Practice File - 01

The document outlines a work breakdown structure (WBS) and schedule for a project. It includes the WBS ID, activity ID, activity name, predecessor details, and activity type for each task. It also provides assumptions about the project start date and calendar. Several questions are asked at the end regarding calculating durations and filtering the schedule report.

Uploaded by

yamanta_raj
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views

Practice File - 01

The document outlines a work breakdown structure (WBS) and schedule for a project. It includes the WBS ID, activity ID, activity name, predecessor details, and activity type for each task. It also provides assumptions about the project start date and calendar. Several questions are asked at the end regarding calculating durations and filtering the schedule report.

Uploaded by

yamanta_raj
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 12

WBS Name WBS ID ActivityID Activity Name

Project 1 - -
Management 1.1 P-M-I-MG-MLS-0001 Start
Management 1.1 P-M-I-MG-LOE-0001 Project Duration
Engineering 1.2 - -
Data Sheet 1.2.1 P-E-I-HV-BAT-0003 HVAC Technical Data Sheets
Data Sheet 1.2.1 P-E-I-HV-BAT-0006 Blast Proff Door Technical Da
Drawing 1.2.2 P-E-I-HV-BAT-0009 HVAC Air Flow Diagram
MTO 1.2.3 P-E-I-HV-BAT-0012 HVAC Plumbing Clean Agent
Material Requisition 1.2.4 P-E-I-HV-BAT-0015 HVAC Plumbing Clean Agent
Procurement 1.3 - -
HVAC 1.3.1 P-P-I-IN-BAT-0003 Inquiry preparation
HVAC 1.3.1 P-P-I-IN-BAT-0005 Inquiry issuance
HVAC 1.3.1 P-P-I-IN-BAT-0009 Proposal received
HVAC 1.3.1 P-P-I-IN-BAT-0013 Technical Clarification
HVAC 1.3.1 P-P-I-IN-BAT-0017 TBE Issuance
HVAC 1.3.1 P-P-I-IN-BAT-0021 Bid Close
HVAC 1.3.1 P-P-I-IN-BAT-0025 CBE Issuance
HVAC 1.3.1 P-P-I-IN-BAT-0029 Vendor Selection
HVAC 1.3.1 P-P-I-IN-BAT-0033 PO Issuance
HVAC 1.3.1 P-P-I-IN-BAT-0037 PO effective
HVAC 1.3.1 P-P-I-IN-BAT-0041 Manufacturing
HVAC 1.3.1 P-P-I-IN-BAT-0045 Inspection
HVAC 1.3.1 P-P-I-IN-BAT-0049 Shipment
HVAC 1.3.1 P-P-I-IN-BAT-0053 Custom Clearance
HVAC 1.3.1 P-P-I-IN-BAT-0057 Delivery at site
Management 1.1 P-M-I-IN-MLS-0003 Finish

Assumption:
Project Name = PJC-01
1. Project Start Date : 01-Jan-2021
2. Calendar 7 WW (10 hour per day)

Assignment:
1. How long is project duration?
2. Please provide me project critical path in PDF file
3. Please filter task dependent activities in PDF file
4. Please filter Level of effort activities in PDF file
5. Please filter activities after 30-May-2021 in PDF file
6. How long is Construction duration?
7. How long is Procurement duration?
Predecessor Details
Original DU (D) Activity Type
(Activity ID & Relationship Type)

