Abstract: With the extensive improvement of infrastructure in China in the past ten years, the
soft soil foundation is becoming more and more complicated. Therefore, the improvement of
soft soil foundation treatment has become a difficult problem that today's engineering
designers have to face. This paper systematically reviews the development of soft soil
foundation treatment technology in our country, and emphatically introduces the development
process of foundation treatment at home and abroad, especially in our country in recent years,
which embodies the cross and comprehensive application of various foundation treatment
technologies and forms a unique composite reinforcement technology.
Key words: soft soil foundation treatment; Overview; Composite reinforcement technology;
Composite foundation
Introduction
With the continuous development and progress of society, especially in China's coastal cities, it is
even more necessary to build high-rise buildings, docks and roads on weak foundations. In this
process, more and more complicated soft soil foundation treatment problems will be encountered, thus
providing opportunities and challenges for the development of new soft soil foundation treatment
technologies. In the past ten years, the development of soft soil foundation treatment has been mainly
carried out in three directions: first, gradually from a single reinforcement method to a multi-method
composite form; Second; Gradually from the consumption of high manpower, materials and expenses
to the development of mechanical and economic methods; Third, gradually from high energy
consumption, high pollution technology to new low carbon technology, the harmonious development
of man and nature. Therefore, reasonable and effective treatment of soft soil foundation has become a
key issue in engineering construction.
1 Definition of soft soil
Generally speaking, soft soil refers to silt, muddy soil, dredger fill, miscellaneous fill and
saturated loose silt and silt. This kind of soil has high compressibility, low strength, high natural water
content, large natural void ratio, low shear strength, small permeability coefficient and other
engineering characteristics. Under the action of external load, the bearing capacity of the foundation is
usually low, the deformation of the foundation is large, the uneven deformation is also large, and the
deformation stability lasts a long time. Therefore, China's Ministry of Construction stipulates that soft
soil is defined as any one that meets the following three characteristics: (1) fine clay with mainly gray
Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence. Any further distribution
of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.
Published under licence by IOP Publishing Ltd 1
The 6th International Conference on Environmental Science and Civil Engineering IOP Publishing
IOP Conf. Series: Earth and Environmental Science 455 (2020) 012081 doi:10.1088/1755-1315/455/1/012081
appearance;(2) the natural water content is greater than or equal to the liquid limit;(3) natural pore
ratio is greater than or equal to 1.00[1].
2 Principles and Objectives of Soft Foundation Treatment
In principle, the treatment of soft soil foundation should first consider the use of natural
foundation. For the design of silt and muddy soil, a better soil layer should be used as the foundation
bearing layer. The upper covering soil layer is relatively thin. Attention should be paid to the
protection of the bottom surface of the soft soil foundation trench during construction to reduce
disturbance. For flushing and miscellaneous construction wastes and industrial wastes with stable
performance, they can be used as foundation when the uniformity and compactness are good. If the
foundation is weak and cannot meet the requirements, it needs to be treated. According to the
engineering conditions and the different soil conditions or composition of the foundation, the purpose
of treatment can be divided into the following five types: (1) improving the shear strength of the
foundation soil to keep the foundation stable;(2) reduce the compressibility of the foundation and
increase the compression modulus of the foundation soil, thus reducing the settlement or uneven
settlement of the foundation;(3) improving the permeability of the foundation to reduce the
permeability of the foundation soil or reduce the water pressure;(4) improving the dynamic
characteristics of the foundation, preventing liquefaction of the foundation, and improving its vibration
characteristics to improve the seismic performance of the foundation;(5) improve the bad foundation
characteristics of special soil, thus eliminating or reducing the foundation deformation caused by the
subsidence or expansion and contraction of soil, and avoiding building glass damage or affecting its
normal use.
3 Common Treatment Methods for Soft Soil Foundation
There are many types of soft soil foundation treatment methods, which can be divided into
temporary treatment and permanent treatment according to time. According to the depth of treatment,
it can be divided into shallow treatment and deep treatment. According to the treatment principle and
mechanism, it can be roughly divided into the types of changing foundation structure form, drainage
N consolidation method, artificial foundation and dynamic compaction method[2].
