G99 Type A Final 2020
G99 Type A Final 2020
Contents
Contents
Information Sheets
Decision Tree for Distributed Generation Connection Guides
Connection Process—Capacity Cut Off Points
Provision of Information: DNO Websites
Legislative and Regulatory Documents Hierarchy
F: Selling Electricity
Smart Export Guarantee (SEG)
Contracts For Difference
Glossary
References
Revisions
Distributed Generation Connection Guide:
Information Sheets
The following pages contain a number of information sheets. These bring information that is
contained throughout the Guide into a single page. The information sheets include:
• Decision Tree for the Distributed Generation Connection Guide—to help you to identify
whether this is the right Guide for you.
• Capacity cut off points—a diagram illustrating the impacts that the generation capacity of
your generating equipment has on the requirements and opportunities for your project.
• Provision of Information: DNO websites—a summary of the information you can expect to
find on DNO websites.
You will find the Guide introduction and contents after these information sheets.
i
Decision Tree for the
Distributed Generation Connection Guide
There are a number of Distributed Generation Connection Guides, each with a corresponding
‘Summary’ guide. The purpose of the summary guides is to act as a quick check, providing only
the most useful information in a condensed format. This flowchart guides you to the most
relevant Connection Guide for the Distributed Generation you are planning to install. The Guides
can be found on the Distribution Generation section of the ENA website.
Yes No
Combined Heat and Power (CHP): A micro-CHP plant rated 6 kW (3-phase) (the size of a big
dishwasher 0.8 x 1 x 1 m) could have a thermal output of 18 kW.
ii
Connection Process: Capacity Cut Off Points
The tasks that you have to undertake to get The table below illustrates some of the
connected vary with the capacity of the impacts that the capacity of your generating
generating plant. In general, the bigger the units have on the connection process and
generator, the more complex the connection requirements on you.
requirements.
Connection
Size Definitions
Process
Generation Incentives
England Metering
Single Three North South Licencing Schemes
and
Phase Phase Scotland Scotland
Wales
Smaller Covered by G98 Smaller
Power if connected at Power
Stations low voltage Stations
(230V or 400V)
and type tested.
1MW
Power Generating Modules should
G99 Type B refer to Type D if connection voltage
5MW
is > 110kV.
10MW Must have
G99 Type C CFD
30MW Half (Contracts
Large Power Station Hourly
Must hold an for 50MW
50MW Must hold a metering.
agreement with Medium Difference)
generation Projects in
NGESO—BEGA or Power
licence, unless the order of
BELLA. Station
exempt. several MW
100MW 100MW
G99 Type D Large Power station Must hold a
Larger Must hold a Bilateral Embedded generation Larger
Power Generation Agreement (BEGA) licence. Power
Stations with NGESO. Stations
iii
Provision of Information: DNO Websites
There is a great deal of published information available from your DNO that can be helpful for
your project planning. Some of the most useful sources are summarised here, and links to the
DNO websites are in the table below.
Standards of Performance
Ofgem has set minimum performance standards for connections, both during and after their
construction. If your DNO fails to meet these standards, you may be entitled to receive
payment. Ofgem has guidance documents about these Standards on their website:
www.ofgem.gov.uk/licences-codes-and-standards/standards/quality-service-guaranteed-
standards
Flexibility Services
In recent years, DNOs have been offering customers the opportunity to provide flexibility
services in an effort to control demand and generation on their networks. This can help to solve
congestion issues and free up spare capacity across the DNOs network. Flexible technologies
include batteries, solar plus storage, CHP, Electric Vehicles and other technologies. For more
information refer to the Local Flexibility Markets break out box in Chapter F of the Guides.
iv
Provision of Information: DNO Websites
Active Network Management (ANM)
This is the process of using control systems to manage the real time output of Distributed
Generation in constrained areas. This technique can manage problems on the network such as:
• Thermal Constraints
• Voltage Constraints
• Fault Level
ANM is now been included in Business As Usual connection offers but may only be available in
certain sections of the network. For more information refer to your local DNO website.
Flexible connections
Connecting new generators to the distribution networks in constrained areas can require
reinforcement of the network with associated increased connection costs and waiting times.
DNOs can offer an alternative in the form of flexible connections. This involves acceptance of
constraints within the terms of the connection, such as a maximum export level or restricting
generation export under certain network conditions. Flexible connections can be used as a
temporary solution whilst awaiting the completion of the network upgrades or as a permanent
alternative to reinforcing the network. For more information visit you local DNOs website.
The register will also hold details of network reinforcements associated with new connections as
well as flexibility services. The DNOs are required to keep this register up to date. For more
information on the ECB visit your local DNOs website.
v
Legislative and Regulatory Documents Hierarchy
The following diagram shows the legislative and regulatory documents in the power sector. These
are grouped by category, and where possible the relationship between documents is illustrated.
The documents have been colour coded by document category. The most relevant examples of
each documents are included in the boxes below.
EU
REGULATIONS LICENCES GOVERNMENT POLICY
NETWORK
CODES
AGREEMENTS RENEWABLE
CODES AND STATEMENTS GENERATION
INCENTIVES
TECHNICAL PERFORMANCE TARIFF
STANDARDS STANDARDS REGULATION
vi
Distributed Generation Connection Guide:
An Introduction
Page 1
Distributed Generation Connection Guide:
An Introduction
The format of the Guide which are evolving and a number of issues are
under consultation. The Guide has tried to
This Guide has been written and formatted
capture the most up to date position at the
with you, the reader, in mind. In particular we
time of writing. However, for the most up to
think this Guide will be useful for customers
date information you should refer to key
with generation, installers and developers.
documents and organisation websites. Please
We have tried to make this Guide as clear and
see the reference section for more
easy to read as we can, bearing in mind that
information.
some of the issues discussed are technical and
complex. In particular: Governance of related Codes and documents
• Terms which may be unfamiliar are Many of the codes and other documents
defined or explained in boxes around described in this guide are governed in such a
the main text. way that any interested and materially
affected party can propose a change to the
• Key points and summaries are
codes and documents. This includes the
highlighted.
