A Scrum Analysis
A Scrum Analysis
Purva Rane
Northeastern University
12/12/2020
A SCRUM ANALYSIS
Table of Contents
1. Overall Journey......................................................................................................................3
2. Future Milestones...................................................................................................................3
3. A Brief Journey into Advanced Agile...................................................................................4
3.1. Week 1..................................................................................................................................4
3.2. Week 2..................................................................................................................................5
3.3. Week 3......................................................................................................................................6
3.4. Week 4......................................................................................................................................7
3.5. Week 5......................................................................................................................................8
3.6. Week 6......................................................................................................................................8
4. Sprint Retrospective...............................................................................................................9
4.1. What went well in Sprint 1 & 2?...........................................................................................9
4.2. What went wrong in Sprint 1 & 2?.......................................................................................9
5. A Different Approach towards Scrum...............................................................................10
6. References.............................................................................................................................12
2
A SCRUM ANALYSIS
1. Overall Journey
I have been familiar with projects per se since a very young age. It started with my art, which
then turned into academics, and finally my perspective towards project changed during my
bachelors. I gained the knowledge of various procedures, task, obstacles that occur during any
assignment and how to overcome them. The sense of accomplishment that I get after resolving
these challenges or after finishing the project has inspired me to pursue my major in Agile
Sanchar Nigam Limited (BSNL) as a part of the project management team. Here, my major
responsibilities included creating WBS to document the work packages, deliverables, resources
thereby determining the KPI and critical success factors to evaluate strategic and overall
performance of the project. This experience gave me the taste of the dynamic work done by the
project management team. Hence, I wanted to pursue a master’s degree in Project Management.
2. Future Milestones
As I had previous experience in the technical aspects of executing a project, I was determined in
pursuing Agile Project Management was to maximize my opportunities in getting to know the
gist while executing a project and aligning the project objectives with the strategic business
goals. As it is universally known, for Scrum, the teams are cross-functional and self-organizing
i.e., each team member will be required to take a feature from idea to implementation. This
further motivated to study and have an in-depth knowledge about what goes on in managing a
Scrum team. Unlike the traditional waterfall framework, Agile methodology uses an iterative
approach ensuring enhanced quality, customer satisfaction, and continuous learning environment
3
A SCRUM ANALYSIS
From this lab coursework, it is safe to say that I have learned and acquired hand-on training on
The hand-on training was scheduled for sex weeks. Prior to commencing this lab coursework, we
were divided into three groups where each group comprised of 5-6 members. Post division, the
teams were assigned a software platform to work on their projects. These platforms included-
Jira, Atlassian DevOps, and Monday.com. Our team was assigned to work with Monday.com.
The scope for the project was to create a library including 28 papers; each paper related to Agile,
Scrum and other methodologies. A product backlog was provided including these 28 user stories
in the first week. This turned out to be a good in terms of gaining knowledge and expanding it by
3.1. Week 1
In the first week, there was not much to do as we were getting to know each team member.
We did some research about Monday.com associated with its usefulness and features that
In addition to assigning the role of ‘Scrum Master’ to each team member, we learned and
started to implement the guidelines and best practices to help us work efficiently in a scrum
organization.
As per the assignments, we were guided by Prof. Roos. In the end of week 1 we submitted
Meeting Notes (discussion on how to execute the given assignments and responsibilities)
Team Background (as none of us worked with any of us in the previous classes, this
4
A SCRUM ANALYSIS
Contact Information
The time for daily stand-up meeting was decided at 6pm via WhatsApp and Email every day
except Thursday and Saturday. Along with a daily standup meeting immediately after the
class has ended via a Zoom call, another daily standup meeting will be held at 2 pm via
Zoom call.
3.2. Week 2
In this week, there was a sense of continual learning as we were getting familiar with the
platform- Monday.com.
The initial product backlog was provided with priorities set by the Product Owner (Prof.
Roos). These 28 user stories were thoroughly read and researched by each team member in
needs.
To assign user points to the given 28 user stories, we planned on playing the game- ‘Planning
Poker.’ This eventually turned out to be efficient thereby discussing the complexities of each
Having said that, we agreed and established a common ground on having some flexibility in
terms of changing the user story points later if need be. For example, a priority was
reassigned to a team member (James Howard) as he had prior experience related to that
subject.
As the access to a free trail for Monday.com was 14-days, each team member except one
5
A SCRUM ANALYSIS
In week 2, we struggled with using some of the boards to track the sprints by implementing
Velocity was determined by the release dates for each Sprint and the timeframe to
accomplish the proposed items in each Sprint. We also considered team availability and other
At the end of week 2, we embraced the software Monday.com and agreed on sending an
3.3. Week 3
The Product Backlog was changed i.e. the priorities for the given user stories were changes.
For this week, we were asked to submit the Sprint 1 plan which would include all the stories
In addition, hours of work estimated for each task assigned to each team member was also
Since the priorities were changes, team members- Chuzhe and Carrie were assigned new
A revised story estimation was done by playing the game- Planning Poker to deal with the
changes in priorities.
