Project: EXPO 2020 - OV016 - USA PAVILION Inspection and Test Plan (Itp)
Project: EXPO 2020 - OV016 - USA PAVILION Inspection and Test Plan (Itp)
Revision: 00
Project: EXPO 2020 – OV016 – USA PAVILION
Date: 04/04/2020
Sheet No:
INSPECTION AND TEST PLAN (ITP) Discipline: Structural Steel 1
1.0 Documents:
Approval of controlling
documents (Method
Statement, QC process,
Prior to starting
1.1 Material Approval, Contract Documents / Project Specifications. Submittal Record review H H --- R
works
Supplier Approval, Shop
Drawings and
calculations)
2.0 Pre-works:
Material Inspection request
Inspection of incoming 100% Each Material Inspection
2.1 Visual Inspection I R --- R
materials Delivery reports
100% Each
2.2 Conformity of materials Mill Test Certificates MTCs Review Documents I R --- R
delivery
Monitoring
Welding Operation Visual Inspection
3.3 AWS D1.1 All I R --- R
Report
SA 2.5 SSPC10
Surface Preparation
4.1 Abrasive Blasting All Area Visual Inspection I R --- R
& Painting Reports
Profile 45-70µm and manufacture’s requirements
Daily Temperature
4.2 Ambient conditions Project Specifications Daily Record
Record review R R --- R
Surface Preparation
4.4 Paint Application Approved Paint system All Area Visual Inspection I R --- R
& Painting Reports
Surface Preparation
4.5 DFT Measurement As per Paint Data Sheet Spot Physical inspection I/H R --- R
& Painting Reports
Incoming fabricated
material on Site and
Material Inspection
Installation of Steel Erection Drawings GA / Shop Drawings All Area Visual Record H S
5.1 Request MIR --- S
Structure members Review
Final fit up ,
All Area
5.2 Erection of structural steel Must achieve Project requirements Approved IR Visual Inspection H S --- S
members
Bolt fixing
Site welding for Visual Inspection/
All Area
5.3 Adjustment of the steel Must achieve Project requirements Approved IR Dimensional I R --- R
members. inspection
15 Degree Bend
Test for 5% of the
studs, selected at
5.4 Bend test of Shear Studs Must achieve Project requirements Approved IR Physical test H S --- R
random, minimum
2studs per erected
member.
Document No: GSC/EUS/ITP-2020-001
Revision: 00
Project: EXPO 2020 – OV016 – USA PAVILION
Date: 04/04/2020
Sheet No:
INSPECTION AND TEST PLAN (ITP) Discipline: Structural Steel 4
Final Alignment and Bolt Approved Method Statement & AISC – RCSC - 2014 (includes
Torque tightening Approved IR Bolt Torque
5.5 April 2015 Errata) Specification for Structural Joints using All I/H W --- W
Tightening Report
ASTM A325 or A490 Bolts and ASTM F3125
GSC: Sub contractor (German steel) TPI – Third Party Inspection / Laboratory Inspection W – Witness : Notification required (IR) Presence not mandatory I - Inspection.
ELEC: Main contractor (Electra Solutions) KAA – Engineer (Khatib & Alami) H – Hold Point: Notification required (IR) Presence mandatory R – Review S - Surveillance –
Surveillance –
Surveillance
Approved by: