0% found this document useful (0 votes)
51 views

Exam For Module123

The document contains questions about power plant equipment and systems. It includes multiple choice questions about components like valves, pumps, turbines and generators. The questions cover topics like capacities, functions, parts and configurations of the different systems in a power plant.

Uploaded by

Kian Tecson
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views

Exam For Module123

The document contains questions about power plant equipment and systems. It includes multiple choice questions about components like valves, pumps, turbines and generators. The questions cover topics like capacities, functions, parts and configurations of the different systems in a power plant.

Uploaded by

Kian Tecson
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 12

SET A

1. What is the diameter of the Butterfly Valve?


a. 48 inches
b. 96 inches
c. 69 inches
d. 84 inches

2. What RWS component or equipment that removes heat from the Generator winding?
a. cooling coil
b. cooling water
c. air cooler
d. conservator

3. What equipment that is used to supply compressed air to the high pressure air tank?
a. air pressure tank
b. air compressor
c. air blower pump
d. pneumatic system

4. What device protects high pressure air tank from overpressure?


a. pressure regulator valve
b. unloader valve
c. pressure relief valve
d. check valve

5. What plant system provides cooling to the bearings and air coolers of Generators?
a. raw water system
b. raw air system
c. water pump
d. lube oil system

6. A system that provides the required lubrication to the turbine guide bearing, generator’s
lower guide bearing, upper guide bearing, and thrust bearing for a smooth operation of the
unit?
a. Lubricating Oil System
b. Lubricating Grease System
c. Oil and Grease Lubrication
d. Fluid Lubrication

7. What dewatering pump equipment that has no motor pump?


a. Jet Pump
b. Sump Pump
c. Submersible Pump
d. Centrifugal Pump

8. What turbine component permits water to flow through, thus, filling the scroll case?
a. Raw Water System
b. Turbine Wicket Gates
c. By-pass valve
d. Turbine Runner
9. What component of RWS that regulates water pressure ( from 250 psi to 50 psi)
a. High pressure gate valve
b. Pressure regulating Valve
c. Low Pressure gate Valve
d. Pressure relief Valve

10. What is the volume capacity of the governor sump tank?


a. 5030 liters
b. 1090 liters
c. 3050 liters
d. 2060 liters

11. How many wicket gates are there in each turbine?


a. 12
b. 24
c. 36k
d. 48

12. What downstream element is use to reduce water leakage within the turbine?
a. Turbine shaft
b. Shaft seal
c. Turbine cover
d. Ring cover

13. How many sets of air coolers are installed around the generator?
a. 6
b. 9
c. 12
d. 15

14. How many brake pads/shoes are there that are in contact with the generator rotor?
a. 2
b. 4
c. 6
d. 8

15. What speed the turbine shaft is capable of sustaining an adequate bearing oil wedge?
a. 400 rpm
b. 300 rpm
c. 200 rpm
d. 100 rpm

16. The function of ______________ is to allow oil fill in the gap between thrust bearing shoe
and runner, and floats the rotor on the film of oil.
a. Generator Jacking System
b. Generator Braking System
c. Turbine Control System
d. Generator Excitation System

17. When generator speed is ________, apply brake by pushing down brake applicator at 10
seconds interval.
a. 40 rpm
b. 60 rpm
c. 80 rpm
d. 100 rpm
18. What is the pressure capacity of the air braking tank used in braking the generator?
a. 100 psi
b. 125 psi
c. 300 psi
d. 600 psi
19. Thrust bearing is a particular type of rotary bearing. They are designed to support a
predominantly ______________?
a. Radial load
b. Axial load
c. No load
d. Full load

20. The main function of the guide bearings is to keep the shaft aligned vertically and support any
______________ that can take place during the operation.
a. Radial load
b. Axial load
c. Full load
d. No load

21. Leakage water arising in the head cover goes down directly into the?
a. Sump pump pit only
b. Jet pump pit only
c. Sump pump pit and jet pump pit.
d. Tailrace

22. What is the diameter of the turbine shaft?


a. 18 inches
b. 19 inches
c. 20 inches
d. 21 inches

23. The function of the _________ is to control the operating ring for wicket gate positioning.
a. Butterfly valve
b. Servomotors
c. Auxiliary valve
d. Unloader valve

24. The function of the __________ to control the flow of water going to the turbine.
a. Wicket gates
b. Check valve
c. Suction valve
d. Butterfly valve

25. The type of device that drives the electric generator.


a. Governor
b. Motor
c. Pump
d. Prime mover

26. The device which transforms the output electric signal of the governor into a proportional
mechanical displacement.
a. Transformer
b. Transducer
c. Transponder
d. Transporter
27. Used to produce a signal proportional to turbine speed for the governor speed sensing circuit,
electronic speed switches and speed indicators.
a. Pressure gauge
b. Float switch
c. Speed signal generator
d. Turbine runner

