K2S-CW230907-BA6008-00003 - A01 - Commissioning Test Procedure For Contrl Valve

This document provides information for the installation of backup power and ancillary work for the K2S Project by Morpol Engineering Services Limited. It includes a project background describing the need for backup power supply to four oil and natural gas host communities. The document defines terms, lists abbreviations, and references related documents. It also outlines the general and detailed scope of work, work methodology, workforce, health and safety requirements, site support services, prerequisites, and commissioning test procedures.

Uploaded by

Azeta Robert
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
246 views13 pages

K2S-CW230907-BA6008-00003 - A01 - Commissioning Test Procedure For Contrl Valve

This document provides information for the installation of backup power and ancillary work for the K2S Project by Morpol Engineering Services Limited. It includes a project background describing the need for backup power supply to four oil and natural gas host communities. The document defines terms, lists abbreviations, and references related documents. It also outlines the general and detailed scope of work, work methodology, workforce, health and safety requirements, site support services, prerequisites, and commissioning test procedures.

Uploaded by

Azeta Robert
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

The Shell Petroleum Development Company of Nigeria Ltd

Originat
Originator Morpol Engineering Services Limited

Project Installation of Back-up Power and


nd Ancillary
Work for K2S Project.

Document Title

Document Number K2S-CW230907-BA6008-00003

DCAF Control ID NA

Security Classification Restricted

Owning Discipline BA Construction..

Month/Year January/2021

Proprietary Information: This document contains proprietary information and may not be partly or wholly
reproduced without prior written permission from Shell Petroleum Development Company.
Company

Revision Date Description Originator Checker Approver

K2S-CW230907- BA6008-00003 Page 1 of 13

This document is controlled electronically and is uncontrolledwhen printed


ADDITIONAL AGREEMENT/APPROVAL RECORD
Party RefInd Name Sign Date

Revision Philosophy

All revisions for review will be issued at R01, with subsequent R02, R03, etc as required.

All revisions approved for issue or design will be issued at A01, with subsequent A02, A03,
etc as required.

Documents approved for Construction will be issued at C01, C02, and C03 respectively.

Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc.

Narrative sections revised from previous approved issues are to be noted in the table
below and/or highlighted in the RH margin (using the appropriate revision status) thus: |
A02

Previous revision highlighting to be removed at subsequent issues.

Drawings/diagrams revised from previous approved issues are highlighted by 'clouding'


the affected areas and by the use of a triangle containing the revision status.

Revision History

Revision No. Date of Reason for change


issue

K2S-CW230907- BA6008-00003 Page 2 of 13

This document is controlled electronically and is uncontrolledwhen printed


Table of Contents

TITLE PAGE ................................................................................................................... 1

ADDITIONAL AGREEMENT / APPROVAL RECORD ............................................2

1. GENERAL INFORMATION .....................................................................................4

Project background .......................................................................................................4

Purpose .........................................................................................................................5

2. DEFINITIONS / ABBREVIATIONS........................................................................5

Definitions .....................................................................................................................5

Abbreviations ................................................................................................................5

Company supplied documents .....................................................................................5

