New & On-Going Power Projects
New & On-Going Power Projects
Kinyerezi III – The project involves China Power USD JV Company 2020
600MW gas fired construction of 300MW Investment 401million formed;
power plant simple cycle gas fired (CPI) Feasibility study
power plant for phase I at is under review
Kinyerezi and later
300MW combined cycle
in phase II to make a
total of 600MW under
PPP arrangement
Ruhudji – 358MW The project involves Financing not Estimated • Feasibility 2022
hydro power construction of 358MW yet secured Cost for study for
project hydro power plant on power plant power plant
Ruhudji River South- is US$ need to be
East of Njombe Town in 407.4M and updated as the
Njombe Region and US$ 53.2M available one
construction of 170 km for is of 1998.
400kV single circuit transmission • Procurement
transmission line (TL) line of transaction
from Ruhudji HPP to advisor is on
backbone substation at progress
Kisada.
Somanga Fungu The project involves Kilwa Energy USD 365.6 Investor 2018
320MW Gas Fired construction of 210MW - IPP Million working with
Power Plant simple cycle gas fired banks to achieve
power plant for phase I at financial closure
Somanga - Kilwa and
later 110MW combined
cycle in phase II to make
a total of 320MW
Rumakali – The project involves Financing not Cost of HPP Feasibility study 2022
222MW hydro construction of 222MW yet secured estimated to completed in
power project hydro power plant on US$ 344M 1998 and
Rumakali River West of and US$ therefore need to
Njombe Town and 44.22M for be updated
construction of 150 km transmission
400kV single circuit line.
transmission line (TL)
from Rumakali HPP to
Mbeya
250-350MW The project involve Financing not Project cost Pre-feasibility 2018
Somanga gas fired construction of 250MW yet secured will be study has been
power plant combined cycle gas fired but WB confirmed completed.
power plant at Somanga - financed after Procurement of
Kilwa under PPP procurement feasibility Transaction
arrangement of TA to study Advisor to
package the package the
project project is in the
final stage
Ngaka 200MW The project involves Financing not Project cost Evaluation of 2019
coal fired plant construction of 200MW yet firmed will be expression of
coal fired power plant confirmed interest for
and the transmission line after consultancy
from Ngaka to feasibility service is done
Makambako study
Mchuchuma The project involves Financing not Estimated Feasibility study 2020
300MW coal fired construction of 300MW yet secured cost USD for power plant
plant coal fired power plant 645.75millio need to be
and the transmission line n updated.
from Mchuchuma to Procurement of
Makambako transaction
advisor is on
progress
Ngozi 200MW This project involves Financing not Estimated Feasibility study May, 2021
geothermal plant development of 600MW yet secured cost for phase is on progress
geothermal plant at I: USD
Ngozi, Mbeya. 821million
Construction is in two
phases; 200MW for
Phase I and 400MW for
Phase II and construction
of 220kV T/L of 18km
from Ngozi - Mwakibete
Mbeya S/S.
50MW Kisaki This project involves Financing not Estimated Project Concept May, 2021
Geothermal development of 50MW yet secured cost: USD submitted
geothermal plant and 293million
utilize heat in the brine
for direct uses at Kisaka,
Morogoro and
construction of 220kV
T/L of 100km from
Kisaka - Kidatu,
Morogoro.
50MW Luhoi, This project involves Financing not Estimated Project Concept May, 2021
Rufiji Geothermal development of 50MW yet secured cost: USD submitted
geothermal plant and 266million
utilize heat in the brine
for direct uses at Luhoi,
Rufiji and construction of
220kV T/L of 18km from
Luhoi - Kibiti.
