in case or discontinuance of
manufacture of any spares by the Contractor or his Sub -Contractors, the
Contractor will provide the Owner, two years in advance full manufacturing
drawings, material specifications and technical information required by the owner
for the purpose of manufacture of such items.
36.11 The prices of all future requirements of items of spares beyond 3 years
operational requirement will be derived from the corresponding ex-works price at
which the order for such spares have been placed by Owner as part of mandatory
spares or recommended spares. Ex-Works order price of future spares shall be
computed in accordance with the price adjustment provisions covered under the
main contract excepting that the base indices will be counted from the scheduled
date of successful completion of trial operation of the last equipment under the
main project and there will be no ceiling on the amount of narration in the prices.
The above option for procuring future long term requirement of spares by the
Owner shall remain valid for a period of 5 years from successful completion of
commissioning last unit of equipment.
36.12 The Contractor will indicate in advance the delivery, period of the items
of spares, which the Owner may procure in accordance with above sub-clause. In
case of emergency requirements of spares, the Contractor would make every effort
to expedite the manufacture and delivery of such spares on the basis of mutually
agreed time Schedule.
36.14 It is expressly understood that the final settlement between the parties
in terms of relevant clauses of the bidding documents shall not relieve the
Contractor of any of his obligations under the provisions of long term availability
of spares unless otherwise discharged in writing by the Owner.
E. RISK DISTRIBUTION
37.2 In order to enable the Contractor to carry out his obligation under the
contract such as receipt at site, storage, erection, testing, etc., the Owner shall
hand over (wherever applicable) the goods to the Contractor against an indemnity
bond in the format enclosed as Annexure- VIII & IX.
37.3.2 This transfer of title shall not be construed to mean the acceptance
and the consequent "Taking Over" of equipment and materials. The Contractor
shall continue to be responsible for the quality and performance of such
equipment and materials and for their compliance with the specifications until
"Taking Over" and the fulfillment of guarantee provisions of this Contract.
37.3.3 This transfer of title shall not relieve the contractor from the
responsibility for all risks of loss or damage to the equipment and materials as
specified under the clause entitled ‘insurance' of this section.
37.3.4 In order to enable the contractor to carry out its obligation under the
contract such as receipt at site, storage, erection, testing, etc., the owner shall
hand over (wherever applicable) the goods to the contractor against an Indemnity
Bond in the format enclosed as Annexure VIII & IX. The Contractor shall be fully
responsible for the safety of the goods while the same are under his custody as
above.
37.4 The Contractor shall be fully responsible for the safety of all the
equipments/ materials while the same are under his custody as above until
“Taking Over of the Stations” by the Owner in accordance with Clause 9.0 of
Section-V, Special Conditions of Contract-SCC, Volume-I.
38.0 Insurance:
38.1 The Contractor at his cost shall arrange, secure and maintain all insurance
as may be pertinent to the works and obligatory in terms of law to protect his
interest and interests of the Owner against all perils detailed herein. The form and
the limit of such insurance as defined herein together with the under-writer in
each case shall be acceptable to the Owner. However, irrespective of such
acceptance, the responsibility to maintain adequate insurance coverage at all time
during the period of contract shall be of Contractor alone. The Contractor's failure
in this regard shall not relieve him of any of his contractual responsibilities and
obligations. The Contractor shall, however, be authorized to deal directly with
insurance company or companies and shall be responsible in regard to
maintenance of all insurance covers. Further the insurance should be in freely
convertible currency.
38.3 The perils required to be covered under the insurance shall include,
but not be limited to fire and allied risks, miscellaneous accidents (Erection risks)
Workman compensation risks, loss or damage in transit, theft, pilferage, riot and
strikes and malicious damages, civil commotion, weather conditions, accidents of
all kinds, etc. The Scope of such insurance shall be adequate to cover the
replacement/reinstatement cost of the equipment for all risks up to and including
delivery of goods and other costs till the equipment is delivered at site. The
insurance polices to be taken should be on replacement value basis and/or
incorporating escalation clause. Notwithstanding the extent of insurance cover
and the amount of claim available from the underwriters, the Contractor shall be
liable to make good the full replacement/ rectification value of all
equipment/materials and to ensure their availability as per project requirements.
38.4 All costs on account of insurance liabilities covered under the contract will
be on Contactor's account and will be included in Contract Price. However, the
Owner may from time to time, during the pendency of the contract, ask the
Contractor in writing to limit the Insurance coverage, risks and in such a case,
the parties to the contract will agree for a mutual settlement, for reduction in
contract price to the extent of reduced premium amount. The Contractor, while
arranging the insurance shall ensure to obtain all discounts on premium that
may be available for higher volume or for reason of financing arrangement of the
project.