3. REFERENCE DOCUMENTS ...................................................................................6

4. GENERAL SCOPE OF WORK ..................................................................................6

5. DETAILED SITE ACTIVITIES ................................................................................6

6. GENERAL WORK METHODOLOGY ................................................................. 7-9

7. WORK FORCE MATRIX ......................................................................................... 10

8. HSE REQUIREMENTS .......................................................................................... 10

9. SITE SUPPORT SERVICES .................................................................................... 10

10. PRE-REQUISITES ..............................................................................................10-11

11. TEST AND CALIBRATING EQUIPMENT / TOOLS ....................................11-12

12. COMMISSIONING TEST PROCEDURE ....................................................... 12-13

K2S-CW230907-KOLS1-IN6180-00003

Page 3 of 14

This document is controlled electronically and is uncontrolledwhen printed


1.0 GENERAL INFORMATION
1.1 PROJECT BACKGROUND
The Backup Power Supply to Kolo Creek Oil & NAG Host Communities Project is being
undertaken to supply safe, reliable back up electric power to the four (4) SPDC’s Kolo Creek
Oil and NAG host communities of Imiringi, Elebele, Otuasega and Oruma in the event of
power outages from the Kolo Creek Power Station (KCPS) turbines. This will help to sustain
SPDC’s Freedom to Operate (FTO), secure K2S 400MMScf/d NAG production to Soku GP,
ensure socio/economic integration and empowerment of the local communities. Currently,
SPDC supplies fuel gas to KCPS to power their gas turbine generators for supply of electric
power to Bayelsa State including the four host communities and Shell’s Oil and Gas facilities at
Kolo Creek via two 33kV transmission feeders (C and D). Feeder C supplies power to SPDC,
Otuasega, Imiringi, Elebele and other non- SPDC Oil & NAG host communities, while Feeder
D supplies power to Oruma and other non- SPDC Oil & NAG host communities. Each of
these communities has functional town distribution network (TDN), 33kV/415V transformer
substations and feeder panels. There are gang isolators at various points of the 33kV
transmission network that enable isolation of selected sections of the power transmission and
distribution networks for maintenance and load shedding purposes. Owing to community load
demand growth and following the enrolment of Oruma community to the list of K2S project
host communities, the originally proposed generator (1.2MVA) meant to serve all the
communities is now grossly inadequate as KCPS confirmed that the four communities current
total peak load stands at 3MW (3.75MVA). Design has allowed for a load growth factor of 10%
over a period of nine years, arriving at an installed capacity of 6.0MW (7.5MVA).

Three nos. of 2.027 eMW 11KV 50 Hz gas generators with combined output of 6.081 eMW
will be installed and voltage stepped up to 33KV via a 8.0MVA 11KV/33KV transformer at the
Kolo Creek Oil & NAG Manifold into a 1.2km 33kV underground power cable feeding an
indoor 33kV, Ring Main Unit (RMU) at KCPS. An outgoing feeder from the RMU will supply
into the existing KCPS overhead transmission line. The proposed backup power is sufficient to
meet both the present combined community load of 3.75MVA (as advised by KCPS) and
forecasted load growth for nine years. Backup power supply will be tripped at a set point of 5.6
eMW corresponding to 93% generator loading.

K2S-CW230907- BA6008-00003 Page 4 of 13

This document is controlled electronically and is uncontrolledwhen printed


As part of execution for the backup power there are other miscellaneous works related to
close-out of outstanding Kolo Creek to Soku (K2S) Project (punch list items) and K2S wells Rig
intervention.

1.2 PURPOSE:
The purpose of this statement is to ensure that all works required to be performed are
carried out following requisite standards, established and approved fundamental
principles in order to ensure high quality job delivery and from the work procedures
contained therein develop a safe method of carrying out the entire work.

2.0 DEFINITIIONS AND ABBREVIATIONS


2.1 DEFINITIONS
COMPANY - Shell Petroleum Development Company
COMPANY Representative - Means any authority or person appointed in writing
by COMPANY to witness the test to be carried out

CONTRACTOR - Refers to MORPOL Engineering services, the party


which carries out the commissioning test, calibration,
equipment and services.
2.2 ABBREVIATIONS
DWG - Extension name assigned to AutoCAD file format drawings.
MORPOL - MORPOL engineering services.
PSI - Pound force per square inch
BAR - 100 kilopascals
CAL - Calibrate
JHA - Job Hazard Analysis
PPE - Personnel Protective Equipment
PTW - Permit to Work
Amp - Ampere
2.3 COMPANY SUPPLIED DOCUMENTS
Data sheet
P & ID

K2S-CW230907- BA6008-00003 Page 5 of 13

This document is controlled electronically and is uncontrolledwhen printed


3.0 REFERENCE DOCUMENTS
PROJECT
DESCRIPTION
SPECIFICATION
ISO 4126-5:2013(EN) Safety devices for protection against excessive pressure
00-ES-800-006 Standard specification for control valves
ATEX ’95 Standard for working on equipment in Explosive atmosphere

4.0 GENERAL SCOPE OF WORK


The work activity shall be carried out by qualified and trained personnel. It shall be
performed in compliance with international standards of preference and design
specification where available.