- - -
0 Start Milestone
- P-E-I-IN-MLS-0001 Level of effort
- - -
60 P-M-I-MG-MLS-0001 : FS Task Dependent
30 P-E-I-HV-BAT-0003 : SS + 30 Days Task Dependent
15 P-E-I-HV-BAT-0006 : FS Task Dependent
15 P-E-I-HV-BAT-0009 : FS Task Dependent
20 P-E-I-HV-BAT-0012 : FS Task Dependent
- - -
10 P-E-I-HV-BAT-0015 : FS Task Dependent
5 P-P-I-IN-BAT-0003 : FS Task Dependent
30 P-P-I-IN-BAT-0005 : FS Task Dependent
15 P-P-I-IN-BAT-0009 : FS Task Dependent
15 P-P-I-IN-BAT-0013 : FS Task Dependent
5 P-P-I-IN-BAT-0017 : FS Task Dependent
5 P-P-I-IN-BAT-0021 : FS Task Dependent
2 P-P-I-IN-BAT-0025 : FS Task Dependent
2 P-P-I-IN-BAT-0029 : FS Task Dependent
15 P-P-I-IN-BAT-0033 : FS Task Dependent
180 P-P-I-IN-BAT-0037 : FS Task Dependent
60 P-P-I-IN-BAT-0041 : FF Task Dependent
20 P-P-I-IN-BAT-0045 : FS Task Dependent
20 P-E-I-IN-BAT-0049 : SS+10Days Lag Task Dependent
3 P-E-I-IN-BAT-0053 : FS Task Dependent
0 P-E-I-IN-BAT-0057 : FS , P-E-I-IN-LOE-0001: FS Finish Milestone

PDF file
PDF file
DF file
in PDF file
Duration % Comp. Activity Role Cost
Resource Name Resource Type Budget
Type Type Code Name Account
Activity % Actual Actual Financial
Start Finish OBS EPS
Comp. Start Finish Period
ActivityID Activity Name Original DU (D) Predecessor Details Activity Type
(Activity ID & Relationship Type)
- - - - -
P-E-B-MA-MLS-0001 Start Project 0 Start Milestone
P-E-B-MA-LOE-0001 Management P-E-B-MA-MLS-0001 : FS Level of effort
- - - - -
P-E-B-MA-COM-0001 Inquiry preparation 5 P-E-B-MA-MLS-0001 : FS Task Dependent
P-E-B-MA-COM-0003 Inquiry issuance 5 P-E-B-MA-COM-0001 : FS Task Dependent
P-E-B-MA-COM-0005 Proposal received 15 P-E-B-MA-COM-0003 : FS Task Dependent
P-E-B-MA-COM-0007 Technical Clarification 10 P-E-B-MA-COM-0005 : FS Task Dependent
P-E-B-MA-COM-0009 TBE Issuance 5 P-E-B-MA-COM-0007 : FS Task Dependent
P-E-B-MA-COM-0011 Bid Close 5 P-E-B-MA-COM-0009 : FS Task Dependent
P-E-B-MA-COM-0013 CBE Issuance 5 P-E-B-MA-COM-0011 : FS Task Dependent
P-E-B-MA-COM-0015 Vendor Selection 2 P-E-B-MA-COM-0013 : FS Task Dependent
P-E-B-MA-COM-0017 PO Issuance 2 P-E-B-MA-COM-0015 : FS Task Dependent
P-E-B-MA-COM-0019 PO effective 15 P-E-B-MA-COM-0017 : FS Task Dependent
P-E-B-MA-COM-0021 Manufacturing 180 P-E-B-MA-COM-0019 : FS Task Dependent
P-E-B-MA-COM-0023 Inspection 60 P-E-B-MA-COM-0021 : FF Task Dependent
P-E-B-MA-COM-0025 Shipment 20 P-E-B-MA-COM-0023 : FS Task Dependent
P-E-B-MA-COM-0027 Custom Clearance 20 P-E-B-MA-COM-0025 : SS+10days Lag Task Dependent
P-E-B-MA-COM-0029 Delivery at site 3 P-E-B-MA-COM-0027 : FS,P-E-B-MA-COM-0025 : FS Task Dependent
P-E-B-MA-COM-0031 Finish Procurement 0 P-E-B-MA-COM-0029 : FS Finish Milestone
- - - - -
C-E-B-MA-COM-0031 Excavation 5 P-E-B-MA-COM-0023 : FS Task Dependent
C-E-B-MA-COM-0033 Barbending 10 C-E-B-MA-COM-0031 : FS Task Dependent
C-E-B-MA-COM-0035 Filling 5 C-E-B-MA-COM-0033 : FS Task Dependent
C-E-B-MA-COM-0037 Concreating 3 C-E-B-MA-COM-0035 : FS Task Dependent
C-E-B-MA-COM-0039 Groating 2 C-E-B-MA-COM-0037 : FS Task Dependent
C-E-E-MA-MLS-0003 Finish Project 0 C-E-B-MA-COM-0039 : FS , P-E-B-MA-LOE-0001 : FS Finish Milestone

