K2S-CW230907-BA6008-00003 - A01 - Commissioning Test Procedure For Contrl Valve
K2S-CW230907-BA6008-00003 - A01 - Commissioning Test Procedure For Contrl Valve
Originat
Originator Morpol Engineering Services Limited
Document Title
DCAF Control ID NA
Month/Year January/2021
Proprietary Information: This document contains proprietary information and may not be partly or wholly
reproduced without prior written permission from Shell Petroleum Development Company.
Company
Revision Philosophy
All revisions for review will be issued at R01, with subsequent R02, R03, etc as required.
All revisions approved for issue or design will be issued at A01, with subsequent A02, A03,
etc as required.
Documents approved for Construction will be issued at C01, C02, and C03 respectively.
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc.
Narrative sections revised from previous approved issues are to be noted in the table
below and/or highlighted in the RH margin (using the appropriate revision status) thus: |
A02
Revision History
Purpose .........................................................................................................................5
2. DEFINITIONS / ABBREVIATIONS........................................................................5
Definitions .....................................................................................................................5
Abbreviations ................................................................................................................5
K2S-CW230907-KOLS1-IN6180-00003
Page 3 of 14
Three nos. of 2.027 eMW 11KV 50 Hz gas generators with combined output of 6.081 eMW
will be installed and voltage stepped up to 33KV via a 8.0MVA 11KV/33KV transformer at the
Kolo Creek Oil & NAG Manifold into a 1.2km 33kV underground power cable feeding an
indoor 33kV, Ring Main Unit (RMU) at KCPS. An outgoing feeder from the RMU will supply
into the existing KCPS overhead transmission line. The proposed backup power is sufficient to
meet both the present combined community load of 3.75MVA (as advised by KCPS) and
forecasted load growth for nine years. Backup power supply will be tripped at a set point of 5.6
eMW corresponding to 93% generator loading.
1.2 PURPOSE:
The purpose of this statement is to ensure that all works required to be performed are
carried out following requisite standards, established and approved fundamental
principles in order to ensure high quality job delivery and from the work procedures
contained therein develop a safe method of carrying out the entire work.
The scope of commissioning testing will be executed as per the following main
documents:
i. Work Schedule (See the Ms Project and/or Ms Excel)
ii. Job Hazard Analysis
iii. Work permit
iv. Check sheets & Test report forms
v. As-built Drawings/Documents P&ID
The following constitutes the minimum PPE requirement for the Installation works:
Safety shoes
Coverall
Personnel floatation device
Hard gloves
Ear muffs/protector
Hard hats
Eye goggles
6.10 Weather Monitoring
Due to the season and possibly dangerous adverse weather conditions, there shall
be a daily review of the weather forecast (Storm watch, wind and lightning
monitoring) to confirm to the site and for work on site. At any indication of adverse
weather conditions, the site coordinator shall suspend work / or the transit to site
until the weather improves.
Operational Procedure
- Apply Instrument Air for Supply pressure to Regulator 67 CFRS
- Adjust Regulator 67CFRS until pressure as per datasheet for
Supply Pressure to POSITIONER
- Set controls from FAR to provide current Input Signal (4-20mA) to
POSITIONER
- Verify Current Input Signal to Stroke test ( Low Travel – Mid Travel - High
Travel )
- See Percentage of Actual Travel (0-100%) to match with
Current input Signal (4-20mA) on data sheet
12.1 RECORDS
A file will be maintained which will include the calibration certificates and
register. The file will be subject to monthly review by the respective
Construction and QA Managers.