The work shall be carried out on the following Instrument devices:


Fuel Gas Scrubber
2nos Globe control valves

5.0 DETAILED SITE ACTIVITIES


The activities required to be performed for the execution of this job shall include but
not limited to the following:
 Mobilization, HSES and Demobilization.
 Documentations (PTW, JHA, MS etc)
 Test equipments set up
 Test results Record taking
 Testing and calibration

The scope of commissioning testing will be executed as per the following main
documents:
i. Work Schedule (See the Ms Project and/or Ms Excel)
ii. Job Hazard Analysis
iii. Work permit
iv. Check sheets & Test report forms
v. As-built Drawings/Documents P&ID

K2S-CW230907- BA6008-00003 Page 6 of 13

This document is controlled electronically and is uncontrolledwhen printed


6.0 GENERAL WORK METHODOLOGY
In general, the followings define the work procedure to be adopted for the
commissioning test
6.1 Permit-To-Work (PTW) system
The objective of the PTW system is to ensure that all work activities are carried out in
a safe manner by specifying and putting appropriate controls in place to prevent any
accidents that can potentially jeopardize the lives of people, asset and the
environment at worksites. The Permit to Work (PTW) system ensures that all persons
responsible for worksite safety are aware of the controls and work activities to be
carried out, and have given their written approval for the execution of that work.
Additionally, the PTW also provides instruction to the person(s) carrying out the
work, of the conditions under which work may be started and completed.
The Permit-To-Work system achieves these objectives by:
 Complying with Company approved standards during work.
 Identification of hazards and putting in place adequate precautionary measures
Prior to start of work
 Providing awareness to the person responsible for the work and the competent
person who approves the work.
 Monitoring of work progress and reporting process.
Permit-To-Work is mandatory for all non-routine tasks during the work. The Client
system shall be used for all activities to ensure a consistent approach to work safely
and that proper consideration is given in identifying the hazards and risks exposure
prior to start of work in a systematic and disciplined approach.
The PTW shall reflect the following:
 Description of detailed work to be carried out and identification of the source of
energy and hazards involved.
 Preparation of JHA and identification of appropriate equipment for the work.
 Description of the precautionary controls to be put in place.
 Approval of relevant complementary certificates for test and safety equipment
related to the task.
 Ensuring the involvement of competent persons i.e. permit holders, Supervisor.
 Providing appropriate PPE (Personal Protective Equipment) required for the
task.
 Competent person to check and ensure that the PTW is properly authorized by
appropriate persons and fully completed before work can start.
 Ensuring proper housekeeping and satisfactory conditions at worksite.
 Ensuring a formal closure of the permit on completion of each task.

K2S-CW230907- BA6008-00003 Page 7 of 13

This document is controlled electronically and is uncontrolledwhen printed


6.2 Planning
Good and proper work planning for the site activities is a critical process for safe
execution. We shall prepare and submit our work plan in advance (at least a day
earlier) to client before the start of work.
Planning shall be a continuous process whereby works are planned in advance and
submitted to provide adequate time for detailed review and approval by appropriate
persons.
MORPOL Discipline CSU Lead is responsible for the daily planning and reporting
of progress of their work activities to client CSU team.

6.3 Daily Toolbox Meeting


Toolbox Talks/meetings shall be performed daily at the commencement of every
activity/task and shall include the requirements to review the Safe Work Procedure,
associated hazards, potential overlap of operations and responsibilities, adherence to
PTW requirements and other necessary measures.
The discipline commissioning engineer (or alternates) shall chair the meetings with
attendance by HSE officer of the client.

6.4 HSE Awareness Training


The practical aspects of the site activities require the full co-operation and safety
consciousness of all staff. Site specific safety induction shall be conducted for all
personnel before they are allowed to start work on site. This induction session
includes awareness of the activities and risks involved, access control, roles and
responsibilities, emergency response and general safety awareness. It is the
responsibility of MORPOL to ensure that all personnel attend the awareness
training or safety induction at site where applicable and maintain up-to-date records
of attendance for audit purposes.

