CHECKLIST For Installation of Power Cables

The checklist ensures that power cables and wires are properly installed according to specifications by verifying the approved materials are used, cable trays and conduits are clean before installation, correct cable sizing is used, color coding follows specifications, emergency and normal circuits use separate conduits, bending radiuses meet manufacturer standards, cables are supported properly, sufficient space remains in cable trays after pulling, extra length is provided for termination, cables are tagged, and insulation resistance and continuity tests are conducted after installation.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (6 votes)
7K views

CHECKLIST For Installation of Power Cables

The checklist ensures that power cables and wires are properly installed according to specifications by verifying the approved materials are used, cable trays and conduits are clean before installation, correct cable sizing is used, color coding follows specifications, emergency and normal circuits use separate conduits, bending radiuses meet manufacturer standards, cables are supported properly, sufficient space remains in cable trays after pulling, extra length is provided for termination, cables are tagged, and insulation resistance and continuity tests are conducted after installation.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

CHECK LIST FOR INSTALLATION OF

POWER CABLE AND WIRES

S.No. Description Yes No Remarks

Check that the materials are in accordance


1.
with the approved material submittal
Ensure the cable tray, conduits & trunking is
2.
clean before installation.
Ensure the correct size of cable and wires
3.
are used.
Ensure proper color coding is followed as per
4.
the specification and approved drawings.
Ensure emergency and normal circuits are
5.
run through separate conduits.
Check cable bending radius is as per
6.
manufacturer’s recommendation.
Check cables and wires pulled inside the
7. containments are supported properly as per
specification.
Check if there is sufficient free space in cable
8.
tray after cable pulling as per standard.

Ensure extra length of cable & wires is


9.
provided for termination.

10. Check for tagging of cable & wires.

Conduct insulation resistance test / continuity


11. after the installation of cables, wires, and
control and signal cables.