45MW Malagarasi The project involves Not yet Estimated Feasibility 2020
hydropower plant Engineering, secured cost: USD Study
Procurement, Installation African 149.5million completed.
and Commissioning of Development Solicitation of
45MW Malagarasi Bank(AfDB) financing in
hydropower plant which has booked in progress
will be implemented at their portfolio
the Malagarasi River to co-finance
Kigoma-Region. with French
Development
Agency(AFD
)
400kV Iringa – The project involves IDA, AfDB, USD 470 Construction of March 2017
Shinyanga construction of 657km of JICA, EIB Million T/L is 84%
transmission 400kV Transmission and Korea completed and
project (Backbone) Line, upgrade of EDCF that of
substations at Iringa, substation is
Dodoma, Singida and 67% completed
Shinyanga and
implementation of rural
electrification along the
T/L
400kV North East The project involves GoT - 15% USD GoT is soliciting 2017
Grid construction of 400kV, Exim Bank 692.7million funds for
682 km of Transmission of China – 85 financing the
Line from Kinyerezi to % 15% of the
Arusha via Chalinze and Contractor: contract value of
Segera with associated TBEA the project
Substation. The project
also involves
construction of 220kV
T/Ls from Kibaha to
Bagamoyo and from
Segera to Tanga
220kV The project involves SIDA & GoT USD Distribution 2017
Makambako – construction of 250 km 111.4million component 20%
Songea of 220kV Transmission completed
transmission line Line, construction of new
220/33kV substation at
Madaba and Songea,
upgrade of Makambako
substation, construction
of 33kV, 900 km of
distribution lines and
connection of 2,270 new
customers in 120 villages
in Ruvuma and Njombe
Regions
400kV North West The project involves African Total Solicitation of 2018
Grid Mbeya – construction of 1,148km Development Estimated funds for
Sumbawanga – of transmission lines and Bank(AfDB) Cost is 664 construction
Mpanda – Kigoma associated substations as has booked in MUSD.
- Nyakanazi an extension of national their portfolio
grid to North-Western to co-finance
part of the country from with French
Mbeya to Nyakanazi via Development
Sumbawanga, Mpanda Agency(AFD
and Kigoma. The )
proposed project will
enhance grid connection
to North West of
Tanzania and
decommission expensive
liquid fuel power plants
at Mpanda, Kigoma,
Ngara, Biharamulo,
Sumbawanga, Kasulu
and Kibondo. This
project will be done in
phases. Phase I from
Mbeya – Sumbawanga
340km; Phase II from
Nyakanazi – Kigoma –
Mpanda 568km and
Phase III from
Sumbawanga – Mpanda
240km.
400 kV Singida- The project involves AfDB, JICA USD 258.82 Valuation of 2018
Arusha construction of 400kV, million properties for
transmission line 414.4km of transmission compensation
line from Singida to has started
Arusha (Tanzania -
Kenya Interconnector)
and construction of
400/220kV Singida &
Arusha Substations
400 kV Chalinze- The project involves Financing not Estimated Procurement of 2018
Dodoma construction of 400kV, firmed USD 175 Consultant for
transmission line double circuit 350km of million feasibility study
transmission line from is in progress
Chalinze to Dodoma and
rural electrification along
the line
220 kV The project involves Arab Bank USD Contract signing 2017
Bulyanhulu-Geita construction of 55 km of for Economic 30million with Consultant
transmission line 220kV transmission line Development for project
from Bulyanhulu to in Africa supervision is
Geita, extension of (BADEA), underway
Bulyanhulu substation, OFID & GoT
construction of new
substation at Geita and
construction of 33kV
lines 115km for
electrification of 15
villages in Geita District
220kV T/L Geita – The project involves KfW, AFD, Euro Contract signing 2017
Nyakanazi construction of 144 km EU & GoT 29million & with Consultant
transmission Line of 220kV transmission TZS 5billion for project
line from Geita to supervision is
Nyakanazi and underway
implementation of rural
electrification along the
line
400kV T/L Mtwara The project will comprise Financing not USD 231.1m, Pre-feasibility 2020
– Somanga, 253km construction of 253km of yet secured the actual completed in
transmission line from cost will be May, 2015. Full
Mtwara to Somanga established feasibility is
Fungu. It will enhance after needed.
evacuation of power feasibility
from the proposed study.
