EMB MC 2020 18 Adoptation of DENR 2019 16 For ECC Processing of NON ECP Under Build Build Program ONAR
EMB MC 2020 18 Adoptation of DENR 2019 16 For ECC Processing of NON ECP Under Build Build Program ONAR
Executive Summary
Project Description
Page 1 of 14
Sections /
Content Page #
Subsections
1.1 Project Location a) Map showing sitio, barangay, municipality, province, region
and Area boundaries, vicinity, proposed buffers surrounding the area and
Primary & secondary impact areas
I.2. Project Rationale • Cite and focus on the need for the project based on national and
regional/local economic development in terms of contribution to
sustainable development agenda or current development thrusts.
• Describe the justification for the Project with particular reference
made to the economic and social benefits, including employment
and associate economic development, which the project may
provide. The status of the project should be discussed in a regional
and national context.
I.3. Project a) Cite criteria used in determining options for facility siting,
Alternatives development design, process/technology selection, resource
utilization and discuss how the decisions on the preferred options
were made.
Siting: Present the process and criteria for the selection of the alignment
Discuss alternative project locations including factors significant to the
selection such as severity of impacts, perception of affected
communities with regards to project, ancestral domain issues, land
classification, etc.
Design Selection: Discuss factors significant to design selection in
consideration to project’s adverse impacts to environment
Resources: Alternative sources of power, water, raw materials and
other resources needed including factors significant to the selection
such as supply sustainability and climate change projections. In case
the project includes reclamation activity, provide source of filling
materials.
Page 2 of 14
Sections /
Content Page #
Subsections
4. Terminal Building
5. Control Tower
6. Hangar
7. Parking
Other Infrastructure Projects:___________________
Page 3 of 14
Sections /
Content Page #
Subsections
See Table 3 for the list of key environmental impacts which shall be subjected to assessment.
The assessment shall done using the prescribed approach/method and in relation to the
corresponding baseline characterization in the primary and secondary impact areas (as
determined using the Guidelines in Annex 2-2 of the Revised Procedural Manual (RPM) for
DAO 2003-30 or succeeding issuances). The sampling and measurement plan used shall be
discussed. Likewise, the assessment should be done for the various phases of development (i.e.
pre-construction, construction and operation) and should consider climate change projections
and disaster risks based on existing natural hazard information. For all maps, include overlays
of project area footprint, show sensitive/critical receptors and sampling points for baseline data
(indicate geographical coordinates). In conclusion, the residual and cumulative impacts shall be
assessed.
Appropriate mitigation/management measures should be specified for each of the identified key
impacts (Table 3). Appropriate climate change adaptation and disaster risk reduction
measures/options shall likewise be thoroughly discussed. The impact management plan should
be summarized using at the minimum, the format in Annex 2-17 of RPM for DAO 2003-30
4. Environmental Risk Assessment (ERA) & Emergency Response Policy and Guidelines
The level of coverage and type of document required shall first be determined based on Annex
2-7e of RPM for DAO 2003-30.
6.1.Self-Monitoring The monitoring plan shall be summarized using Annex 2-20 of RPM
Plan for DAO 2003-30 or succeeding issuances as template.
Statement on Proponent’s policies to implement the abandonment plan described in Item 1.7
and to formulate and submit procedures for Rehabilitation/ Decommissioning/Abandonment
within a timeframe specified in the ECC.
Present the organizational scheme of the proponent including line of command and reporting
procedures as well as manpower complement and relationships with other operating
departments.
Page 4 of 14
Table 3. Key Environmental Impacts to be included in the Assessment and Formulation of
Management and Monitoring Plan to be reflected in the EIS
✓ For completeness, page numbers should be
provided upon submission of the EIS
Baseli
Impact Monit
Baseline Data Parameter Required Assessment ne Mgmt.
List of Key Impacts Analys oring
Requirements Methodology/Approach Condit Plan
is Plan Remarks
ions
I. Land
1.1.3 Impact in existing Determine if the project area Identify and assess
land tenure issue/s is under CARP or with impact in terms of land
CADC / CADT / CALC/ tenure issues in relation
CALT, with to project
IFMA/CBFMA, within implementation
COC, within MPSA or other
tenurial instruments and
identify corresponding
existing tenure issues
including presence of
informal settlers.
