SSG Appendix D - Minimum Information - v1
SSG Appendix D - Minimum Information - v1
1.0
25 October 2019
Sewerage Companies accept that in some circumstances informal pre-planning applications are
made in connection with prospective developments prior to land purchase with minimal detailed
information available. Sewerage Companies are keen to ensure that such informal discussions
continue and the minimum information requirements in the SSG will not be applied in circumstances
where they are clearly not relevant to the Customer’s request. Where however a proposal raises
strategic issues for the Sewerage Company, it may require wider consideration of sites allocated
within the catchment and any site specific measures for the particular site.
Include evidence of existing drainage connections and flow rates (if available)
Drainage Strategy or Statement and layout plan (showing discharge point) (minimum)
Ground investigation report to show infiltration could be utilised on the site – or use of BGS
data where permeability results not available
Flood Risk Assessment (where required under NPPF guidelines) or statement for site and
associated risk
Confirm if system is proposed for adoption as part of S104
Approved version
1.0
25 October 2019
The Sewerage Company acknowledges the duties and responsibilities of the Lead Local Flood
Authority and the Local Planning Authority to determine planning applications and approve
measures for the disposal of surface water. This should be carried out in consultation with the
Sewerage Company where disposal involves any discharge to the public sewer system.
The right of connection under S106 WIA 1991 is acknowledged with current arrangements setting
out the principles of a size for size connection from April 2018.
*Strategic assessment may be required for a large or complex site before a Stage 2 application can
be considered. The strategic Assessment can be requested at anytime before the S104 application is
applied for. However, we understand that any site may be complex dependent upon the Customer’s
previous experience/knowledge and would also welcome all requests for strategic assessments.
Large or complex sites can be defined under the following criteria;
• Multiple phases
• Multiple landowners/Customers
• Multiple points of connection
• Pumped discharges
• Storage components
This allows the Customer to provide assurances as part of their planning obligations in order to
ensure that the maintenance regime proposed will be satisfactory over the lifetime of the asset.
The following information will enable Sewerage Companies to assess the asset over its intended
lifetime. It also enables the Sewerage Company to assist in dealing with control of flows at ground
level, rather than by providing extensive underground infrastructure.
Responses to this section will enable the Sewerage Company to understand what the development
site is capable of, the restrictions that can affect site drainage, where existing and proposed flows
will arise and be managed and whether the ground is able to accept the flows. Dealing with all these
elements at an early stage allows them to be managed through to completion.
The intention of the Pre-Design strategic assessment is to deal with the intricate site-specific details
for anything that is proposed for adoption - whether that’s taking into account a system that needs
cyclical operational and maintenance requirements, discussions over ownership or considering the
standards needed) before a formal S104 application is requested. Provision of this information at an
early stage will permit the Sewerage Company to determine whether the details proposed will meet
the requirements for adoption and allow the Sewerage Company to provide early advice without the
Customer having to apply for a S104.
Approved version
1.0
25 October 2019
Flood Risk Assessment (where required under NPPF guidelines) or statement for site and
associated risk
Drainage Strategy or Statement and layout plan (showing discharge point including rates)
(minimum)
Ground investigation report to show infiltration could be utilised on the site or BGS data
where permeability results not available
Confirmation of principles of ownership, accessibility, operational requirements of
components
Pre-design assessment
1. Contact with the
Customer will be made to
ascertain if a discussion
or a meeting is relevant
2. Agree a date and time for
a meeting (if required)
Pre-Design response
1. Be based on the expected Information received at
development parameters this stage can only be
discussed and or relevant to the basic
provided information provided
2. Provide an indication of
design, adoption, legal
requirements to support
the future S104
Application
Approved version
1.0
25 October 2019
Table 2.1 - S104 Initial assessment information list – Have you provided?:-
Ownership details
Longitudinal Sections
Hydraulic Calculations
Comments /
Information provided by Sewerage
Information provided by Customer standard
Company
required
S104 Application
Before the application is submitted a Pre-
design strategic assessment can be
requested.
supplied or addressed.
