Document Title TP Document No. Revision Project Title Contract Number Contractor Doc No. Con. Doc. Revision
Document Title TP Document No. Revision Project Title Contract Number Contractor Doc No. Con. Doc. Revision
Not Approved
3
(Revise and resubmit for approval ☐
As built
5
(After FAT as Applicable) ☐
1. Scope of work:
Electrical Construction works which comprise the cabinet replacement activities at GDU’s and hookup the
existing services to the new cabinet.
2. Contractor details:
Contractor: Comsip
E.D. Regulations
British Standards
I.E.E. Regulations
Tatweer Standard Engineering Specifications.
Project Inspection Test Plan
4. Definition/Abbreviations:
DESIGNATIO TATWEER
NAME CPR QUALIFICATION CONTACT NO
N ID
HSSE NEBOSH Diploma
Ali Juma 660111802 AS000456 39461659
Manager NEBOSH IGC 123
Taha Ismail 840807970 Safety Officer AS000659 IOSH / GC2 36055638
6. Responsibilities:
COMSIP will be overall responsible for proper execution methods, reporting, following safe
practices during the entire stage of project.
The Project Manager (COMSIP) shall be responsible for monitoring and organization of the project.
Planning Engineer (COMSIP) shall be responsible for the overall project schedule and breakup of
the project schedule, monitoring and reporting the productivity and percentage completion.
Construction Manager (COMSIP) shall be responsible for overall execution and control of the site
activities, issue of drawings received from Project Manager to site supervisors, control and
maintain the required resources to achieve the targets.
COMSIP HSE In-charge / Officer shall be responsible for site surveillance, reporting HSE
infractions, recommending corrective action and ensuring compliance with Client- HSE program.
The Electrical supervisors / Foreman (COMSIP) shall be responsible for the proper and safe
execution of the work, without any damage to the OWNER’s property.
Performing Authority shall be responsible for performing or supervising work carried out under
permit conditions and remains at the worksite while work is being carried out.
QC In-charge and Inspector (COMSIP) shall be responsible for performing and ensuring that all the
inspection activities are performed in accordance with the approved Inspection Test Plan.
Ensure that all materials which involved construction equipment, support related testing &
measuring apparatus, hand tools etc., are available in the warehouse and comply with the project
specifications and standards. Site handling and identification of all materials and components shall
be in accordance with Project Requirement.
Check if all materials/equipment upon received and to be transported to the working place are in
good condition/ not damage prior to installation. All materials of doubtful condition on quality shall
be immediately segregated from the job site.
Over hanging from the trailer/truck body of any material are not allowed. Ensure that all the
materials properly secured during transit.
Ensure safety barriers are erected at designated work areas with enough warning boards.
Trenching
The cable route is to be investigated and surveyed. The available drawings shall be studied in
detail and ascertain the position of existing underground utilities using cable locator and using trial
hole survey report.
Mark the cable trench route as per the approved cable route drawing using WHITE color powder or
similar.
Mechanical Excavation shall be done with extra care to avoid hitting other assets such as pipelines
and other underground utilities.
If existing underground facilities are identified Excavation shall be done manually by appropriate
hand tools & once exposed, measures shall be taken to protect from damage.
The excavated material shall be stacked away from the edge of the trench to provide a walkway
and to avoid excavated soil falling in the trench
Barricades, Sign Boards etc. should be provided around the excavated area.
Elevations should be periodically checked to obtain the required depth of excavation.
Backfilling and compaction shall be commenced after completing all layers of covering of laid
cables by approved back fill material followed by placement of cable protection tiles and inspected
by TP QC.
After the cable tiles are covered with 200mm of compacted backfill, PVC warning tape shall be laid.
After laying the warming tape the same procedure shall be repeated for backfilling and compaction
till the top of the cable trench.
Pre-cast concrete cable route markers shall be installed along the route of the direct buried cables,
at duct and joint positions and at all places where the route changes direction, on straight routes,
cable markers shall be installed not exceeding 25 meters.
Foundation, support and Cabinet Installation
Ensure that the area where the equipment will be installed is surface leveled and has clear access.
Lifting and rigging should conform to the manual and recommendation and should be in
accordance to its procedure.
The support structure must be installed as per the approved drawing: starting with the foundation
and the rest of the support structure shall be mounted as per drawing.
Install the cabinet on the support with proper mounting accessories.
The cabinet is occupied with passive equipment’s and no grounding or earthing will be provided for
the structure and cabinet.
After successful completion submit RFI to QC Dept. and get the installation inspection as per ITP.
HOOKUPS & SYSTEM IMPROVEMENTS
WORK FOR FIBER OPTIC NETWORK PROJECT
Method Statement & Risk Assessment for Cabinet
Revision – A0 TP-GDUS-01163-MST-A4
Replacement at GDU's
Pre-Testing
Inform to all operations team who are related this work.
Verify all the 1G existing ring are operational.
Fusion Splicing work steps
Open the splice enclosure and markdown all the existing fibers.
Cut all three existing cables (WM28 Tie In, LRVS13 & WM27 Tie In).
Organize all the three cables inside the cabinet.
Splice 1-6 fibers from WM28 tie in to WM27 1-6 fibers
Splice 1-6 fibers from LRVS13 to WM27 7-12 fibers
Splice 13-18 fibers from LRVS13 to WM28 tie in
For detailed fusion splicing procedure see the separately attached approved method statement.
Post Testing
Perform Bidirectional OTDR test between the end to end locations if needed
Perform Bidirectional LSPM test between the end to end locations if needed
Verify all the 1G existing ring are operational.
