ACCIDENT PREVENTION PROGRAM
Zone: Assessment Date : Assessment Team:
Activity : Transformer Installation Risk Assessment No.: Assessment Author :
HAZARD EFFECT Reduced
TASK HAZARD C L RISK MITIGATED BY C L Alarp
( Consequences ) Risk
All Power tools to be handled carefully
to avoid personal injuries, wherever
Power tools Electric shock Serious injury possible, safeguards shall be fitted to the
equipment . only trained & certified
operators to use power tools.
Emergency Phone numbers shall be
posted in site office and educate the
Fire Protection Personnel Injury & Damage employees to use the emergency
Fire Hazard numbers in case of emergency.
& Prevention to Property
Adequate number of Fire Extinguishers
shall be provided and fire watch
personnel shall be assigned.
All workmen to be properly trained
before taking part in any electrical work.
ground fault circuit interrupters are to
Electrical works Fall Hazard Personnel Injury be installed properly on all circuits. All
activities shall be planned and with work
permits approved by Safety dept.
Toilet must be available to employees
Sanitation & Environmental Health & Environmental At each work location shall be available.
housekeeping Hazard hazard To be kept clean by regular routine
service. Disposal to be arraigned daily.