0% found this document useful (0 votes)
312 views

Iec60076 11 I1 (Ed2.0) en

Uploaded by

Ryan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
312 views

Iec60076 11 I1 (Ed2.0) en

Uploaded by

Ryan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

IEC 60076-11:2018/ISH1:2020 –1–

© IEC 2020

INTERNATIONAL ELECTROTECHNICAL COMMISSION


____________

IEC 60076-11
Edition 2.0 2018-08

POWER TRANSFORMERS –

Part 11: Dry-type transformers

INTERPRETATION SHEET 1

This interpretation sheet has been prepared by IEC technical committee 14: Power
transformers.

The text of this interpretation sheet is based on the following documents:

DISH Report on voting


14/1052/DISH 14/1054/RVDISH

Full information on the voting for the approval of this interpretation sheet can be found in the
report on voting indicated in the above table.

___________

14.3.2 Temperature-rise test

Question

The independent certification body in Poland "Instytut Energetyki" carries out the testing of
transformers or its inspectors witness this testing at the manufacturers' premises. The
description of resistance measurement during the temperature rise test has caused a dispute
between a manufacturer and the inspector on where exactly the resistance should be
measured. The inspector requested that the resistance be measured on "winding lead exits"
inside the enclosure, while the manufacturer argued for the measurement to be made on
"winding terminals" which in its opinion were the bushings on the enclosure cover.
IEC 60076-11:2018-08/ISH1:2020-07(en)

ICS 29.180
–2– IEC 60076-11:2018/ISH1:2020
© IEC 2020
Subclause 14.3.2.1 General, states:

The winding temperature rise shall be established by the rise in resistance method or
by superposition method. For the determination of the average winding temperature
rise the measured temperatures of the cooling air or of the water intake of the cooling
equipment shall be used.

For three-phase transformers, the resistance measurements shall be made between


the central and an outer phase line terminals.

NOTE When the temperature rise is performed it is advisable to measure the windings resistance close to the
windings.

Where should the measurements be made?

Interpretation

Testing of the winding resistance at transformer terminals (bushings) includes leadwork or


busbars and often also multiple connections. Because of this, the tested winding resistance
and its change due to heating is affected by the resistance of all these leads and connections.
Consequently, the derived winding temperature rise if measured at the transformer terminals
could be lower than if the winding resistance were tested directly on the winding lead exits.
That is why the standard suggests (in the NOTE) that measurement of the windings'
resistance be carried out close to the windings. That way, the accuracy of the indirect winding
temperature measurement by resistance is higher.

In the case of dry-type transformers without enclosures, it is possible to have access close to
the winding lead exits and not only to the transformer line terminals. Therefore,
measurements shall normally be made at such locations.

On the other hand, if the dry-type transformer is equipped with an enclosure, the resistance
measurement close to the winding lead exits requires opening the enclosure to have access
to carry out the test (hence, affecting the normal cooling efficiency of the unit). Nevertheless,
the advice to measure the resistance normally close to the winding lead exits holds. Limiting
the enclosure opening by using special through elements for the cabling and/or by closing the
required opening by temporary means as well as possible will minimize the impact on the
normal cooling efficiency.

You might also like