Assumption:
1. Project Start Date : 01-Jan-2021
2. Calendar 7 WW (10 hour per day)

Assignment:
1. How long is project duration? 342 days
2. Please provide me project critical path in PDF file
3. Please filter task dependent activities in PDF file
4. Please filter Level of effort activities in PDF file
5. Please filter activities after 15-Jun-2021 in PDF file
6. How long is Construction duration? 25 DAYS
7. How long is Procurement duration? 342 days
WBS ID WBS Name ActivityID

1 Project -
1.1 Management P-M-I-MG-MLS-0001
1.1 Management P-M-I-MG-LOE-0001
1.2 Engineering -
1.2.1 Management P-M-I-MG-LOE-0003
1.2.1 Management P-M-I-MG-MLS-0005
1.2.2 Schematic Diagram E-B-G-IN-DIG-1435
1.2.3 Engineering Standard Specification E-B-G-IN-ESS-1480
1.2.4 Index E-B-G-IN-INX-1500
1.2.5 List E-B-G-IN-LST-1600
1.2.5 List E-B-G-IN-LST-1650
1.2.5 List E-B-G-IN-LST-1700
1.2.6 Material Take off E-B-G-IN-MTO-1900
1.3 Procurement -
1.3.1 Management P-M-I-MG-MLS-0015
1.3.1 Management P-M-I-MG-MLS-0020
1.3.2 HVAC P-P-I-IN-HVC-0003
1.3.2 HVAC P-P-I-IN-HVC-0005
1.3.2 HVAC P-P-I-IN-HVC-0009
1.3.2 HVAC P-P-I-IN-HVC-0013
1.3.2 HVAC P-P-I-IN-HVC-0017
1.3.2 HVAC P-P-I-IN-HVC-0021
1.3.2 HVAC P-P-I-IN-HVC-0025
1.3.2 HVAC P-P-I-IN-HVC-0029
1.3.2 HVAC P-P-I-IN-HVC-0033
1.3.2 HVAC P-P-I-IN-HVC-0037
1.3.2 HVAC P-P-I-IN-HVC-0041
1.3.2 HVAC P-P-I-IN-HVC-0045
1.3.2 HVAC P-P-I-IN-HVC-0049
1.3.2 HVAC P-P-I-IN-HVC-0053
1.3.2 HVAC P-P-I-IN-HVC-0057
1.3.1 Management P-M-I-IN-MLS-0010
1.3 Construction -
Management C-E-E-MA-MLS-0025
Management C-E-E-MA-MLS-0030
1.3.1 Column Foundation C-E-B-MA-COM-0031
1.3.1 Column Foundation C-E-B-MA-COM-0033
1.3.1 Column Foundation C-E-B-MA-COM-0035
1.3.1 Column Foundation C-E-B-MA-COM-0037
1.3.1 Column Foundation C-E-B-MA-COM-0039
1.1 Management C-E-E-MA-MLS-0035

Assumption:
Project Name = PJC-03
1. Project Start Date : 01-Jan-2021
2. Calendar 7 WW (10 hour per day)

Assignment:
1. How long is project duration?
2. Please provide me project critical path in PDF file
3. Please filter task dependent activities in PDF file
4. Please filter Level of effort activities in PDF file
5. Please filter activities after 15-Jun-2021 in PDF file
6. How long is Construction duration?
7. How long is Procurement duration?
Activity Name Original DU (D)