38.5 The Clause entitled 'Insurance' under the Section-IV, Erection Conditions of
Contract-ECC, Volume-I covers the additional Insurance requirements for the
portion of the Works to be performed at the Site.
Under the contract, the Contractor shall be responsible for loss or damage to the
plant / structures until the successful completion of commissioning as defined
else where in the bid document.
40.1 In case the Contractor's performance is delayed due to any act of omission
on the part of the Owner or his authorised agents, then the Contractor shall be
given due extension of time for the completion of the works, to the extent such
omission on the part of the Owner has, caused delay, in the Contractor's
Performance of the Contract. Regarding reasonableness or otherwise of the
extension of time, the decision of the Engineer shall be final.
40.2 In addition, the Contractor shall be entitled to claim demonstrable and
reasonable compensation if such delays have resulted in any increase in cost. The
Owner shall examine the justification for such a request for claim and if
satisfied, the extent of compensation shall be mutually agreed depending
upon the circumstances at the time of such an occurrence.
All demurrage, wharfage, and other expenses incurred due to delayed clearance of
the material or any other reason shall be to the account of the Contractor.
42.1 Force majeure is herein defined as any cause which is beyond the
control of the Contractor or the Owner as the case may be, which they could not
foresee or with a reasonable amount of diligence could not have foreseen and
which substantially affects the performance of the contract, such as:
42.2 The Contractor or the Owner shall not be liable for delays in performing his
obligations resulting from any Force Majeure cause as referred to and/or defined
above. The date of completion will subject to hereinafter provided, is extended by
a reasonable time even though such cause may occur after Contractor's
Performance of obligation has been delayed due to other causes.
42.3 Bankruptcy:
43.1 The Owner reserves the right to suspend and reinstate execution of the
whole or any part of the works without invalidating the provisions of the contract.
Orders for suspension or reinstatement of the works will be issued by the
Engineer to the Contractor in writing. The time for completion of the works will be
extended for a period equal to duration of the suspension.
44.1 If the Contractor shall neglect to execute the works with due diligence
and expediency or shall refuse or neglect to comply with any reasonable Order
given to him, in writing by the Engineer in connection with the works or shall
contravene the provisions of the contract, the Owner may give notice in writing to
the Contractor to make good the failure / neglect or contravention complained of.
Should the Contractor fail to comply with the notice within thirty (30) days from
the date of serving the notice, then and in such case the Owner shall be at liberty
to employ other workmen and forthwith execute such part of the works as the
Contractor may have neglected to do or if the Owner shall think fit, without
prejudice to any other right he may have under the contract to take the work
wholly or in part out of the Contractor’s hands and re-contract with any other
persons or persons to complete the works or any part thereof and in that event
the Owner shall have free use of all Contractor’s equipment that may have been at
the time on the site in connection with the works without being responsible to the
Contractor for fair wear and tear thereof and to the exclusion of any right of the
Contractor over the same, and the Owner shall be entitled to retain and apply
balance which may otherwise be due on the Contract by him to the Contractor, or
such part of the works or of completing the works as the case may be. If the cost
of completing the works or executing a part there of as aforesaid shall exceed the
balance due to the Contractor, the Contractor shall pay such excess amount.
Such payment of excess amount shall be independent of the Penalty for delay,
which the Contractor shall have to pay if the completion of works is delayed.
44. 2 In addition, such action by the Owner as aforesaid shall not relieve the
Contractor of his liability to pay Penalty for delay in completion of works as
defined in Clause 14.0 of this Section.
44.3 Such action by the Owner as aforesaid the termination of the contract
under this clause shall not entitle the contractor to reduce the value of the
contract performance guarantee nor the time thereof. The contract performance
guarantee shall be valid for the full value and for the full period of the contract
including guarantee period.
45.1 The Owner reserves the right to terminate the contract either in part or in
full due to reasons other than those mentioned under clause entitled contractor's
default. The Owner shall in such an event give fifteen (15) days notice in writing to
the Contractor of his decision to do so. The Contractor, upon receipt of such
notice, shall discontinue the work on the date and to the extent specified in the
notice, make all reasonable efforts to obtain cancellation of all orders and
contracts to the extent they are related to the work terminated and terms
satisfactory to the Owner. Stop all further Sub-Contracting or purchasing activity
related to the work terminated, and assist the Owner in maintenance, protection,
and disposition of the works acquired under the contract by the Owner.