Inform to all operations team who are related this work.
9. Emergency Procedures:
In the event of an emergency, stop the work and all the workers at the site will go to the nearest assembly
point.
Inform the area owner first (Tatweer) and report the issue. Dial 88883
Comsip shall ensure that the site supervisor, foremen and Safety officer have mobile phones for easy
communications.
Compactor
19. Control Measures, the below key recommended safeguards shall be strictly followed:
1. All employees shall have valid Tatweer Badge and security sticker for their vehicles/fleet
HOOKUPS & SYSTEM IMPROVEMENTS
WORK FOR FIBER OPTIC NETWORK PROJECT
Method Statement & Risk Assessment for Cabinet
Revision – A0 TP-GDUS-01163-MST-A4
Replacement at GDU's
2. Ensure to have applicable safe system of work/permits/certificates from concern authorities prior to
commence the respective job.
3. Ensure performing authority or his delegation must full time present at site for effective site
supervision.
4. Before starting job each day, contractor Supervisor shall conduct Tool Box Talks for safety
awareness on relevant hazard & controls.
5. Safety signs and barricades shall be placed as required & respect the safety sign board & barrier-
“they are there for a reason”
6. All employees involved in the job shall be Competent and enough experienced.
7. Adequate site supervision (Full time Performing Authority) and safety coverage shall be provided
8. Ensure strict compliance of Tatweer Heat Stress Index code and management- HSE -061
9. All the employees shall wear their suitable personal protective equipment (PPE) and personal H2S
monitor at all times at jobsite.
10. Enforcing & practice stop work culture if condition dictate unsafe
11. Maintain the Simultaneous operation & relation with other contractors by Conducting SIMOPS
meeting.
12. No smoking allowed except designated smoking area.
13. Employees are prohibited to come or work at site under the influence of drugs & Alcohol
14. While driving- wearing seat belts are mandatory & use of mobile phones are prohibited while
driving.
15. Adhere to maximum road speed limit – 70 KPH on main road and 50 KPH on interior road
otherwise posted.
16. Ensure all equipment shall be inspected and certified before use including competency of
operators.
17. First aid box and emergency equipment shall be inspected and ensure present of certified first aid
responder to be at working site.
18. All Incidents, near miss shall be report promptly to the supervisor/HSE adviser and to TP control
room on 88 88 3 and HSE department by email To [email protected]
19. Emergency equipment shall be ready for use such as first Aid box, etc...
20. In case of any emergency, proceed to nearest DESIGNATED Safe Assembly Point and follow
instructions of Emergency Response Team
21. The required firefighting equipment shall be inspected and available at work site
22. Respective HSE checklist to be used to ensure the work sites have safe plant/equipment & working
environment
23. Ensure to have approved land Management way leave for its full compliance where & when
required
24. Basic welfare facilities shall be provided for site crews. - Rest shelter. Cool drinking water, portable
toilets, lunch room etc.
25. Standard tools & Equipment shall be used. No home-made tools allowed.
26. Ensure before leaving the work site the area shall be checked for proper house-keeping,
elimination of all possible sources of fire, shutdown of all construction equipment, and proper
storage of tools and tackles etc.
27. Necessary safety measures will be taken while working near the existing facilities. Maintain safe
distance from power lines.
HOOKUPS & SYSTEM IMPROVEMENTS
WORK FOR FIBER OPTIC NETWORK PROJECT
Method Statement & Risk Assessment for Cabinet
Revision – A0 TP-GDUS-01163-MST-A4
Replacement at GDU's
20. Other:
Not Applicable
HOOKUPS & SYSTEM IMPROVEMENTS WORK FOR FIBER OPTIC NETWORK PROJECT
Revision – A0 Method Statement & Risk Assessment for Cabinet Replacement at GDU's TP-GDUS-01163-MST-A4
Note: The following are examples on Hazard and Consequence:
Hazard
Consequence
Ache/pain May cause irritation to skin, eyes, and respiratory tract Irritation to respiratory system
Back, arm disorders and may cause allergic reaction and breathing Irritation to skin, and respiratory tract
Back, neck pain and injuries difficulties Irritation to the eyes and throat
Burns Major injuries (i.e. amputations, major fractures, Irritation to respiratory system and eyes
Bursting of sludge drain multiple injuries) or health effects (i.e. severely life Irritation to respiratory system, eyes and skin
Cancer shortening disease, occupational illness) Irritation to skin
Carpel Tunnel Syndrome Lower back injury
Causes burns to any area of contact & destructive Lower performance
to upper respiratory tract Nuisances smell
Cold burns Physical injury
Cuts or lacerations Psychological pressure
Death Redness of skin
Diseases and infections Serious burns
Drowning Serious burns or death
Environmental impact Single or multiple fatalities or permanent disability
Electrical Shock Slips or trips under insufficient lighting
Explosion Sprains and fractures
Eye burns Sprints, cuts or fractures
Eye cataract Stinging eye irritation and nose or throat irritation
Eye irritation Toxic
Eyestrain Unconsciousness
Fatigue/stress Upper limb disorders
Fire Visual discomfort
First aid injury Wrist pain and tense muscles
Fractures Head injury
Frost bite Heat dermatitis
Lost Time/ Non Lost Time injury (i.e. sprains, Heat exhaustion
fracture, cut, lacerations, burns or bruises) or health Heat stress
effect (i.e. deafness or dermatitis) Heat stroke
Document Title:
Date: DD-MM-YYYY
Attachments: YES NO
1
2