3.1 dynamic compaction method
Dynamic compaction method is internationally known as dynamic compaction method or
dynamic consolidation method. It is a foundation consolidation method initiated by French Menard
Technology Company in 1969[3].China introduced dynamic compaction technology for the first time
in the late 1970s. After that, several tests have been carried out and remarkable results have been
achieved. As a foundation treatment method with wide applicability and high economic benefits,
dynamic compaction method has achieved great response in China's engineering field, and has been
quickly applied to industrial and civil buildings, highways, docks, airports and other projects
throughout the country, thus accumulating a lot of experience[4].The principle of dynamic compaction
reinforcement is a foundation treatment technology that generates an impact force on the foundation
through strong tamping energy and forms a shock wave in the foundation. Under the impact force, the
rammer punches the upper soil mass, damages the soil mass structure, forms a tamping pit, and
compresses the surrounding soil by power, thus reinforcing the foundation.
3.2 Replacement of Cushion
The replacement cushion method refers to digging out all the weak and unfavorable soil layers
within the treatment range below the foundation bottom surface, replacing them with loose materials
with good soil quality and low compressibility, and rolling or ramming them to serve as the bearing
stratum to bear the pressure from the upper part. Then sand, crushed stone, fly ash, dry slag, soil (lime
soil, lime ash) or other materials with stable performance and no erosion are used as the cushion layer
to improve the bearing capacity of the bearing layer and reduce the bearing pressure of the natural soil
layer under the cushion layer, thus reducing the settlement of the foundation. The sand cushion layer
should pay strict attention to water content during construction, control water content, and adopt
layered paving and compaction methods.
3.3 preloading consolidation method
2
The 6th International Conference on Environmental Science and Civil Engineering IOP Publishing
IOP Conf. Series: Earth and Environmental Science 455 (2020) 012081 doi:10.1088/1755-1315/455/1/012081
Pile-load preloading method: pile-load preloading method refers to applying load to saturated soft
soil foundation by filling and other loading, and gradually discharging pore water in the soil by static
pressure to promote consolidation deformation of the soft soil foundation, so as to improve the
effective stress of the soil layer, enhance the strength of the foundation and reduce the settlement of
the foundation. It can be divided into single-stage loading or multi-stage loading according to the soil
quality. According to the stacking materials, it can be divided into gravity preloading, pressure
preloading and water preloading[6].
Vacuum preloading method: The vacuum preloading method refers to laying sand cushion layer
on the surface of soft soil foundation to be reinforced, then embedding vertical drainage pipes, and
then isolating it from the atmosphere with airtight sealing film. The film is embedded in the soil
around. Through the water absorption pipes embedded in the sand cushion layer, the vacuum device is
used for air extraction to form vacuum and increase the effective stress of the foundation[7].The
relative surcharge preloading method needs to consider the problems of high transportation and
construction costs due to a large number of surcharge sources, instability of the site due to large-area
surcharge, and large lateral displacement[8].The vacuum preloading method does not need to consider
the stability of foundation. The vacuum load can be quickly applied to the design value in a short time,
so the preloading time can be significantly reduced[9].
3.4 Compaction Method
Compaction method mainly refers to the process of compacting some soft and thick foundation
with compaction piles. The actual operation of the compaction pile is also relatively simple. First, the
casing pile should be squeezed into the foundation, where the soft soil is squeezed around the casing
pile and densified. At the same time, the hole is formed due to the squeezing of the casing pile. Then,
the casing pile is pulled out and filled with sand or gravel, lime, lime soil, soil and other materials and
compacted. The main purpose of doing this is to combine the material in the hole with the surrounding
squeezed soft soil layer to form a composite soil layer, which will jointly act as a bearing layer to bear
the pressure from the upper building, thus improving the overall bearing capacity of the soft soil
foundation and reducing the settlement of the foundation[10].
3.5 vibroflotation method
Vibroflotation method is a foundation treatment method that generates horizontal or vertical
vibration force through vibroflotation device and vibrates surrounding soil with pressure water to
improve foundation bearing capacity, increase foundation stability, reduce settlement and further
improve earthquake liquefaction resistance.This law originated in Germany in 1936.It was used for the
first time in 7.5 m subsoiling sand foundation of a building in Berlin, and its bearing capacity and
relative density have more than doubled[11].China began to study vibroflotation method and trial-
produce vibroflotation device in 1970s. In 1977, Nanjing Academy of Water Resources Sciences and
the Water Resources Planning and Design Institute of the Ministry of Communications cooperated to
develop the first vibroflotation device in China. It was first applied to the hull reinforcement workshop
of Nanjing Shipyard and achieved satisfactory results even though the equipment was crude at that
time[12].
