Build 170 24 Build Right Concrete Formwork Basics
Build 170 24 Build Right Concrete Formwork Basics
BUILD
RIGHT Concrete formwork
basics
Concrete can be formed into a variety of intricate shapes with interesting surface
BY CONCRETE finishes, but this relies on quality formwork. Whether using traditional boxing or
NEW ZEALAND INC
proprietary formwork, it’s important to get the basics right.
Design of formwork
In addition to vertical loads and horizontal pres-
sures (from wet concrete), allowance must be
oiling for reuse. for beam sides and walls are 2–6 days depending
●● Textured rubber linings that can be used with on temperature conditions, but this may vary.
any formwork system. It is essential to ensure Removal of any soffit formwork is related to
the rubber is well fixed to the backing. Using structural propping and should be covered in the
Proprietary formwork system. the correct release agent is also important. specification to allow the concrete’s required
●● Thin plastic sheeting requiring backing support strength.
Sheeting and decking can be used to produce a smooth surface
Sawn or dressed timber can be used as sheeting finish. Many uses can be achieved. However, Proprietary systems
and decking. It can eliminate studs on slab work the impervious face of the liner can trap air As many formwork requirements are common
when supported on runners or stringers. Edges bubbles and so form blow holes. across projects, a number of reusable proprietary
may be square cut or tongue and groove. To formwork systems have been developed.
prevent grout loss, joints should be sealed with a Release agents These mostly modular systems are designed
flexible foamed strip. Most form materials require the application of for speed and efficiency, with health and safety
The advantages of using exterior grade plywood a release agent to the surfaces that will be in built in. There are a variety of main systems:
as a form supported by timber framing include it: contact with the concrete to make removal of ●● Table form/flying form – large preassembled
●● is rapidly fixed the formwork easier. As well as effecting release, units, often creating an entire bay of a
●● can provide large smooth surface areas release agents can also influence the concrete suspended floor slab, offer mobility and rapid
without joints surface appearance and durability. erection for projects with consistent or
●● has high resistance to impact When selecting the release agent, consider the repetitive layouts.
M
●● System column formwork – these are modular, Other developments include: is placed the slab, which then ties the floor
Y
allowing quick installation of column forms on ●● lightweight, adjustable formwork metal/ elements together.
site and are available in a variety of materials. plywood interlocking forms that can Permanent formwork is not restricted to hori- CM
This type of formwork comes with different incorporate handrails and full access platforms zontal surfaces. Systems are available that make MY
internal surfaces depending on the finish to give a complete formwork/shuttering and it possible to pour vertically and create walls. CY
●● Horizontal panel systems – these lightweight ●● proprietary metal boxing brackets to support vertical permanent formwork made of expanded
K
modular systems provide versatile solutions wide horizontal planks for slab edge formation polystyrene blocks into which reinforcing steel
on site and can be used for most types ●● proprietary one-piece adjustable brackets that and concrete are placed.
of construction. They are generally made incorporate locating pins specifically design for
from aluminium, high-tensile steel or use with polystyrene pod slabs on ground Slab on grade
fibreglass. ●● proprietary interlocking aluminium panels There are polystyrene and plastic dome systems
●● Vertical panel systems – these crane-lifted supported by galvanised steel pipes that are available for residential or light commercial
modular panel systems are commonly used clamped together to provide a slab edge form. slab on grade and are sometimes referred to
on building sites to form vertical elements as permanent formwork, although the slab
and usually consist of a steel frame with Permanent formwork edging tends to be formed using timber or steel
plywood, steel, plastic or composite facing Permanent formwork remains in place after the formwork. However, there are slab edge-forming
material. concrete has gained adequate strength. It may systems available that incorporate bracing ele-
●● Jump form – not reliant on support from other contribute to the load-carrying capacity of the ments to eliminate form deflection.
parts of the building or permanent works, this structure or simply contain the concrete while it is
system supports itself on the concrete cast being cast and gaining its initial strength. Pay attention to the details
earlier and is suitable for construction of multi- Permanent forms for suspended floors are Time spent before placing concrete to ensure the
storey vertical concrete elements. typically: exactness of formwork design and fabrication
●● Slip form – these are like jump form, but the ●● interlocking long-span profiled metal trays details is never wasted. In addition to health and
formwork is continuously raised vertically to installed over a supporting structure – the safety considerations, design and fabrication
extrude a reinforced concrete section and is floor slab is then cast over the metal form shortcuts can prove troublesome and costly, with
suitable for construction of core walls in high- ●● timber infill between spanning precast significant hours and money required to remedy
rise structures. concrete beams (rib and infill) over which defects.