3. Offer a strategic assessment meeting,
where relevant
4. Detail the nominated contact to
support communication about the
initial assessment
5. Confirm any reference number for the
application
S104 Application Re-submission
As a minimum the re-submission of the Any information
details should contain any data not that has
previously supplied as part of the initial previously been
application, including any additional supplied will not
details discussed where LP or TS need to be re-requested
be considered: to progress the
1. Consider any recommendations made initial technical
from the initial submission. assessment,
2. Re-submitted fully Completed S104 unless significant
Application form changes to the
3. Programme for start date design are
4. Planning details required before
a re-submission
5. Ownership details
is made.
6. Site location plan
7. Site/Engineering layout plan
Requests to
8. Longitudinal Sections discuss the
9. Access schedule(s) proposals may
10. Pumping station details be requested to
11. Special Asset or Component drawings assist with the
12. Any Manufacturers details relevant to application.
the application
13. Details of who will be preparing the
standard Agreements
14. Contact details for mediation
companies
The documents supplied should contain
the information listed in Table 2.1 and 2.2
- S104 Application details and
information (relevant to missing
information).
Ensure any changed drawing are
crosschecked for accuracy before
(re)submitting
S104 Technical Assessment will check to
ensure that
1. The details are in accordance with the
Design and Construction Guidance
2. If required, agree an extension
3. any local practice or Technical Standard
details are adhered to
Approved version
1.0
25 October 2019
Table 2.2 S104 - Application details and information Key comments to be incorporated
within details supplied
Must Supply with application in RED and must supply before Technical Acceptance all details should be provided before
the Agreement will be entered into.
Programme Construction start date Not necessary but relevant if timescales are key
of works Programme of works
and start
date
Confirmation of permission to discharge
surface water
Confirmation for discharge of Highway
drainage
Agreed Flow rate(s) for any system
Flood Risk Assessment or statement for site
Planning / and associated risk, including any Ground
design investigation report and results OR SI to show
details infiltration could be utilised on the site
Drainage Strategy or Statement and layout
plan (showing discharge point including rates)
Run-off rates and attenuation quick estimates
Confirmation of principles of ownership,
accessibility, operational requirements of
components
Customer details
Landowner details
Ownership Principal designer details
details Contractor details
Surety details
Adjoining landowner details
Site Plan showing the boundary of the site Minimum 1:2500 scale
Location Benchmark details OS Map reference
plan
Approved version
1.0
25 October 2019
Full set of Design & Layout Details for Kerb lines and service strips/margins at least
Development 1m away from centreline of sewer and 0.5m
Key plan for multiple sheets away from outside edge of manhole.
Minimum 1:500 scale
North Point A manhole is required when serving more than
Site contours 6 properties.
Show coal mining details (if applicable)
Show Source Protection zones (if applicable) Manholes at every change in direction, gradient
Show flood areas or pipe size.
Show flood exceedance paths on and offsite
details Maximum distance between manholes of 90m
Coloured and indexed in accordance with
sector guidance to show lengths of adoptable A 3m wide vehicular access road to within 5m
Site Layout system of a maintainable asset/component
Plan Green boundary of land owned by Customer
New Pipe lengths coloured showing the Soakaways a minimum of 5m away from any
direction of flow, pipe material, gradient, structure or boundary
shape and size
Pipe lengths should have a self-cleansing A turning area for a 4,000 gallon tanker (if
regime required)
Existing pipes shown black detailing direction
of flow, pipe material, gradient, shape and Manhole details could be provided within a
size table
Cover and invert levels of all manholes and
inspection chambers including existing
manholes where connections are proposed
Protected strips where systems are not
located within a public highway
Scaled at 1:100 vertical & 1:500 horizontal Show gravity sewers connected soffit to soffit,
Show existing ground level where there is a change in pipe size
Proposed cover and invert levels and any Offline surface water should be laid invert to
backdrops invert
Longitudinal
Show the pipe material, strength, diameter Eliminate unnecessary crossovers of pipes
Sections
and bedding Show filled ground that has been / will be
backfilled
Show any foundation details in relation to
sewers
Show manhole Type, shaft and chamber size
and depths, overall depth as well as cover and
invert level(s) of all incoming and outgoing
Manhole &
pipes
Inspection
Show manhole cover type, shape, size and
Chamber
depth
Schedule
Number of incoming pipes
General arrangement drawings for bespoke
manholes
Full set of Hydraulic Calculations for sewerage Matches details on drawings and calculations
Hydraulic
systems
Calculations
Flow Full set of manufacturers details Matches details on drawings and calculations
Control Including head flow characteristics See Local Practice requirements for full design
systems and construction requirements
Full set of manufacturers details or request Details correlate on all drawings and
Pumping conditional assessment* but must provide calculations
station cover level, invert level, head of rising main, See Local Practice requirements for full design
details flow rate) and construction requirements
Full set of relevant manufacturers details or Matches details on all correlating drawings and
Component request conditional assessment details
details Ground condition details to support system See Local Practice requirements for full design
proposed and construction requirements
Approved version
1.0
25 October 2019
Mediation Contact details of Mediation Company The Sewerage Company will be able to provide
details Address details a list of independent Mediation Companies
Technical Acceptance – Written confirmation that the full system proposed for adoption has met the
requirements for the system to form part of a S104 Agreement for the whole of the specified site.