3.6 chemical reinforcement method
The methods described above, whether they are dynamic compaction method, preloading method
or cushion replacement method, all use various mechanical or external forces to encrypt the soil, but
they do not change the chemical composition of the original foundation soil in essence, thus they are
all physical reinforcement methods. As the name implies, the chemical reinforcement method uses the
addition of new materials to change the chemical properties of foundation soil. Therefore, the
chemical consolidation method is to use certain chemical materials or chemical reactions to fill and
reform the soft soil foundation, promote the consolidation of the soft soil layer, reduce the
compressibility of the soil layer, and improve the bearing capacity of the foundation. There are many
chemical slurries used to reinforce the foundation by chemical reinforcement method. The common
materials are: cement slurry[13], water glass slurry[14], acrylamide slurry[15]and pulp waste slurry.
Chemical reinforcement method can be divided into pressure grouting method, high-pressure rotary
3
The 6th International Conference on Environmental Science and Civil Engineering IOP Publishing
IOP Conf. Series: Earth and Environmental Science 455 (2020) 012081 doi:10.1088/1755-1315/455/1/012081
spray method, deep mixing method and electroosmotic silicification method according to the particle
size of foundation soil and the properties of chemical grout.Select the best scheme according to
different engineering and soil conditions.
4 New Development of Soft Soil Base Treatment
4.1 Development of Soft Soil Foundation Treatment Methods
4.1.1 Multi-flocculant Combined with Vacuum Preloading Method
As mentioned earlier, when the soil has the characteristic of high water content, the vacuum
preloading method will be taken into account in site treatment. However, as soft soil is mainly
composed of fine particles, when it passes through the drainage membrane, the blockage often occurs
near the prefabricated vertical drainage in the process of vacuum preloading. Therefore, the drainage
capacity is significantly reduced, which often leads to insufficient consolidation and poor geotechnical
properties of soil.In response to this problem, Wang Jun and others proposed a method of multi-
flocculant combined with vacuum preloading[16]to treat dredged slurry. The method is mainly
realized by pretreating dredged mud with lime[17]and anionic polyacrylamide (APAM)[15]before
vacuum. The reinforcement principle of this method is that a certain amount of lime and APAM are
added to make small and medium particles in soft soil form larger lumps, i.e. flocculated state, thus
improving void ratio and air permeability. This forms a new kind of natural soil, which is easier to be
consolidated by vacuum preloading. At last, the optimum ratio of lime to APAM content is determined
to be 2:0.1 during vacuum preloading.
4.1.2 bamboo net reinforcement method
Land reclamation land is uneven in horizontal and vertical directions. Water content is generally
80%-150% or more. The site is in the state of flowing sludge, and even floating sludge has little
bearing capacity. Therefore, the surface layer must be strengthened. The commonly used pretreatment
technologies for surface layer sediment and debris flow include multi-layer geogrid and geotextile and
sand cushion layer technology, pretreatment technologies for hanging pieces and bamboo chips, sand-
free vacuum preloading, etc. Surface pre-treatment bamboo net technology[18]is a surface pre-
treatment technology based on bamboo raft technology. Vertical bamboo is inserted into sludge to
make the bamboo net enter the frame bamboo net structure. Because this technology makes the
bamboo raft into a three-dimensional skeleton, the bamboo net tends to be stable on the plane.
Yuanman[20]et al. through the study of Shantou highway embankment treatment project and
engineering examples, show that the bearing capacity of untreated super soft soil surface layer is 32.6
kPa.When the surface layer is treated for 3 months, it is 323% higher than that of the earlier treatment
and 695% higher than that of the untreated one.
4.1.3 Compound Negative Pressure Consolidation Technology
When facing the soil with large water content, poor permeability and zero bearing capacity in
engineering, conventional foundation treatment methods cannot be carried out and foundation
treatment faces many difficulties. To solve this problem, a compound negative pressure consolidation
technology is proposed. The technology includes three procedures: modified vacuum preloading,
electro-osmotic dewatering and dynamic consolidation. Modified vacuum preloading enables the
foundation to be initially consolidated with a certain strength to prepare for subsequent work.
Electroosmotic dewatering can effectively reduce the groundwater level and soil moisture content
before tamping and promote the dissipation of excess pore water pressure after tamping.
Electroosmotic dewatering and dynamic consolidation are coupled for many times to reinforce the
foundation of dredger fill. Gao Youbin[21]and others used this method in the field. The results show
that when applied to the foundation treatment of dredger fill, modified vacuum preloading can rapidly
improve the bearing capacity, electroosmosis method can rapidly reduce the underground water level,
effectively avoid the occurrence of "spring soil" phenomenon during dynamic compaction, thus
improving the optimal tamping energy. Compound negative pressure consolidation technology can be
effectively applied to newly reclaimed soft soil foundation.
