Format Progress Report Sumbawa

This document is a monthly progress report for the EPC Infrastructure Post-Harvest Modern Rice Milling Plant project. It provides an executive summary of engineering, procurement, and construction activities for the past month at the Gresik site, including house repair work and settling pond repairs. It outlines objectives for the upcoming week in these areas and attachments include weekly and monthly schedule updates, progress details for engineering, procurement, construction and commissioning, and a manpower status table.

Uploaded by

Febry Christoper
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
84 views

Format Progress Report Sumbawa

This document is a monthly progress report for the EPC Infrastructure Post-Harvest Modern Rice Milling Plant project. It provides an executive summary of engineering, procurement, and construction activities for the past month at the Gresik site, including house repair work and settling pond repairs. It outlines objectives for the upcoming week in these areas and attachments include weekly and monthly schedule updates, progress details for engineering, procurement, construction and commissioning, and a manpower status table.

Uploaded by

Febry Christoper
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Pekerjaan Engineering Procurement And Construction

(EPC) Infrastruktur Pasca Panen Modern Rice Milling


Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 1 OF 10

CLIENT/OWNER : Perum BULOG


CONTRACTOR : PT Barata Indonesia (Persero)
PROJECT NAME : EPC Infrastruktur Pasca Panen Modern
Rice Milling Plant (MRMP)
LOCATION : Sumbawa

For
0
Proposal
DI BUAT DI PERIKSA DI SETUJUI DI PERIKSA DI SETUJUI
REV. TGL STATUS
PT. BARATA INDONESIA Perum BULOG
Pekerjaan Engineering Procurement And Construction
(EPC) Infrastruktur Pasca Panen Modern Rice Milling
Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 2 OF 10

MONTHLY REPORT
EPCC
(BULAN TAHUN )

PURCHASE ORDER NO :
PROJECT NAME : PEMBANGUNAN INFRASTRUKTUR PASCA
PANEN MODERN RICE MILLING PLANT
(MRMP)
DATE :
Pekerjaan Engineering Procurement And Construction
(EPC) Infrastruktur Pasca Panen Modern Rice Milling
Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 3 OF 10

Table of Contents

1. EXECUTIVE SUMMARY............................................................................................... 4
2. OBJECTIVES FOR THIS WEEK ...................................................................................... 5
2.1. ENGINEERING 5
2.2. CONSTRUCTION 5
2.3. PROCUREMENT 5
3. OBJECTIVES ACHIEVED NEXT WEEK ............................................................................ 5
3.1. DESIGN ENGINEERING & PROJECT MANAGEMENT 5
3.2. PROCUREMENT 5
3.3. CONSTRUCTION 5
4. ATTACHMENT ........................................................................................................... 6
4.1. WEEK S-CURVE 6
4.2. MONTHLY S – CURVE 6
4.3. DETAIL ENGINEERING PROGRESS 7
4.4. DETAIL PROCUREMENT PROGRESS 7
4.5. DETAIL CONSTRUCTION PROGRESS 8
4.6. DETAIL COMMISIONING PROGRESS 8
4.7. MANPOWER STATUS 9
5. OBSTACLE AND ACTION PLAN .................................................................................. 10
6. PROJECT PHOTOGRAPHY ......................................................................................... 10
Pekerjaan Engineering Procurement And Construction
(EPC) Infrastruktur Pasca Panen Modern Rice Milling
Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 4 OF 10

1. Executive Summary
Activity until this month for Engineering activity at Gresik are Approval & Approved
Documents, Drawing detail to House Repairing Work, Drawing detail to Settiling Pond
Repairing Work and Document and Image Revision. Construction activity are house
repairing work and repairing or demolition settling pond.

1.1 Progress Summary


Pekerjaan Engineering Procurement And Construction
(EPC) Infrastruktur Pasca Panen Modern Rice Milling
Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 5 OF 10

2. Objectives for This Week


2.1. Engineering

2.2. Construction

2.3. Procurement

3. Objectives Achieved Next Week


3.1. Design Engineering & Project Management

3.2. Procurement

3.3. Construction

Pekerjaan Engineering Procurement And Construction
(EPC) Infrastruktur Pasca Panen Modern Rice Milling
Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 6 OF 10

4. ATTACHMENT
4.1. Week S-Curve

4.1. Week S-CURVE

4.2. Monthly S – Curve

4.2. Monthly S-Curve


Pekerjaan Engineering Procurement And Construction
(EPC) Infrastruktur Pasca Panen Modern Rice Milling
Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 7 OF 10

4.3. Detail Engineering Progress

4.3. Detail Engineering Progress

4.4. Detail Procurement Progress

4.4. Detail Procurement Progress


Pekerjaan Engineering Procurement And Construction
(EPC) Infrastruktur Pasca Panen Modern Rice Milling
Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 8 OF 10

4.5. Detail Construction Progress

4.5. Detail Construction Progress

4.6. Detail Commisioning Progress

4.6. Detail Commisioning Progress


Pekerjaan Engineering Procurement And Construction
(EPC) Infrastruktur Pasca Panen Modern Rice Milling
Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 9 OF 10

4.7. Manpower Status

No Project Management Total Name Remark


(example)
1 Project Manager
2 Construction Manager
3 Procurement Manager
4 Procurement Supervisor

5 Finance & GA Manager


6 Finance & GA Supervisor
7 QA / QC Manager
8 Project Control Manager
9 Project Control Supervisor
10 Document Control Head
Office
11 Document Control Site
12 Engineering Manager
13 Mechanical Manager

14 Piping Engineer

15 Civil Engineer

16 Electrical & Instrument


Engineer
Pekerjaan Engineering Procurement And Construction
(EPC) Infrastruktur Pasca Panen Modern Rice Milling
Plant (MRMP)
Document No.: Manajemen Pelaksanaan Rev. : 0
Page No
MRMP-SB-GEN-DOC-009 Format Progress Report 10 OF 10

17 Process Engineer

18 Civil Supervisor
19 Field Engineer

20 HSE Officer
21 Piping Drafter
22 Warehouse Man
23 Surveyor
24 Surveyor Assistant

5. Obstacle and Action Plan

No Obstacle Impact Action Plan Action By Status Due