Mtwara power plant to
Somanga and link the
South Regions to the
National Grid System.
Project for The project aims on Government Euro 21.8 Construction December,
Reinforcement of improvement of of Finland million 80% 2015
Power Distribution power supply for the and USD completed
in Dar es salaam City of Dar es 1.5
Region Salaam. The project million
involves construction
of the 33/11kV
Distribution Control
Centre (DCC),
construction of New
City Centre (NCC)
Substation with 2 x
50 MVA
transformers and
erection of 132kV
underground cable
from Ilala - New City
Centre
90MW Rusumo This is a shared World Bank, USD 340 Procurement 2021
Falls Hydropower power project AfDB and Million of
project – 220kV between Tanzania, GoT for power Supervision
Transmission Line Rwanda and Burundi. plant and Consultant
Component It involves USD 35 for T/L has
construction of million been
90MW hydropower. for T/L finalized
Each country will while for
construct its T/L power plant
220kV from the is on
power plant and will progress.
take 27MW. The Acquisition
length of of way leave
transmission line on corridor for
Tanzania side from Rusumo –
Rusumo to Nyakanazi
Nyakanazi is 98.2km. 220kV TL is
also in
progress.
220kV Masaka - This project will Financing not Estimated Part of the 2018
Mwanza comprise 640km of yet secured cost for T/L is under
Transmission Line Transmission line Tanzania development
from Masaka Part is i.e. Geita -
(Uganda) to Mwanza USD 279. Nyakanazi -
- Mabuku S/S 275Millio Rusumo.
(Tanzania). The aim n KfW has
of this project is to shown
strengthen security of interest to
supply, connecting of facilitate
off grid part in North upgrade of
West Tanzania and the
facilitate feasibility
interconnection and study. MoU
trade among EAC. between two
countries is
underway to
be signed.
400kV Somanga- The project will World Bank Estimated Compensati 2018
Kinyerezi comprise cost is on payment
construction of USD 150 in progress.
198km of million
transmission line
from Somanga Fungu
to Kinyerezi. It will
enhance evacuation
of power from the
proposed Somanga
fungu power plant to
Dar es Salaam and
link the South
Regions to the
National Grid
System.
Proposed 400kV • This project will Financing not • Estimate • Environmen 2019
Chalinze to comprise 350km of yet secured d cost is tal Impact
Dodoma transmission line with 217MUSD Assessment
transmission line. associated substations. but the Certificate
This is one among • It will enhance actual cost (EIA) has
the BRN projects evacuation of power will be been issued
which is in line from Dar es Salaam established by NEMC.
with the where power plants are after • Contract
Government 2025 located to central part feasibility negotiation
Vision. of the country. study. between
• It will be linked by TANESCO
the Backbone and M/S
transmission line which SMEC for
is the interconnector for Consultancy
Zambia-Tanzania and Services has
Kenya. been held.
• It will enhance Consultancy
security and reliability services is
of supply expected to
be completed
in year 2016.
• The
Consultant
will produce
Full
Feasibility
Study for the
Project and
thereafter the
accurate cost
will be
known.
Proposed 400kV • This project will Financing not • Estimate • 2015 Pre- 2021
Mtwara to comprise 253km of yet secured d cost is feasibility
Somanga transmission line from USD study is
Transmission Line Mtwara to Somanga 231,074,23 available
fungu. 8 but the
• It will enhance actual cost
evacuation of power will be
from the proposed established
Mtwara power plant to after
Somanga and link the feasibility
South Regions to the study.
National Grid System.
• TANESCO desires to
the implementation of
the Project to improve
the power supply
condition in Tanzania
and create an
opportunity for bilateral
electricity trade with
neighboring countries