45.2 In the event of such a termination the Contractor shall be paid the amount
due to him for the work already under taken. If the Contractor is an individual or
a proprietary concern and the individual or the proprietor dies and if the
Contractor is a partnership concern and one of the partners dies, then unless the
Owner is satisfied that the legal representatives of the individual Contractor or of
the proprietor of the propriety concern and in the case of partnership, the
surviving partners, are capable of carrying out and completing the contract, the
Owner shall be entitled to cancel the contract as to its incomplete part without
being in any way liable to payment of any compensation to the estate of deceased
Contractor and/or to the surviving partners of the Contractor's Firm on account
of the cancellation of the contract except the amount which has already become
due and payable. The decision of the Owner that the legal representatives of the
deceased Contractor or surviving partners of the Contractor, cannot carryover and
complete the contract, shall be final and binding on the parties. In the event of
such cancellation the Owner shall not hold the estate of the deceased Contractor
and/or the surviving partners of the Contractor’s firm liable to damages for not
completing the contract.
If, at any time during performance of the contract, the Contractor or his Sub-
Contractor(s) should encounter conditions impending timely delivery of the goods
and for performance of services, the Contractor shall promptly notify the Owner,
in writing, of the fact of the delay, its likely duration and its cause(s). Upon receipt
of the Contractor's request, the Owner shall evaluate the situation and may, at
his discretion, extend the time for performance, in which case the extension shall
be ratified by an amendment to notification of Award/Contract Agreement.
46.3 In the events referred to in Sub-Clauses 46.1 and 46.2 above, the
parties shall mutually discuss to arrive at reasonable settlement on all issues
including amounts due to either party for the work already done on "Quantum
Merit" basis that shall be determined by mutual agreement between the parties.
48.2 If any dispute or difference of any kind whatsoever shall arise between
the Owner and the Contractor, arising out of the contract for the performance of
the works whether during the progress of the works or after its completion or
whether before or after the termination, abandonment or breach of the contract, it
shall, in the first place, be referred to and settled by the Engineer, who, within a
period of thirty, (30) days after being requested by either Party to do so, shall give
written notice of his decision to the Owner and the Contractor.
The Contractor shall prepare and submit every six months, a statement covering
payments claimed and the payments received vis-a-vis the works executed, for
reconciliation of accounts with the Owner. The Contractor shall also prepare and
submit a detailed account of Owner issued materials received and utilised by him
for reconciliation purpose in a format to be discussed and finalized with the
Owner before the award of contract.
50.1 The Owner or his representative shall have the right to inspect and/or
to test the goods to confirm their conformity to the contract. The special
conditions of contract and/or the technical specifications shall specify the
inspections and tests the Owner requires to be done and the place where they are
to be conducted. The Owner shall notify the Supplier/Contractor in writing on the
identity of any representatives authorised for these purposes.
50.3.2 The levy of re-inspection charges on the default firms when KPTCL
Officers are deputed for 2nd time for inspection of materials/equipment which
were not ready for inspection on first visit or materials rejected on first time as
follows:
(a) Rs.15000/- per man, per day + applicable CGST, SGST, IGST,
UTGST prevailing/ applicable on the day of inspection + any other Tax as per
statutory requirement.
/PLUS/
(b) Actual To & Fro charges by Air/Train/Bus. (as the case may be)
50.4 The Owner's right to inspect, test and, where necessary, reject the
goods after the arrival of the goods shall in no way be limited or waived by reason
of the goods having previously been inspected, tested and passed by the Owner or
his representative prior to the goods transportation.
50.5 Nothing in Clause 50.1 to 50.4 shall, in any way, release the Supplier /
Contractor from any warranty or other obligations under this contract.
51.0 Consortium :
51.1 In case of Bids where the Bidder has Associated with Consortium
partners and establishes satisfactory fulfillment of the qualification requirements
stipulated in the bid documents based on the experience of such Consortium,
then such Consortium shall be, jointly and severally, bound with the Bidder and
responsible to the Owner for successful performance of the contract. Such
document shall be addressed to the Owner and shall be signed by such
Consortium Partners. The model format of the above document is enclosed as
Annexure – XI for Consortium .
51.2 VOID.
52.0 Notices:
52.1 Any notice given by one party to the other, pursuant to contract, shall be
sent in writing by registered post with acknowledgement due or fax. Fax notice
shall be confirmed in writing to the address specified in the Contract and
Superintending Engineer Elecy. of Transmission Circle concerned.
52. 2 Notice(s) shall be deemed to have been duly and properly served upon
the parties hereto, if sent by any of the above-mentioned methods to the address
mentioned in the contract and Superintending Engineer Elecy. of
Transmission Circle concerned.