Conditional Assessments –Certain elements of the system may take longer to gain Technical Acceptance; like
pumping stations and storage components. In such a case, Conditional Acceptance can be provided to allow
the agreed element of the system to be constructed on site (certain fundamental details will need to be
agreed before Conditional Acceptance will be applied (additional charges will apply)) but the outstanding items
can continue to be assessed until Technical Acceptance is given. It is noted that for the remaining elements of
the site the Technical Acceptance must be granted within 6 months of the Conditional Acceptance being
issued, otherwise the Conditional Acceptance no longer stands.
Approved version
1.0
25 October 2019
Table 3.1 S104 - Agreement details and information – relevant for any system.
Standard Agreements can be generated by the Customer instead of asking the Sewerage Company to
produce them, taking into consideration the same requirements. Where Agreements are generated by the
Customer, they must inform the Sewerage Company that they will be preparing the Agreements. Where a
Customer will prepare the Agreements there will be a requirement for the Sewerage Company to check the
details contained within the Agreements to ensure that they are standard Agreements.
Full set of Design details for Development that were technically accepted
Full Set of correctly coloured layout details for Development that were technically accepted (land
registry acceptable)
Any charges
Mediation details
Comments /
Information provided by Customer Information provided by Sewerage Company
standard required
Receive a technical Acceptance for the
design of the prospectively adoptable
system advising of the details needed
for the Agreement
The Customer
Provide the details to be incorporated may choose to
within the standard S104 Agreement as create the
detailed in Table 3.1 Agreement details standard S104
and information Agreements but
For the S104 Agreement this will be a must confirm to
standard Agreement with no alterations the Sewerage
allowed to be made. Company that this
is their intention
Agreement details check Details of all
A check of the details to be incorporated parties to the
within the standard S104 Agreement will be Agreement are
made:- needed.
1. Sufficient number of drawings provided
Once Technical
2. The drawings have been coloured and
Acceptance of a
Approved version
1.0
25 October 2019
1. Customer pays the relevant inspection and administration fees, set by the Sewerage
Company, to allow inspections to be undertaken by the Sewerage Company. The
Sewerage Company’s response will be for information only and is without prejudice to
the requirements it may have as part of the full Technical Acceptance process.
2. Customer shall provide plan showing which sewers he wants inspected prior to full
Technical Acceptance
3. Where the site has a diversion incorporated within the application NO works on the
diversion should take place until the Agreement is in place and signed by all parties.
Note that there is a risk that because of the partial nature of the approval, changes may be required
as part of Technical Acceptance, resulting in laid sewers needing to be altered to meet the
requirements of the Technically Accepted system.
Comments /
Information provided by Customer Information provided by Sewerage Company
standard required
Receive a Conditional or technical
Acceptance for the design of the
prospectively adoptable system advising
that the system meet the DCG, LP and
TS.
Provide the details to enable an early The only system
start to be confirmed that can be
requested to be
1. Ensure that the system has inspected is the
element that has
received a Conditional or
met the required
Technical Acceptance. specifications and
2. Provide the coloured plan and has been provided
all details needed coloured conditional
showing the accepted system Acceptance or
which needs to be inspected. Technical
3. Complete the Early start Acceptance. The
remainder of the
request form
system must be
4. Provide the full set of details as progressed
requested to arrange a Pre- towards Technical
Approved version
1.0
25 October 2019
Comments /
Information provided by Customer Information provided by Sewerage Company
standard required
Ensure that the S104 Agreement is signed
by all parties or the Full Technical
Acceptance and or/the Conditional
Acceptance or has been granted and the
Early start request form has been signed
Ensure all charges have been paid in
accordance with charges document
Request a Pre-start inspection before any
works on the prospectively adoptable
system commences tying it in with your
programme of works.