In order to maintain the velocity of the team, the sprints were rebalanced with almost
A screenshot of our Task Board was submitted to show progress for each task. In addition, a
copy of Burndown Chart was also submitted followed by meeting notes taken down during
6
A SCRUM ANALYSIS
While analyzing the Burndown Chart, I realized that our burndown chart went up and then
3.4. Week 4
In this week, we focused on ‘Sprint Retrospective’ during the daily standup meeting. This
Areas for improvement and provide a platform to talk about values the whole team can
Takeaways on how to improve a role and have conversations on how to perform better as
If a sprint retrospective runs poorly, following could happen [ CITATION Pro19 \l 1033 ]:
It could turn into a basing session by bringing up things that would never end up getting
implemented.
During this retrospective, we discussed the grades and feedback given to us by our Prof.
Roos thereby determining corrective measures to improve the overall team performance.
In order to track the progress, we reviewed and regularly monitored the Burndown chart and
velocity chart.
Lastly, we discussed next week’s tasks including improving the quality of papers, improving
7
A SCRUM ANALYSIS
3.5. Week 5
In this week, we combined the papers in Sprint 1 and the stories planned to be released in
Sprint 2.
In addition, hours of work estimated for each task assigned to each team member was also
Since the priorities were changes, team members- Chuzhe and Carrie were assigned new
A revised story estimation was done by playing the game- Planning Poker to deal with the
changes in priorities.
In order to maintain the velocity of the team, the sprints were rebalanced with almost
A screenshot of our Task Board was submitted to show progress for each task. In addition, a
copy of Burndown Chart was also submitted followed by meeting notes taken down during
3.6. Week 6
In this last week, we conducted a daily standup meeting where we simply discussed the
lessons learned.
We thoroughly understood each role involved in developing a product i.e., Scrum Master,
In addition to the above-mentioned roles, we analyzed and reviewed the artifacts created by
the team during product development i.e., Product Backlog, Sprint Burndown Chart, and
Sprint Backlog.
8
A SCRUM ANALYSIS
Lastly, we submitted the entire 28 set of papers to create a library associated with Scrum and
Agile topics as per the scope of this project along with the Burndown Chart and Task Board.
4. Sprint Retrospective
Everyone attended the daily standup meetings on time and followed the ground rules
Each team member carried out their own research associated with Monday.com
The communication and coordination amongst the team members was at a high level
The team managed and implemented the assigned tasks with changes in Product Backlog
The flow of communication between the previous Scrum Master’s and next week’s Scrum
The tasks and changes were regularly updated and monitored by the entire team
The user stories were timely implemented, and the estimated work hours were thoroughly
calculated
The compilation of 28 papers was in accurate APA format along with references
The coordination was rather smooth while communicating on Zoom video call associated
The communication with respect to the project updates was carried out via WhatsApp
As per Agile environment, it was incorrect to carry out regular follow-ups regarding each
9
A SCRUM ANALYSIS
In the beginning, our team had some difficulty explaining the burndown chart
Emerged in the 1970s and popularized in 2001, Scrum is the best known as a way of doing work
within the Agile Methodology placing high value on people as an asset [ CITATION Rac1 \l
1033 ]. In order to empower project team members, one can adapt the development approach of
scrum best practices in case of any changes occur while executing phase of the project. They are
While working on the lab course work, our team implemented the above-mentioned best
practices in order to attain maximum efficiency at the end. Firstly, I believe instead of giving us
28 papers with a scope of creating library associated with Agile and Scrum Framework, we could
have developed or executed projects involving products as they are executed within an
organization. This could have helped us have a better and thorough understanding with the work
environment around a Scrum Framework. Given a chance, I would love to implement Scrum
Framework in lean product development. As we know change is inevitable as the customer needs
are inconsistent along with uncalled for changes in market trends and growth. In case of
traditional waterfall methodology, the concept of change management and implementing these
changes is rather rigid. On the contrary, due to iterative approach in Agile Methodology, changes
are identified at an early basis thereby maintaining the quality of the product. In addition, while
10
A SCRUM ANALYSIS
As result of these feedback loops, there is a constant involvement of customer which enables the
development team to achieve tangible results thereby eliminating any knowledge gaps in
understanding the customer expectations and needs. As per the daily standup meetings, I believe
15 minutes is a short period of time to let each team member give their update and discuss ideas
associated with the next iterations. Having said that, increasing or reducing the planned events
will in turn disrupt team’s work rhythm thereby leading to burnout, reduced velocity and low
quality.
In conclusion, the roles, responsibilities, events, artifacts and ground rules involved in Scrum
Framework are immutable i.e., the existence of scrum is in its entirety. This lab course work has
helped me understand and gain hands-on experience by using Monday.com which will in turn
11
A SCRUM ANALYSIS
6. References
Proventures. (2019, March 15). What Is A Sprint Retrospective and Why Should We Run It?
retrospective/
12
A SCRUM ANALYSIS
13