4.1.4 Microbial Infiltration Grouting Method
4
The 6th International Conference on Environmental Science and Civil Engineering IOP Publishing
IOP Conf. Series: Earth and Environmental Science 455 (2020) 012081 doi:10.1088/1755-1315/455/1/012081
Microbial infiltration grouting is a new foundation treatment technology. Its working principle is
to improve the compressive strength of the foundation by infiltrating or injecting microbial slurry into
sand samples. This method is often compared with saturated grouting method in tests. Among them,
Andres Quiros[22]and others have shown through experimental research that the effect of treatment of
unsaturated soil samples by infiltration method (average unconfined compressive strength is
(19.7±5.86)MPa) is better than that of saturated soil samples by grouting method (average unconfined
compressive strength is (15.1±5.73)MPa).
4.1.5 chemical electroosmosis
The chemical electroosmosis method is obtained by a series of developments of the traditional
electroosmosis method. Its main working principle is to inject chemical solutions near the cathode and
anode electrodes respectively. Under the action of direct current electric field, the chemical solutions
react chemically to generate corresponding precipitates to reinforce the soil, thereby improving the
strength of the soil and accelerating the consolidation rate of the soil. Taiwan's European Zhang Yu
and others have carried out a series of laboratory tests on the concentration of chemical solutions,
types of suitable soils and treatment effects, and have enriched and perfected the corresponding
construction techniques[23].The research and application of this technology in China is still in its
infancy.
4.2 Development of Soft Soil Foundation Treatment Materials
The development in material direction is mainly reflected in geosynthetics and grouting materials.
Geotechnical materials are mainly embodied in geosynthetic needle-punched geotextiles, nonwoven
geotextiles, geomembranes of PVC, EP, EVA and other new materials, clay liners (GCL) and plastic
drain boards. Grouting materials are mainly embodied in the research of inorganic grouting materials
such as ultra-fine, dry grinding, wet grinding cement, stable slurry, paste slurry, etc. Acrylate, acid
water glass, epoxy, polyurethane, etc. have been developed as organic grouting materials.
5 Conclusion and prospect
In this paper, through a series of brief introduction of soft soil foundation treatment methods, with
emphasis on the introduction of new technologies, new methods and new materials, the following
conclusions and suggestions can be obtained:
(1) With the continuous improvement and development of reinforcement methods, soft soil foundation
treatment gradually develops from a single reinforcement method to a multi-method composite form,
and gradually changes from a single physical reinforcement method to a combination of physical reinf
orcement method and chemical reinforcement method.
(2) With the development of material science and the state's management of energy conservation and e
nvironmental protection, soft soil foundation treatment is gradually developing from high energy cons
umption and high pollution technology to new low carbon technology and harmonious development b
etween human and nature.
(3) With the innovation of management methods, soft soil foundation treatment gradually develops fro
m the consumption of high manpower, materials and expenses to the realization of mechanical and eco
nomic methods.
(4) With the rise of reclamation projects and sea-crossing bridge projects in coastal cities, more soft so
il foundation problems will be faced in the construction, and relevant engineering and technical person
nel and units need to strengthen technical and economic input.
Acknowledgements
This research was financially supported by open fund of State Key Laboratory of Nuclear Resources
and Environment(East China University of Technology)(NRE1930)and project supported by graduate
innovation fund of East China University of Technology(DHYC-201931).
References
[1] Gong Xiaonan. (2000): Foundation Treatment Manual (2nd Edition). Beijing: China Construction
Industry Press.
[2] Zhang Qinliang, Shao Dongsheng. (2009): Treatment Methods of Deep Soft Soil Foundation.
Information of China Construction, 9-28.
5
The 6th International Conference on Environmental Science and Civil Engineering IOP Publishing
IOP Conf. Series: Earth and Environmental Science 455 (2020) 012081 doi:10.1088/1755-1315/455/1/012081
[3] Menard L, Broise Y.(1975): Theoretical and practical aspects of dynamic consolidation[J].Journal
of Geotechnical Engi-neering, 25 (1) :3-18.
[4] Xu Yixiang, Liu Huiluo.(2016): Study on application of dynamic compaction method in mountain
high fill foundation treatment [J]. Building Structure, 46 (S2):528-530.
[5] Xi Ningzhong, Yu Haicheng, Xi Fengyi.(2016): Comprehensive Treatment Technology of Soft
Foundation in the Reclaiming Land from the Sea [J]. Building Science, 32 (01): 121-128.
