02 Project Management
02 Project Management
WPL_J401
Tasks
The following diagram shows tasks listed in a typical project in Microsoft Project.
When building a house, for example, you may need to seek council approval, prepare the site works,
lay the slab, erect the walls, and so on. These are the tasks required to construct the house. The
time taken to complete each task is called its duration. The project is completed when all of the
tasks have been accomplished.
Resources
Tasks can only be accomplished by providing resources. Resources can take the form of people,
money, equipment, facilities or supplies. The following diagram shows resources listed in a typical
project in Microsoft Project.
The duration of tasks may be affected by the number or resources that can be directed towards it.
For example, it may take one painter three days to paint your house. Three painters however, may
take only one day. This type of task is known as resource driven, because the number of resources
influences the duration of the task.
Other tasks are fixed in duration. For example, when building a house on a concrete slab you may
need to wait five days for the concrete to cure before erecting the frame. No matter how many
resources you provide, you will still need to wait the five days.
Your project therefore, is made up of tasks and resources.
The Gantt chart uses horizontal bars to represent task duration across a period referred to as the
timescale. Any tasks that are on the critical path appear with red horizontal bars, whilst those tasks
that have slack time appear in blue.
Network Diagram
A Network Diagram chart is used in Microsoft Project to display the task relationships graphically.
Each task is shown as a part of a network of nodes. Their relationships are drawn using connecting
lines and arrows. The following diagram shows an example of a Network Chart in Microsoft Project.
NOTES: