Duct Works Checklist
Duct Works Checklist
Given Duct hanger supports as per specification MS angle of 20x20x3 with 2 coats of primer and enamel paint
should be given at intervals of 2.5m
4
For supply ducts 19mm
Insulation provided as per given specification For return ducts 13mm
5 For joints 3mm thick AL foiled tape