- -
Start 0
Project Duration -
- -
Engineering Duration
Engineering Finish -
Block Diagram for Metering System 45
Technical Specification for Metering System 30
Basic Instrument Index 20
Basic IO Summary 20
Lis of Instrument in FEED 15
Basic Instrument Air Consumption Power 10
Basic MTO Summary Instrument 30
- -
Procurement Start 0
Procurement Duration -
Inquiry preparation 10
Inquiry issuance 5
Proposal received 30
Technical Clarification 15
TBE Issuance 15
Bid Close 5
CBE Issuance 5
Vendor Selection 2
PO Issuance 2
PO effective 15
Manufacturing 180
Inspection 60
Shipment 20
Custom Clearance 20
Delivery at site 3
Procurement Finish 0
- -
Construction Start 0
Construction Duration -
Excavation 5
Barbending 15
Filling 15
Concreating 15
Groating 15
Finish Project 0

t Date : 01-Jan-2021
WW (10 hour per day)

project duration?
de me project critical path in PDF file
task dependent activities in PDF file
Level of effort activities in PDF file
activities after 15-Jun-2021 in PDF file
Construction duration?
Procurement duration?
Predecessor Details Activity Type Duration % Comp.
(Activity ID & Relationship Type) Type Type

- -
Start Milestone
P-E-I-IN-MLS-0001 Level of effort
- -
P-M-I-MG-MLS-0005 : FS Level of effort
E-B-G-IN-MTO-1900 : SS Finish Milestone
P-M-I-MG-MLS-0001 : FS Task Dependent
E-B-G-IN-DIG-1435 : SS + 20 Days Task Dependent
E-B-G-IN-ESS-1480 : FS Task Dependent
E-B-G-IN-INX-1500 : FS Task Dependent
E-B-G-IN-LST-1600 : SS Task Dependent
E-B-G-IN-LST-1650 : FS Task Dependent
E-B-G-IN-LST-1700 : FS Task Dependent
- -
E-B-G-IN-MTO-1900 : FS Start Milestone
P-M-I-IN-MLS-0010 : FS Level of effort
E-B-G-IN-MTO-1900 : FS Task Dependent
P-P-I-IN-HVC-0003 : FS Task Dependent
P-P-I-IN-HVC-0005 : FS Task Dependent
P-P-I-IN-HVC-0009 : FS Task Dependent
P-P-I-IN-HVC-0013 : FS Task Dependent
P-P-I-IN-HVC-0017 : FS Task Dependent
P-P-I-IN-HVC-0021 : FS Task Dependent
P-P-I-IN-HVC-0025 : FS Task Dependent
P-P-I-IN-HVC-0029 : FS Task Dependent
P-P-I-IN-HVC-0033 : FS Task Dependent
P-P-I-IN-HVC-0037 : FS Task Dependent
P-P-I-IN-HVC-0041 : FF Task Dependent
P-P-I-IN-HVC-0045 : FS Task Dependent
P-P-I-IN-HVC-0049 : SS+10Days Lag Task Dependent
P-P-I-IN-HVC-0053 : FS Task Dependent
P-P-I-IN-HVC-0057 : FS, P-M-I-MG-MLS-0020 : FS Finish Milestone
- -
P-P-I-IN-HVC-0045 : FS Task Dependent
C-E-E-MA-MLS-0025 : FS Level of effort
P-P-I-IN-HVC-0045 : FS Task Dependent
C-E-B-MA-COM-0031 : FS Task Dependent
C-E-B-MA-COM-0033 : SS + 5 days Lag Task Dependent
C-E-B-MA-COM-0035 : SS + 5 days Lag Task Dependent
C-E-B-MA-COM-0037 : SS + 5 days Lag Task Dependent
C-E-B-MA-COM-0039 : FS, C-E-E-MA-MLS-0030 : FS Finish Milestone
Activity Resource Resource Role Cost Activity % Actual
Budget Start Finish
Code Name Type Name Account Comp. Start
Actual Financial
OBS EPS
Finish Period