28. Used to control the opening and closing of the pressurized oil that enters the servomotor.
a. Main relay valve
b. Auxiliary valve
c. Pressure regulator valve
d. Pressure relief valve

29. The Governor Pressure tank by Fuji Electric Co., Ltd. has capacity of?
a. 1000 liters
b. 2000 liters
c. 3000 liters
d. 5000 liters

30. It supplies the governor the information about the opening degree of the servomotor.
a. Static Feedback Unit
b. Dynamic Feedback Unit
c. Frequency Feedback Unit
d. Voltage Feedback Unit

31. What is volume capacity of LGB and ThB Oil Reservoir for unit 4?
a. 45 drums
b. 54 drums
c. 48 drums
d. 36 drums

32. The function of the ______________ is to gradually slow down the speed of turbine shaft from
rated speed to at rest.
a. Generator braking system
b. Generator jacking system
c. Generator cooling system
d. Generator excitation system

33. How many water lines are there in a raw water cooling system?
a. 1
b. 2
c. 5
d. 6

34. This valve is used to shut-down the entire cooling system.


a. 10” high pressure main gate valve with by-pass.
b. Two 10” low pressure side gate valve.
c. Two 10” high pressure side gate valves with by-pass.
d. Emergency shutdown valve.
35. Used to filter the water to prevent clogging up in the generator air coolers and other cooling
equipment.
a. Strainer
b. Scraper
c. Polisher
d. Backwasher

36. Currently, how many jet pumps are there used in jet pump pit operation?
a. 2
b. 3
c. 4
d. 5

37. The stationary top part of a hydraulic turbine.


a. Head cover
b. Head band
c. Head elevation
d. Head set

38. What is the rotation direction of the turbine runner viewed from the top?
a. Counter clockwise
b. Clockwise
c. All of the above
d. None of the above

39. The turbine runners are of ___________ and are designed and constructed to withstand safely
the stresses due to operation at maximum run away speed.
a. Francis Type
b. Kaplan Type
c. Pelton Type
d. Screw Type

40. The turbine main guide bearing is of ___________, located above the turbine runner, and
consists of a bearing support and a removable bearing shell.
a. Self-lubricating type
b. Non Self-lubricating type
c. All of the above
d. None of the above
Answer Key Set A

1. D
2. B
3. B
4. C
5. A
6. A
7. A
8. C
9. B
10. C
11. B
12. B
13. A
14. C
15. C
16. A
17. D
18. B
19. B
20. A
21. C
22. B
23. B
24. D
25. D
26. B
27. C
28. A
29. B
30. A
31. A
32. A
33. B
34. A
35. A
36. B
37. A
38. B
39. A
40. A
SET B

1. What is volume capacity of LGB and ThB Oil Reservoir for unit 4?
a. 45 drums
b. 54 drums
c. 48 drums
d. 36 drums

2. The function of the ______________ is to gradually slow down the speed of turbine
shaft from rated speed to at rest.
a. Generator braking system
b. Generator jacking system
c. Generator cooling system
d. Generator excitation system

3. How many water lines are there in a raw water cooling system?
a. 1
b. 2
c. 5
d. 6

4. This valve is used to shut-down the entire cooling system.


a. 10” high pressure main gate valve with by-pass.
b. Two 10” low pressure side gate valve.
c. Two 10” high pressure side gate valves with by-pass.
d. Emergency shutdown valve.

5. Used to filter the water to prevent clogging up in the generator air coolers and other
cooling equipment.
a. Strainer
b. Scraper
c. Polisher
d. Backwasher

6. Currently, how many jet pumps are there used in jet pump pit operation?
a. 2
b. 3
c. 4
d. 5

7. The stationary top part of a hydraulic turbine.


a. Head cover
b. Head band
c. Head elevation
d. Head set

8. What is the rotation direction of the turbine runner viewed from the top?
a. Counter clockwise
b. Clockwise
c. All of the above
d. None of the above
9. The turbine runners are of ___________ and are designed and constructed to withstand
safely the stresses due to operation at maximum run away speed.
a. Francis Type
b. Kaplan Type
c. Pelton Type
d. Screw Type

10. The turbine main guide bearing is of ___________, located above the turbine runner,
and consists of a bearing support and a removable bearing shell.
a. Self-lubricating type
b. Non Self-lubricating type
c. All of the above
d. None of the above

11. Leakage water arising in the head cover goes down directly into the?
a. Sump pump pit only
b. Jet pump pit only
c. Sump pump pit and jet pump pit.
d. Tailrace

12. What is the diameter of the turbine shaft?


a. 18 inches
b. 19 inches
c. 20 inches
d. 21 inches

13. The function of the _________ is to control the operating ring for wicket gate
positioning.
a. Butterfly valve
b. Servomotors
c. Auxiliary valve
d. Unloader valve