1.2
Geology/Geomorphology
Page 5 of 14
✓ For completeness, page numbers should be
provided upon submission of the EIS
Baseli
Impact Monit
Baseline Data Parameter Required Assessment ne Mgmt.
List of Key Impacts Analys oring
Requirements Methodology/Approach Condit Plan
is Plan Remarks
ions
1.3 Pedology
Page 6 of 14
✓ For completeness, page numbers should be
provided upon submission of the EIS
Baseli
Impact Monit
Baseline Data Parameter Required Assessment ne Mgmt.
List of Key Impacts Analys oring
Requirements Methodology/Approach Condit Plan
is Plan Remarks
ions
Relate discussions to
estimated GHG
1.4.2 Threat to existence Summary of endemicity / emissions and possible
and/or loss of local conservation status carbon sequestration
species program/s
2. THE WATER
2.1
Hydrology/Hydrogeology
2.1.1 Change in drainage Drainage map (also showing Identify and assess
morphology / inducement local drainage project impact on the
of flooding/ Reduction in system/infrastructures); change in drainage
stream volumetric flow Historical flooding/drought morphology/local
occurrences, stream flow drainage system and
measurements/estimates; resulting effects of
Delineation of watershed flooding pattern in the
/sub-watersheds/ floodplain; project area and
and identification of surrounding. Include
aquifers if any climate projections
effects on flooding.
Relate discussions to
item 3.1.1
2.2 Oceanography (applicable to projects with jetty/port and/or subsea structures that will change the bathymetry in the
area)
Page 7 of 14
✓ For completeness, page numbers should be
provided upon submission of the EIS
Baseli
Impact Monit
Baseline Data Parameter Required Assessment ne Mgmt.
List of Key Impacts Analys oring
Requirements Methodology/Approach Condit Plan
is Plan Remarks
ions
Page 8 of 14
✓ For completeness, page numbers should be
provided upon submission of the EIS
Baseli
Impact Monit
Baseline Data Parameter Required Assessment ne Mgmt.
List of Key Impacts Analys oring
Requirements Methodology/Approach Condit Plan
is Plan Remarks
ions
2.5 Marine Ecology (applicable if project involves activities, discharges or with structure in marine waters)
3.1
Meteorology/Climatology
3.1.1 Change in the local Monthly average rainfall Identify and assess
micro-climate e.g. local and temperature of the area; project impact in terms
temperature Climatological of change in the local
normals/extremes; Wind micro- climate change.
Page 9 of 14
✓ For completeness, page numbers should be
provided upon submission of the EIS
Baseli
Impact Monit
Baseline Data Parameter Required Assessment ne Mgmt.
List of Key Impacts Analys oring
Requirements Methodology/Approach Condit Plan
is Plan Remarks
ions
Page 10 of 14
✓ For completeness, page numbers should be
provided upon submission of the EIS
Baseli
Impact Monit
Baseline Data Parameter Required Assessment ne Mgmt.
List of Key Impacts Analys oring
Requirements Methodology/Approach Condit Plan
is Plan Remarks
ions
Sources of information:
UNESCO, National
Museum (NM), National
Historical Commission of
the Philippines (NHCP),
National Commission for
Culture and Arts (NCCA)
and the Local Government
Units (LGUs) in the project
area and other UN or
National Publications
Page 11 of 14
✓ For completeness, page numbers should be
provided upon submission of the EIS
Baseli
Impact Monit
Baseline Data Parameter Required Assessment ne Mgmt.
List of Key Impacts Analys oring
Requirements Methodology/Approach Condit Plan
is Plan Remarks
ions
• recreational
facilities / sports
facilities
Page 12 of 14
Level of Coverage:
Refer to Annex 2-7e of the RPM For EIS, check type of report to be submitted
for DAO 2003-30 prior to Operation:
Level 2 (QRA Quantitative Risk
Required) Assessment(QRA)
Level1 (Emergency HAZOP
Plan based on hazard
analysis)
Risk Screening Level
Page 13 of 14