Chapter 9 Practice Problem Solutions
Chapter 9 Practice Problem Solutions
17. a.
Project A Project A
Cumulati Cumulati
Year Cash flow ve Cash flow ve
0 -364000 -52000
1 46000 -318000 25000 -27000
2 68000 -250000 22000 -5000
3 68000 -182000 21500 16500
4 458000 276000 17500 34000
b.
Project A Project A
Year Cash flow DCF Cumulative DCF Cash flow DCF Cumulative DCF
0 -364,000 -364,000 -52,000 -52,000
1 46,000 41,441 -322,559 25,000 22,523 -29,477
2 68,000 55,190 -267,368 22,000 17,856 -11,622
3 68,000 49,721 -217,647 21,500 15,721 4,099
4 458,000 301,699 84,052 17,500 11,528 15,627
Reinvestment approach:
In the reinvestment approach, we find the future value of all cash except the initial cash flow at the
end of the project. So, reinvesting the cash flows to Time 5, we find:
Time 5 cash flow = $16,900(1.104) + $20,300(1.103) + $25,800(1.102) + $19,600(1.10) – $9,500
Time 5 cash flow = $95,040.59
So, the MIRR using the reinvestment approach is:
Combination approach:
In the combination approach, we find the value of all cash outflows at Time 0, and the value of all
cash inflows at the end of the project. So, the value of the cash flows is:
Time 0 cash flow = –$47,000 – $9,500/1.105
Time 0 cash flow = –$52,898.75
Time 5 cash flow = $16,900(1.104) + $20,300(1.103) + $25,800(1.102) + $19,600(1.10)
Time 5 cash flow = $104,540.59
23. Given the seven-year payback, the worst case is that the payback occurs at the end of the seventh
year. Thus, the worst-case:
NPV is the PV of the inflows minus the PV of the outflows, so the NPV is:
The cash flows for the project are unconventional. Since the initial cash flow is positive and the
remaining cash flows are negative, the decision rule for IRR is invalid in this case. The NPV
profile is upward sloping, indicating that the project is more valuable when the interest rate increases
– this is absurd as value of a project should decline as discount rate or riskiness increases.