14. The function of the __________ to control the flow of water going to the turbine.
a. Wicket gates
b. Check valve
c. Suction valve
d. Butterfly valve

15. The type of device that drives the electric generator.


a. Governor
b. Motor
c. Pump
d. Prime mover

16. The device which transforms the output electric signal of the governor into a
proportional mechanical displacement.
a. Transformer
b. Transducer
c. Transponder
d. Transporter
17. Used to produce a signal proportional to turbine speed for the governor speed sensing
circuit, electronic speed switches and speed indicators.
a. Pressure gauge
b. Float switch
c. Speed signal generator
d. Turbine runner

18. Used to control the opening and closing of the pressurized oil that enters the
servomotor.
a. Main relay valve
b. Auxiliary valve
c. Pressure regulator valve
d. Pressure relief valve

19. The Governor Pressure tank by Fuji Electric Co., Ltd. has capacity of?
a. 1000 liters
b. 2000 liters
c. 3000 liters
d. 5000 liters

20. It supplies the governor the information about the opening degree of the servomotor.
a. Static Feedback Unit
b. Dynamic Feedback Unit
c. Frequency Feedback Unit
d. Voltage Feedback Unit

21. How many wicket gates are there in each turbine?


a. 12
b. 24
c. 36
d. 48

22. What downstream element is use to reduce water leakage within the turbine?
a. Turbine shaft
b. Shaft seal
c. Turbine cover
d. Ring cover

23. How many sets of air coolers are installed around the generator?
a. 6
b. 9
c. 12
d. 15

24. How many brake pads/shoes are there that are in contact with the generator rotor?
a. 2
b. 4
c. 6
d. 8

25. What speed the turbine shaft is capable of sustaining an adequate bearing oil wedge?
a. 400 rpm
b. 300 rpm
c. 200 rpm
d. 100 rpm
26. The function of ______________ is to allow oil fill in the gap between thrust bearing
shoe and runner, and floats the rotor on the film of oil.
a. Generator Jacking System
b. Generator Braking System
c. Turbine Control System
d. Generator Excitation System

27. When generator speed is ________, apply brake by pushing down brake applicator at 10
seconds interval.
a. 40 rpm
b. 60 rpm
c. 80 rpm
d. 100 rpm

28. What is the pressure capacity of the air braking tank used in braking the generator?
a. 100 psi
b. 125 psi
c. 300 psi
d. 600 psi

29. Thrust bearing is a particular type of rotary bearing. They are designed to support a
predominantly ______________?
a. Radial load
b. Axial load
c. No load
d. Full load

30. The main function of the guide bearings is to keep the shaft aligned vertically and
support any ______________ that can take place during the operation.
a. Radial load
b. Axial load
c. Full load
d. No load

31. What is the diameter of the Butterfly Valve?


a. 48 inches
b. 96 inches
c. 69 inches
d. 84 inches

32. What RWS component or equipment that removes heat from the Generator winding?
a. cooling coil
b. cooling water
c. air cooler
d. conservator

33. What equipment that is used to supply compressed air to the high pressure air tank?
a. air pressure tank
b. air compressor
c. air blower pump
d. pneumatic system
34. What device protects high pressure air tank from overpressure?
a. pressure regulator valve
b. unloader valve
c. pressure relief valve
d. check valve

35. What plant system provides cooling to the bearings and air coolers of Generators?
a. raw water system
b. raw air system
c. water pump
d. lube oil system

36. A system that provides the required lubrication to the turbine guide bearing,
generator’s lower guide bearing, upper guide bearing, and thrust bearing for a smooth
operation of the unit?
a. Lubricating Oil System
b. Lubricating Grease System
c. Oil and Grease Lubrication
d. Fluid Lubrication

37. What dewatering pump equipment that has no motor pump?


a. Jet Pump
b. Sump Pump
c. Submersible Pump
d. Centrifugal Pump

38. What turbine component permits water to flow through, thus, filling the scroll case?
a. Raw Water System
b. Turbine Wicket Gates
c. By-pass valve
d. Turbine Runner

39. What component of RWS that regulates water pressure ( from 250 psi to 50 psi)
a. High pressure gate valve
b. Pressure regulating Valve
c. Low Pressure gate Valve
d. Pressure relief Valve

40. What is the volume capacity of the governor sump tank?


a. 5030 liters
b. 1090 liters
c. 3050 liters
d. 2060 liters
Answer Key Set B

1. A
2. A
3. B
4. A
5. A
6. B
7. A
8. B
9. A
10. A
11. C
12. B
13. B
14. D
15. D
16. B
17. C
18. A
19. B
20. A
21. B
22. B
23. A
24. C
25. C
26. A
27. D
28. B
29. B
30. A
31. D
32. B
33. B
34. C
35. A
36. A
37. A
38. C
39. B
40. C