Sl. No. Description Previous Day Present Day Cumulative Quantity Plate Thickness

The document provides a daily progress report for the fabrication yard and laying site from a pipeline project. It summarizes the quantities completed for various fabrication activities like edge cutting, rolling, fitting, welding, testing, coating, and laying. It also provides details of the chainage and quantities laid by different contractors working on the laying site with a total of 132 meters laid so far.

Uploaded by

Jagadeesan S M
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views

Sl. No. Description Previous Day Present Day Cumulative Quantity Plate Thickness

The document provides a daily progress report for the fabrication yard and laying site from a pipeline project. It summarizes the quantities completed for various fabrication activities like edge cutting, rolling, fitting, welding, testing, coating, and laying. It also provides details of the chainage and quantities laid by different contractors working on the laying site with a total of 132 meters laid so far.

Uploaded by

Jagadeesan S M
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Harohalli to Vajarahalli.

DAILY PROGRESS REPORT ON FABRICATION YARD DATE :13-02-2021


MS PIPELINE WORKS
Previous Day Present Day Cumulative Quantity
Plate
Sl. No. Description
Thickness Numbers Meters Numbers Meters Numbers Meters

20 1382 3455 23 57.5 1405 3512.5


1 Edge cutting (Nos)
18 290 725 0 0.0 290 725.0
20 1324 3310 30 75.0 1354 3385.0
2 Rolling (Nos)
18 290 725 0 0.0 290 725.0
20 437 3240 8 60.0 445 3300.0
3 Fit up (Meters)
18 96 720 0 0.0 96 720.0

20 433 3247.5 8 60.0 441 3307.5


4 SAW Welding (Meters)
18 96 720 0 0.0 96 720.0

20 385 2887.5 6 45.0 391 2932.5


5 Radiography test (Meters)
18 96 720 0 0.0 96 720.0

20 372 2790 8 60.0 380 2850.0


6 Hydraulic test (Meters)
18 96 720 0 0.0 96 720.0

20 178 1335 4 30.0 182 1365.0


7 Copper slag Blasting
18 0 0 0 0.0 0 0.0

20 158 1185 0 0.0 158 1185.0


8 Epoxy coating (Meters)
18 0 0 0 0.0 0 0.0

20 151 1132.5 5 37.5 156 1170.0


9 Wrapping of welded mesh (Meters)
18 0 0 0 0.0 0 0.0

20 140 1050 6 45.0 146 1095.0


10 Guniting
18 0 0 0 0.0 0 0.0

20 132 990 0 0.0 132 990.0


11 Laying
18 0 0 0 0.0 0 0.0

DAILY PROGRESS REPORT ON LAYING SITE DATE :13-02-2021


MS PIPELINE LAYING DETAILS
CHAINAGE IN MTRS LAYING DETAILS ( IN NOS)
SL.NO CONTRACTOR NAME TOTAL MTRS AS ON REMARKS
FROM TO TODAY TOTAL
YESTRDAY
1 UBEN PROJECTS 585 952.5 367.5 49 0 49 Work in Progress
2 MAHENDRA REDDY KOKU 1300 1577.5 277.5 37 0 37 Work in Progress
3 JITEESH INFRASTRUCTURE 2300 2315 15 2 0 2 Work in Progress
4 BEM ENTERPRISES 4830 4935 105 14 0 14 Work in Progress
5 RGN ENTERPRISES 5800 6025 225 30 0 30 Work in Progress

TOTAL 990 132 0 132