[6] Jian Xiaoye.(2013): Treatment Methods for Several Soft Soil Foundations [J]. Technology
Innovation and Application, (8):169-170.
[7] Shi Xin and Lu Shanshan.(2019): Application of Vacuum Preloading in Foundation Treatment of
River[J].IOP Conference Series: Materials Science and Engineering:052068.
[8] Zhang Zhen, Chen Yong, Ye Guanbao, Xu Yan.(2018): CPerformance Evaluation of Reinforced
Soft Soil with Surcharge and Vacuum Preloading [J]. Chinese Journal of Underground Space and
Engineering, 14 (S1): 315-321.
[9] Ding Peizhong, Cao Xing.(2000): Application and Effect Analysis of Vacuum Preloading in
Underwater Embankment Filling [J]. Yangtze River, 31 (8): 40-41.
[10] Huang Xuefeng, Chen Zhenghan, Fang Xiangwei, Zhu Yuanqing, Guo Jianfeng, Wei Xuewen.
(2007): Study on Foundation Treatment Thickness and Treatment Method for Collapse Loess with
Large Thickness [J]. Chinese Journal of Rock Mechanics and Engineering, (S2):4332-4338.
[11] Steuerman S.(1939): A new soil compaction device[J].Engineering News Record, (1) :56-58.
[12] Lou Xiaoming, Yu Zhiqiang, Xu Shilong.(2012): Review on the Present Situation of
Vibroflotation Improvement Method [J]. Journal of Civil Engineering and Management, 29 (03):
61-66.
[13] Chao-Sheng Tang, Gu Kai.(2011): Strength behaviour of polypropylene fiber reinforced cement
stabilized soft soil [J]. China Civil Engineering Jouranl , 44 (S2): 5-8.
[14] Cheng Jianji.(1996): Application of Cement-Sodium Silicate in Soft Soil Grouting in Pearl River
Delta [J]. Chinese Journal of Geotechnical Engineering, 04: 83-86.
[15] Lei Huayang, Xu Yinggang, Li Xin, Liu Guangxue, Jin Yawei. (2017): SExperimental study on
consolidation characteristics of polyacrylamide-modifiedlime-stabilized dredger fill [J]. Journal
of Geotechnical Engineering, 39 (S2):107-111.
[16] Jun Wang; Guo Huang; Hongtao Fu; Yuanqiang Cai; Xiuqing Hu; Xiaoming Lou; Yawei Jin; Jun
Hai; Junfeng Ni; Jian Zou.(2019): Vacuum preloading combined with multiple-flocculant
treatment for dredged fill improvement[J].Engineering Geology:105194.
[17] Shriful Islam; N.M. Robiul Hoque; M. Aminul Hoque; Partha N. Mishra; M.M.H. Mamun;
Susmita Dey.(2019): Strength development in fine-grained paddy field soil by lime
addition[J].Journal of Building Engineering:100857.
[18] Dong, Z.L., Zhang, G.X., Mo, H.H., et al. (2008) The Rapid Strengthening Method and Packaged
Technology of the Ultra Soft Soil Shallow Surface. Chinese Patent No. 200810026168.
[19] Chen, C.N. and Xu, J.M. (2007): The Application of Bamboo Network in Super Soft Foundation
Engineering Silt Surface Layer Treatment. Port & Waterway Engineering, 10, 75-77.
[20] Man Yuan; Jihui Ding; Yanliang Cao.(2014): The Application of Bamboo Network Reinforcement
Technology on Hydraulic Fill Soft-Soil Foundation Treatment[J]. World Journal of Engineering
and Technology,Vol.2(No.2):68-72.
[21] Gao Youbin, Wang Bo, Liu Hanlong, Zeng Guohai.(2012): Technology Development in N ewly
Dredger Fill Foundation by Composite Negative-pressure Consolidation Method [J]. Journal of
Disaster Prevention and Mitigation Engineering, 32(03):332-338.
[22] Andres Quiros, Zhang Shuai, Cheng Xiaohui. (2015): Studay of the MICP Injection in
Unsaturated Sandy Soils [J]. Industrial Construction, 45(07):28-30+175.
[23] Ou, Chang-Yu; Chien, Shao-Chi1;Lee, Tsung-Yeh2.(2 013): Development of a Suitable Operation
Procedure for Electroosmotic Chemical Soil Improvement[J].Journal of Geotechnical and
Geoenvironmental Engineering.Vol.139(No.6):993-1000.