Cold Water System in Buildings
Cold Water System in Buildings
Design of Internal and external components of water supply systems forms another
aspect of my professional work experience. Highlighted below are some of the major
The Internal cold and hot water supply network are meant to permanently assure
discharge at the various consumption points at the required pressure. Hence to have an
optimal design consideration must be given to water supply from the choice of storage
There are tables that give the recommended consumption of water per person per day
depending on the building purpose. Please see table 1 in the appendix. For office use, the
recommended consumption of water per person per day is given as 45 litres. It is also
obvious that at the design stage the occupancy of a building may be unknown therefore
there is need to have a guide; Table 2 (please see appendix) gives a recommendation
Zaki-biam Business office with an area of 319sqm (22.0m x 14.5m) as an office has an
estimated occupancy of 1person per 10sqm net floor area. This office usually will open
for 10hours; hence the estimated water storage requirement for this office is given by
the expression.
= 598.13litres/10hrs
While the above mathematical expression provides a basis for the determination of
required storage capacity for buildings based on the expected occupancy, statistic has
shown that the customer influx to the Zaki-biam business office is an average of 45. This
figure however, gets up to 60 during certain peak period of the month; hence for the
purpose of an effective and efficient design the occupancy of this building is put at 60 to
take care of peak periods of the months and the anticipated increase in the customer
Bases on the above occupancy figure of 60; the required storage capacity of the business
Making provision for a minimum of an extra day in case of system failure the storage
= 1125 x 2 = 2250litres
Two overhead storage tanks of 1500litres capacity each were than provided.
have been established based on the frequency of use of these individual appliances and
the desired water flow rate from them. Table 3 and Table 4 gives the recommended flow
rates for various sanitary appliances (litres/sec) and loading units respectively.
From tables, the loading unit for Zaki-biam business office is given as follows;
MAIN BUILDING:
WC = 2 x 2 = 4
WHB = 2 x 2.5 = 5
SINK = 1 x 5 = 5
MOPOL HOUSE
WC = 1 x 2 = 2
EXTERNAL
BIB TAP =2 x 10 = 20
Based on the above loading units the required flow rate from the conversion graph is
given as 0.7 litre/sec, hence the 1litre/sec was adopted as the required flow rate through
d =5 √q2 x 25 x L x 105 /H
L = length (effective) of pipe (m) (actual length + allowance for bends, tees, etc)
1. Prepare the pipe work diagram, numbering from junction to junction, starting
4. Convert the loading units into design flow rates in litres/sec (use probability
equation)
5. Starting from storage tank with known flow rates and velocity less than 3m/sec,
(preferably in between 1m/sec and 0.8m/sec), select a diameter of pipe. Note that
6. Determine the height difference between the inlet and the outlet of pipe (positive
10. Determine actual head loss of pipe work considering effective length
12. If the residual head is less than the required head, for a particular outlet fitting or
if the head is negative, repeat the same process with a larger diameter.
NOTE:
(a) If the details of pipe fittings and valves are not known, add 20 to 30% of actual
head loss in pipe work, as minor head loss due to fittings and valves.
(b) The average rate of flow is to be taken for single fitting, while designing the last
pipe
STEP ONE:
A pipe work diagram as shown below numbering from junction to junction was
Flow rate was calculated using the below probability equation; where
This was then use to calculate the flow in each pipe starting from the single pipes then to
each branch and the entire network of pipes as follows(Z is gotten from tables);
Pipe:
EK = KL + KM = 1 Q = 0.25 x √1 = 0.25lit/sec
BE = EF + EK = 1 + 2 = 3 Q = 0.25 x √3 = 0.43lit/sec
stated and used as the basis for preliminary calculations. Using the above flow rates,
assumed pipe diameter, velocity (m/sec) and head loss (m/m) values from tables (pls
.table ? and table ? in appendix); the results gotten are then tabulated as in table below;
diameter that should be added to the Actual pipe length for the purpose determining the
head loss due to friction. The table? In the appendix gives the approximate equivalent
AB: with 1no 90° bend and 1no gate valve = 32 x 1 x 36 + 32 x 7 = 1152 + 224 = 1376mm
= 1.38m
With the above method the effective length for all the pipe lengths are gotten.
CALCULATING HEAD LOSS Hf:
The Hazen William’s equation is used to compute the Head loss Hf and this depends on
The above method was used to determine the rest values of Head loss, Hf for the
Since the details of pipe fittings and valves are not fully ascertained, 20 to 30% of actual
head loss in pipe network was added as minor head loss due to fittings and valves.
HEAD (M)
The Head at the various junction of the pipe network was calculated by taking the start
point of the network in this case “A” as having “0” (Zero) head as this is origin of the
cold water supply and the head increases as the water flows down from the overhead
tank. Subsequent head values at the various nodes of the pipe network were determined
by subtracting the preceding head losses at the various nodes from the head value at the
The minimum required head/pressure for common appliances are given in table ?
(please see appendix) Following the determination of the available head (please refer to
table ?) ; the available head in pipe Tap CD, Water closet (WC) KM were found to be
below the minimum required head for these appliances i.e. -0.55 and 0.25 respectively
while Wash basinKL had an available head of 0.52 which is just above the minimum
The above scenario necessitated that the pipe diameter CD and EK be changed from
15mm to 20mm diameter and the calculations process was repeated and the Available
head values gotten for tap CD, Water closet (WC) KM and Wash basin (WB) KL
improved considerably and were all above the minimum required head for the
respective fittings this was then adopted as it fulfilled all design requirements and based
on these drawings were then produced for the cold water reticulation system for the
Zaki-biam office.