API RBI Tank Case Study 1
API RBI Tank Case Study 1
Presentation Overview
• Introduction
• General RBI Information
• Atmospheric Storage Tank RBI Overview
• Tank Case Study
• RBI Results
• Lessons Learned
2
Introduction
3
General RBI Information
4
Probability of Failure
5
Atmospheric Storage Tank RBI
6
What is a Tank Failure??
1 Dike Area
6 Tank
Surface Water
Offsite 3
2 Onsite
Subsurface Soil 4
Ground Water 5
7
Atmospheric Storage Tank RBI
• Fluid properties determined by fluid selection
• Hydraulic conductivity and fluid seepage velocity
determined from density and viscosity
Table 7.1 – Fluids and Fluid Properties for Atmospheric storage Tank Consequence Analysis
Level 1
Consequence Liquid Dynamic
Liquid Density
Fluid Analysis Molecular Weight Viscosity
(lb/ft3)
Representative (lbf-s/ft2)
Fluid
8
Atmospheric Storage Tank RBI
Table 7.2 – Soil Types and Properties for Atmospheric storage Tank Consequence Analysis
Hydraulic Conductivity Hydraulic Conductivity
for Water Lower for Water Upper
Soil Type Soil Porosity
Bound Bound
(in/sec) (in/sec)
Silt 3 94E 6
3.94E-6 3 94E 7
3.94E-7 0 41
0.41
9
Atmospheric Storage Tank RBI
• Release Rate Calculation
– Liquid head is assumed to be constant with time
– Leak into ground is as a continuous porous media, by the
soil porosity for tank foundations
– Product leakage flow rate through a small hole is a function
of the soil and fluid properties as well as liquid head (fill
height)
– Tank rupture assumes all product in the tank is lost
– Bernoulli or Girard equation used depending on hydraulic
conductivity
• API RBI for atmospheric storage tanks is currently based
on financial consequences only which requires the use of
a Financial Risk Target
10
Atmospheric Storage Tank RBI
• Financial environmental cost from shell course leakage
⎛ Bblindike
leak
⋅ Cindike + Bblssleak − onsite ⋅ Css − onite +
⎞
leak
FCenviron =⎜ ⎟
⎜ Bbl leak ⋅ C + Bbl leak
⋅ C ⎟
⎝ ss − offsite ss − offite water water ⎠
• Financial environmental cost for a shell course rupture
⎛ Bblindike
rupture
⋅ Cindike + Bblssrupture
− onsite ⋅ Css − onite +
⎞
rupture
p
FCenviron =⎜ ⎟
⎜ Bbl rupture ⋅ C ⎟
ss − offite + Bblwater ⋅ Cwater
rupture
⎝ ss − offsite ⎠
• Total financial environmental cost for shell courses
FCenviron = FCenviron
leak
+ FCenviron
rupture
11
Atmospheric Storage Tank RBI
• Component damage cost for shell courses
⎛ 4 ⎞
⎜ ∑ gff n ⋅ holecostn ⎟
FCcmd = ⎜ n =1 ⎟ ⋅ matcost
⎜ gfftotal ⎟
⎜ ⎟
⎝ ⎠
• Outage Days and the cost of business interruption
t t l = FCenviron
FCtotal i + FCcmdd + FC prodd
• The above consequence calculation is for the tank shell
courses, a similar consequence calculation is used for
th tank
the t k floor
fl
12
Case Study Background
13
Tank Description
• T-1
– Diesel Product Tank
– Installed in 1956, floor replaced in 1992
– 30’ diameter, 40’ tall
– Sits on a ring wall with no release prevention
– No internal inspection since floor replacement
• T-17
T 17
– Heavy Gas Oil Tank
– Installed in 1993
– 120’ di
diameter, 48’ tall
ll
– Sits on a graded concrete slab
– No internal inspection since installation
14
T-143
15
T-1
16
API RBI Risk Targets
17
Key Inputs
18
Damage Mechanisms
19
Tank Bottom Corrosion
20
Thinning Damage
Base Metal Measured Base Metal Calculated
Component Component Type
Rate (mpy)* Rate (mpy)
T-143-Course 2 COURSE-1 0 -
T-143-Course 3 COURSE-2 0 -
T-143-Course 4 COURSE-3 0 -
T 143 C
T-143-Course 4 COURSE 4
COURSE-4 0 -
T-173-Course 1 COURSE-1 0 -
T-173-Course 2 COURSE-2 0 -
T-173-Course 3 COURSE-3 0 -
T-173-Course 4 COURSE-4 0 -
21
External Damage
T 143 Course 1
T-143-Course COURSE 1
COURSE-1 Mineral Wool Marine 84
8.4
22
RBI Results
• Inspection Planning
External
Thinning Cracking RBI
Component Component Damage
Component Inspection Inspection Inspection
Description Type Inspection
Category Category Date
Category
T-143-Pressure
T-143-Shell DRUM C 2015-10-24
Vessel
23
RBI Results - Inspection Plans
• T-1 Bottom – C-level bottom thinning by February of 2015.
– Scanning of 5 to 10+% of the floor plates while supplementing scanning near
the shell and the floor
– 100% visual inspection of the floor
– Scanning should progressively increase if damage is found.
• T-17 Bottom – C-level bottom thinning by March of 2017.
– S
Scanning
i off 5 tto 10+% off the
th floor
fl plates
l t while
hil supplementing
l ti scanning
i near
the shell and the floor
– 100% visual inspection of the floor
– Scanning should progressively increase if damage is found.
• T-1
T 1 Pressure
P Vessel
V l – Modeled
M d l d as a pressure vessel,
l CC-level
l l external
t l
shell inspection recommendation to be completed by October of 2015.
– 95 to 100% external visual inspection of the insulation
– Follow-up with profile or real time radiography of 33 to 65% of suspect areas
– Follow-up of corroded areas with 95 to 100% visual inspection of the exposed
surface with UT, RT or pit gauge.
– This inspection does NOT require an entry.
24
RBI Results – Risk Drivers
• T-1 Bottom
– 15+ years of service with no corrosion data for the bottom
– Conservative estimate for tank bottom corrosion rate of 9.5 mpy
– The calculated bottom thickness at this date using 9.5 mpy corrosion rate
is 0.101” which is at the minimum thickness of 0.10” for tanks without leak
detection as prescribed in API 653.
• T-17 Bottom
– 15+ years of service with no corrosion data for the bottom
– Conservative estimate for tank bottom corrosion rate of 11.0 mpy
g 11.0 mpy
– The calculated bottom thickness at this date using py corrosion rate
is 0.056” which is above the minimum thickness of 0.05” for tanks with
leak detection as prescribed in API 653.
• T-1 Pressure Vessel
– Estimated external corrosion rate of 8.4 mpypy
– The insulation has failed on the tank creating a potential CUI concern.
25
Lessons Learned
26