6.5 Recording and Monitoring


Recording of the test activities and results will be maintained by MORPOL as a
component of the PTW. MORPOL is responsible for ensuring that all permits are
managed properly for monitoring and recording purposes.

6.6 Emergency Response and Preparedness


In general, the Client’s Emergency Response procedure shall be strictly followed in
the event of an emergency at the worksite. The client’s Asset Team Coordinator
shall act as the single point person in managing any emergency situation and will
provide all the necessary assistance to evacuate the victim, if required, for further
medical treatment. He will also act as single-point to communicate with client’s
Emergency Control Centre (ECC) if required.

K2S-CW230907- BA6008-00003 Page 8 of 13

This document is controlled electronically and is uncontrolledwhen printed


6.7 Emergency Response (ER) Drill
CONTRACTOR is responsible to ensure that all members of staff are adequately
trained and familiar with the ER procedure during any emergencies. A joint
(MORPOL, client) emergency drill shall be carried out prior to commencement of
site works. From there onwards, emergency drills shall be conducted at contractor’s
work area regularly to ensure that member of staff are familiar with the standard
emergency response procedure. This is also essential to enhance their preparedness
and effectiveness in responding to an emergency situation. Drills shall be carried out
regularly, recorded (Putting into consideration the time duration of the drill) and
weakness which shall be improved upon in future drills.

6.8 Safety Induction


CLIENT is responsible to ensure that all MORPOL personnel undergo the safety
induction, detailing the control system and actions to be taken in event of an alarm,
muster points, safety equipment, escape or evacuation routes, etc. This is to ensure
that the staff will act in a systematic manner to emergency situations. It is the
responsibility of CLIENT to maintain an updated register of the personnel who
have undergone safety induction.

6.9 Personnel Protective Equipment (PPE)


All personnel on site shall wear appropriate PPE throughout the duration of the
work
The site HSE officer shall ensure compliance with the above and report any
deviation.

The following constitutes the minimum PPE requirement for the Installation works:
 Safety shoes
 Coverall
 Personnel floatation device
 Hard gloves
 Ear muffs/protector
 Hard hats
 Eye goggles
6.10 Weather Monitoring
Due to the season and possibly dangerous adverse weather conditions, there shall
be a daily review of the weather forecast (Storm watch, wind and lightning
monitoring) to confirm to the site and for work on site. At any indication of adverse
weather conditions, the site coordinator shall suspend work / or the transit to site
until the weather improves.

K2S-CW230907- BA6008-00003 Page 9 of 13

This document is controlled electronically and is uncontrolledwhen printed


7.0 WORKFORCE MATRIX
POSITIONS NO.
Commissioning Lead 1
Commissioning Support Electrical 1
Commissioning Support Instrumentation 1
Commissioning Support Mechanical 1
Vendors 5
TOTAL 9

8.0 HSE REQUIREMENTS


 Prior to commencement of the commissioning test, a detailed Job Hazard
Analysis (JHA) shall be conducted detailing all potential hazards, risks and their
control measures. All workers will sign the attendance sheets acknowledging
their participation.
 Ensure that all the correct PTW have been obtained.
 Ensure that test areas are barrier off and with caution signs placed strategically
also to put in place close supervision on the job.
 All workers to wear correct PPE at all times.
 All personnel to be instructed on procedures to be used.
 Ensure that workers are familiar with control valve test activities.
 First Aid facility to be made available on site.

9.0 SITE SUPPORT SERVICES


 On site control valve testing facilities shall be provided.
 Temporary power supply (TLS) shall be provided if needed and maintained by
MORPOL.
 Safety activities, which include toolbox talk, unsafe act audit, safety meetings,
hazards Identification and control, will be co-ordinated by the project
supervisor/Lead

10.0 PRE-REQUISITES FOR TESTING AND CALIBRATION


Prior to start of site activities, we shall confirm the following:
 All personnel, equipment and machinery for the execution of the control
valves commissioning testing works shall be duly certified fit by client and
pre-mobilized by Client, prior to mobilization to site.

