Sl. No. Description Previous Day Present Day Cumulative Quantity Plate Thickness
The document provides a daily progress report on the fabrication yard and laying site for a water transmission pipeline project. At the fabrication yard, activities like edge cutting, rolling, fitting, welding, testing, coating, and laying of plates were ongoing. A total of 59 meters of pipeline was laid at the site by 4 contractors, with work still in progress.
Download as XLSX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
48 views
Sl. No. Description Previous Day Present Day Cumulative Quantity Plate Thickness
The document provides a daily progress report on the fabrication yard and laying site for a water transmission pipeline project. At the fabrication yard, activities like edge cutting, rolling, fitting, welding, testing, coating, and laying of plates were ongoing. A total of 59 meters of pipeline was laid at the site by 4 contractors, with work still in progress.
11 Laying 18 0 0 0 0.0 0 0.0 SPML ONTB BWSSB Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Harohalli to Vajarahalli.
DAILY PROGRESS REPORT ON LAYING SITE DATE :28-01-2021
MS PIPELINE LAYING DETAILS
CHAINAGE IN MTRS LAYING DETAILS ( IN NOS)
SL.NO CONTRACTOR NAME TOTAL MTRS REMARKS AS ON FROM TO TODAY TOTAL YESTRDAY 1 UBEN PROJECTS 585 832.5 247.5 32 1 33 Work in Progress 2 MAHENDRA REDDY KOKU 1300 1442.5 142.5 16 3 19 Work in Progress 3 BEM ENTERPRISES 4830 4875 45 5 1 6 Work in Progress 4 RGN ENTERPRISES 5800 5807.5 7.5 0 1 1 Work in Progress 4 442.5 TOTAL 442.5 53 6 59