1. Complete a Pre-start request form
2. Confirm contact details
3. Provide a copy of the F1O Notice
4. Confirm start on site date
5. Provide a schedule of activity
6. Ensure charges are provided with
request
7. Allow 14 Days to allow for Pre-Start
Inspection to be arranged
Pre-start inspection check
1. Check through the information
provided within the pre-start
inspection request
Approved version
1.0
25 October 2019
Confirmation that any variations have been confirmed and agreed – Minor or Major
Full set of manufacturers details for anything that needs to be operated or maintained
Comments /
Information provided by Customer Information provided by Sewerage Company
standard required
Ensure that the works are in accordance
with the drawings contained within the
S104 Agreement or any minor or major
variations and that the details in table 5.1
are completed/provided
Ensure that the site has the sufficient
properties connected to the system or the
agreed discharge rate(s) to allow the Pre-
Maintenance to be requested
Request a full or part Pre-Maintenance
inspection when all of the works ready to
be progressed
1. Complete a Pre-maintenance
application form
2. Confirm contact details
3. Provide a full set of correctly coloured
As-Built drawings and details in
accordance with agreed details
4. Provide any specific manufacturers
details to support the constructed
system
5. Confirm number of properties
occupied
Approved version
1.0
25 October 2019
Comments /
Information provided by Customer Information provided by Sewerage Company
standard required
Ensure that the system is ready for the
Final Inspection and has been working and
not causing any major operational issues
Request a Final inspection
1. Complete a Final Inspection form
2. Confirm contact details
3. Provide details of any operational
issues
4. Confirm any access requirements have
been provided
5. Health and Safety file for site
Final inspection check
1. Check through the information
provided within the Final inspection
request to ensure everything has
been supplied
2. Check to ascertain if there have been
any operational issues
3. Check to make sure all charges have
been paid
4. Check any local practice requirements
have been supplied/completed
5. Confirm if an inspection can be
arranged
6. Advise if a Handover inspection will
also be required
Cannot arrange an inspection
1. Confirm that the Final inspection
cannot be carried out
2. Define the details as to why this
cannot be completed
3. Call the applicant or email if unable to
gain contact to confirm that we are
unable to arrange the Final inspection
Cannot arrange the Final inspection
1. Receive the details confirming why the
inspection cannot be carried out
2. Look into the site details and complete
the items needed to enable the Final
inspection
3. Re-request the Final inspection
Can arrange a Final inspection
1. Contact the applicant via the details
supplied
Approved version
1.0
25 October 2019
2. Arrange an inspection
3. Confirm the date, time and which
inspector/team member(s) will be
attending
4. Receive confirmation of whom will be
attending the inspection on behalf of
the Customer
Final Inspection
The inspection will be used to give
acceptance for vesting the site, the
inspection will include:
1. Checking to make sure the system is
working correctly
2. No evidence of operational issues.
3. Any on-site access requirements are
provided
Can arrange the Final inspection
1. Receive contact to arrange the
inspection date and time
2. Confirm the personnel details of who
will be at the Final inspection for the
site.
3. See the details that will be reviewed at
the meeting
4. Before Final inspection. Arrange for
the system proposed to be progressed
is ready for inspection
Final Inspection
The inspection will:
1. Confirm all remedial works are
complete
2. Confirm any changes to the As-built
drawings to reflect what has been
constructed on site
3. Define any access requirements
For sites where any items listed above are
not quite complete/outstanding the
customer will receive a full list of details of
the items that need to be completed
For sites where all works are complete
and the drawings reflect what was
constructed the Provisional certificate will
be relevant for issue
Final remedial works /changes to details
The customer will need to review the
details discussed at the Final inspection and
arrange for the items to be finished to
standard.
1. Complete all remedial works on site
Approved version
1.0
25 October 2019
Version Control
Version Number Date Change Purpose Author
1.0 25 October 2019 Approved by Ofwat Water UK