K2S-CW230907- BA6008-00003 Page 10 of 13

This document is controlled electronically and is uncontrolledwhen printed


 Following the successful pre-mobilization of the above equipment, these will be
moved to site and other equipment will be moved under a security escort to be
provided by MORPOL.
 All journey management procedures as outlined in the journey management plan
will be followed.
 Materials, Tools and Equipment will be transported from MORPOL camp to
station where activities are taking place. Security will be provided by MORPOL
during these journeys.
 MEDEVAC rescue vehicles shall be pre-mobilized and be placed on standby
on-site to evacuate any sick/wounded staff to hospital.
 Familiarization with drawings, Scope of Work and Procedures.
 Appropriate Permits to Work are obtained.
 Commissioning personnel agreed for the project are available on site.
 All equipment and procedures are agreed and are in place.
 Ensure that test areas are demarcated and barrier off with caution sign in
place.

11.0 CALIBRATION AND TEST EQUIPMENT / TOOLS


In the execution of this work, the contractor shall use modern test equipment that is in
compliance with the ISO 17025, DPR Regulations, current DEP/International
standards and which shall be suitable in obtaining the tolerance required by the
reference specification for the devices and the equipment shall be operated by qualified
persons who are experienced in their usage.
All test equipment shall be duly calibrated and certified as recommended by client and
subjected to periodic checks throughout the duration of the project in order to
maintain the required accuracy. Calibration of equipment/devices shall be witnessed by
client and a calibration report shall be made available to client prior to commencement
of work.
List of test equipment and tools required for this work shall be but not limited to:
 Instrument toolbox
 Mechanical toolbox
 Loop calibrator
 Hart Communicator (375 or 475)
 Compressor for Air Instrument
 Rotameter
 Pressure Gauge
 Block/Needle Valve
 Flange

K2S-CW230907- BA6008-00003 Page 11 of 13

This document is controlled electronically and is uncontrolledwhen printed


 Tubing and fitting
 Hydro pump
 Barton Recorder (optional)
12.0 COMMISSIONING TEST PROCEDURE

 PROCEDURE (CONTROL VALVE TESTING)


- Visually inspect
- Verify control valve data against data sheet
- Mount the control valve on the line. Ensure that gaskets are used.

Operational Procedure
- Apply Instrument Air for Supply pressure to Regulator 67 CFRS
- Adjust Regulator 67CFRS until pressure as per datasheet for
Supply Pressure to POSITIONER
- Set controls from FAR to provide current Input Signal (4-20mA) to
POSITIONER
- Verify Current Input Signal to Stroke test ( Low Travel – Mid Travel - High
Travel )
- See Percentage of Actual Travel (0-100%) to match with
Current input Signal (4-20mA) on data sheet

- Prior to testing, the valve shall be completely assembled, and all

K2S-CW230907- BA6008-00003 Page 12 of 13

This document is controlled electronically and is uncontrolledwhen printed


instrument and accessories mounted according to the requisition or
assembly processing document.
- Verify the valve in Fully Closed position
- Verify Inlet pressure must not exceed maximum Inlet body valve.
- Slightly Open block valve to the inlet body valve 50 psig ( referenced ANSI
B16.104
- Check Rotameter for actual leak, leakage must not exceed the
Maximum allowable Leak on datasheet

12.1 RECORDS

Test document shall list the following:


a) Calibration body/authority
b) Signature of MORPOL rep
c) Test document number
d) Equipment description (make, type etc)
e) Manufacturers serial number and/or MORPOL unique number
f) Test date
g) Next Test due date
h) Tolerances of accuracy
i) Remarks – Accept/Reject/Comments
j) Reference to the Test Instrument Standard

A file will be maintained which will include the calibration certificates and
register. The file will be subject to monthly review by the respective
Construction and QA Managers.

List of Equipment and Recommended Calibration Intervals

Accuracy & Tolerance Calibration Frequency


Equipment Description
Limits Max.
Control Valve (CV) 12 months

Accuracy and tolerance level to be advised