Change Order Files
Change Order Files
TOTAL APPROVED CHANGE ORDERS 4,940 3,224 4,696 3,224 4,696 3,224
8,164 7,920 7,920
Note: For the total cost of $9.576 Million for the Change Order for the WH7 Pipeline Facilities Increased Capacity, $1.576 Million is funded from Train 3 (WH7) Contengency, and the
balance, $8.0 Million, is funded from Train 4 (WH5) Option.
Note: For the total cost of $9.576 Million for the Change Order for the WH7 Pipeline Facilities Increased Capacity, $1.576 Million is funded from Train 3 (WH7) Contingency, and the
balance, $8.0 Million, is funded from Train 4 (WH5) Option.
WH9PF-1 39 Conduct Geophysical Survey for the WH9 Pipeline route and the Subsea 696 412 08-Jan-04 412 Ch.Order ($1,108) for LNG
Cable route. Conduct Geotechnical Survey at the WH9 Jacket location Agreement T3EPC-02
WH9 Jacket and Temporary Deck Board Authorized as
WH9PF-2 42 Engineering , Procurement and Construction for the WH9 Jacket (12-slots). 9,800 14-Jan-04 Ch.Order for LNG Agreement
with a completion date of 28 June 2004 for offshore installation. T3EPC-02
WH9 Jacket
WH9PF-3 59 Additional Survey coverage for Drill Rig Approach 20 24-Aug-04 20 Booked to DTF Account
Pad Eyes
WH9PF-4 55 Provision of 12 Nos. Pad Eyes welded on WH9 Drill Deck 6 12-Oct-04 6 6
WH9 - Deck Steel Escalation
WH9PF-5 82 Cost of Material Escalation for the Deck Steel Structure that 137 27-Dec-04 137 137
exceeds the agreed basis at the time of awarding the option for WH9.
WH4 Drill Deck Strengthening
WH9PF-6 63C Engineering, procurement, fabrication and trial fit of 1 No. BOP 180 27-Dec-04 180 180
Stack Mounting frame.
Platform Shutdown System Modifications
WH9PF-7 70C Changing the current shutdown logic from PSD to ESD and 66 28-Dec-04 66 66
provide shutdown bypass for H2S detectors.
Well Kill Valves Procured by RasGas DTF
Procurement of 12 (twelve) Actuated Well Kill Valves from Wellhead Tree 390 15-Mar-05 on behalf of Offshore PMT
Manufacturer.
UPS Power Outlet
WH9PF-7 85C Engineering, Procurement and Installation of UPS Power Outlet 26 28-Apr-05 26 26
on the WH9 Drill Deck.
Platform Modification toEnhance SIMOPS
WH9PF-9 60C Provide beams and grating modifications suitable for use during 99 01-Jun-05 99 99
drilling operation to provide sufficient opening for drill bit.
Vent and Relief
WH9PF-10 73C Engineering, procurement, fabrication, Installation and Testing of WH9 400 14-Dec-05 400 400
Deck Vent and Relief modifications.
Additional SIMOPS Materials
WH9PF-11 81 Additional Engineering, procurement and installation of materials required 155 14-Dec-05 155 155
for SIMOPS Wells on WH9 (9 No.'s) and the supply of material for 1 No.
contingency Well.
Note: 1. Early award of the onshore portion of the Export Pipeline for WH6 Option; redesignated WH4 Pipeline when TOR Field Development change was implemented for the Expansion Project.