Construction of Flood Control Structure Along Bislak River, Sitio, Magabobo, Brgy. Salsalamagui, Vintar, Ilocos Norte

This document is a certification of first partial payment for the construction of a flood control structure along the Bislak River in Ilocos Norte, Philippines. It details the project location, funding source, contract cost, start and completion dates, inspectors, and engineer. It also includes a table with the description, quantity, unit cost, and total cost for various items of work completed such as a field office, signage, safety programs, mobilization, roads, clearing, embankment, concrete work, and sheet piling, totaling over 11 million pesos. The certification is signed by representatives from the construction, maintenance, planning, and quality assurance sections to confirm satisfactory progress based on plans and specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
137 views

Construction of Flood Control Structure Along Bislak River, Sitio, Magabobo, Brgy. Salsalamagui, Vintar, Ilocos Norte

This document is a certification of first partial payment for the construction of a flood control structure along the Bislak River in Ilocos Norte, Philippines. It details the project location, funding source, contract cost, start and completion dates, inspectors, and engineer. It also includes a table with the description, quantity, unit cost, and total cost for various items of work completed such as a field office, signage, safety programs, mobilization, roads, clearing, embankment, concrete work, and sheet piling, totaling over 11 million pesos. The certification is signed by representatives from the construction, maintenance, planning, and quality assurance sections to confirm satisfactory progress based on plans and specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


st
ILOCOS NORTE 1
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE I
Cavit, Laoag City, Ilocos Norte

CERTIFICATION OF FIRST PARTIAL PAYMENT

Date

NAME OF PROJECT : Construction of Flood Control Structure along Bislak River, Sitio, Magabobo, Brgy.
LOCATION : Salsalamagui, Vintar, Ilocos Norte
SOURCE OF FUND : GAA 2020
APPRO./CONTRACT COST : PHP 20,427,120.50
DATE STARTED : September 29, 2020
DATE COMPLETED :
PROJECT INSPECTOR : RODRIGO F. AGUSTIN
PROJECT ENGINEER : MARK LOUIE B. GALIZA
CONTRACTOR : DJCM Construction Corporation

We the undersigned members of the Inspectorate Team, conducted a joint inspection of the above-stated
project and found the same to be satisfactorily completed/ongoing in accordance with the Plans and Specifications
of the Contract.

ITEM DESCRIPTION OF WORK QUANTITY UNIT COST TOTAL


-
A.1.1(8) Provision of Field Office for the Engineer 4.00 7,475.56 29,902.24
B.5 Project Billboard/Signboard - 2,526.03 -
B.7 Occupational Safety and Health Program 4.00 19,265.88 77,063.52
B.9 Mobilization & Demobilization - 55,311.10 -
B.15(1) Detour/Access Road - 90,717.18 -
1700(2) Clearing and Grubbing - 110,381.70 -
1704(1) Embankment 3,730.25 338.10 1,261,197.53
1712 (2) Concrete Slope Protection 62.43 5,705.56 356,169.58
1713(1) Rubble Concrete 354.00 3,115.43 1,102,862.22
1717(2)a Sheet Pile 3,762.00 2,402.74 9,039,107.88

-
REMARKS 11,866,302.97

ANGELITO A. DIAN ROBERT G. RABAGO


Representative Representative
Construction Section Maintenance Section

LEON C. DAQUIOAG ERWYN R. ALOG


Representative Representative
Planning & Design Section Quality Assurance and Hydrology Section