Connection and Use of System charging
• Text is emboldened for emphasis. arrangements (for both distribution and
• Where necessary the Guide transmission) and the Distribution and Grid
distinguishes between the arrangements Codes. There are also groups with Distributed
that apply in Scotland and those which Generation community and DNO
apply in England and Wales. This is representation where issues can be raised and
indicated with a Scottish flag. discussed which may lead to changes being
proposed.
• At the end of most chapters there is a
pointer on where to find more The overarching group to discuss commercial
information. and procedural issues associated with
connection is the ENA DER (Distributed Energy
Though this Guide is intended for the general Resource) Connections Steering Group. Any
public and should not require the reader to be issues you have for the Group should be
technical or familiar with the energy industry, raised through trade associations who are
please be aware that the topics covered here represented. Please note that practices
are technical and complex. It is therefore between DNOs may be different; for example
necessary to refer to such concepts as voltage where the connection requirements are
and power. Where possible, terms that may location specific or the connection risks and
be unfamiliar have been explained. the network characteristics are different.
Governance of the Guide
This Guide is a Distribution Code Review Panel
(DCRP) document. The DCRP will update the
Guide using similar processes it has for
updating other distribution related
documents.
There are many areas of regulation and
legislation relating to Distributed Generation
Page 2
Distributed Generation Connection Guide:
Is this the right Guide for my project?
Important note: Generation projects can no longer connect under EREC G83 and G59.
Generation will only be allowed to connect under EREC G98 and G99, with an exception for
certain generators. For more information on this transition, refer to “Recent Changes to
Regulations” page—just before Chapter A.
Page 3
Distributed Generation Connection Guide:
Is this the right Guide for my project?
Guide Criteria
Page 4
Distributed Generation Connection Guide:
Is this the right Guide for my project?
Micro-generator
A Micro-generator is defined in EREC G98 as “A source of electrical energy and all associated
interface equipment able to be connected to an electric circuit in a Low Voltage electrical
installation and designed to operate in parallel with a public Low Voltage Distribution Network
with nominal currents up to and including 16A per phase. For the avoidance of doubt this
includes electricity storage devices”. 16 A per phase corresponds to 3.68 kW on a single-phase
supply and 11.04 kW on a three-phase supply, and refers to the aggregate Micro-generator
capacity installed in a single premises.
Page 5
Distributed Generation Connection Guide:
Is this the right Guide for my project?
Inverters
An inverter is an electrical device that converts Direct Current (DC) to Alternating Current (AC).
This is required when you want to connect a generating unit with a DC output (eg. a
Photovoltaic array) to the distribution network, which operates at AC.
The term Micro Inverter is used to describe small scale inverters which are connected to
(multiple) small generating units, such as individual PV panels. This is often done so that if one
panel is impaired for any reason, then the output of the others is not affected.
EREC G98 and G99 annexes contain methodologies for testing equipment against a set of
test conditions to demonstrate compliance. The manufacturer produces a Type Test or
Compliance Verification Report to demonstrate compliance. Where the whole Micro-
generator or Power Generating Module is type tested (rather than just a part), it is Fully
Type Tested. All Micro-generators connecting under EREC G98 must be Fully Type Tested.
The Fully Type Tested concept also applies in EREC G99.
The ENA hosts an online Type Test Verification Report Register. This register is provided to
allow anyone access to the Type Test Verification reports for products relating to electricity
generation connecting to the DNO networks in the UK. The site also enables product
identification and information sharing. You can access the register at: https://www.ena-
eng.org/gen-ttr/
The product manufacturer is responsible for uploading and maintaining data and
documentation relating to their products. The ENA is carrying out a review of the data that is
submitted and raising any queries with manufacturers. Further information about the review
can be found at:
https://www.energynetworks.org/electricity/engineering/distributed-generation/
requirements-for-generators/ttr-review.html
It should be noted that it is the owners of generation equipment who are responsible for
procuring and installing compliant equipment.
Page 6
Distributed Generation Connection Guide:
Is this the right Guide for my project?
Equipment Certification
Potential Equipment Certificate providers and manufacturers are investigating formal
equipment certification and the ENA are supporting as appropriate.
Emerging Technology
EREC G98 and G99 have a relaxed set of requirements for generation that is classified as an
Emerging Technology. This is because the Requirements for Generators (RfG) allows for
this. The Emerging Technology status only applies to Type A generation, which has a
generating capacity of 0.8 kW to 1 MW and is connected at less than 110 kV (in practice in
Great Britain that is 66 kV or below). The Emerging Technologies are:
• ‘Baxi Ecogen’ generators (the specific products are the Baxi Ecogen 24/1.0, Baxi
Ecogen 24/1.0 LPG and Baxi Ecogen System)
• KD Navien stirling engine m-CHP (Hybrigen SE) (the specific products are the ‘NCM-
1130HH – 1 KWel’ and the ‘NCM-2030HH – 2 kWel’)
• Pellematic Smart_e
• Dachs Stirling SE Erdgas and Dachs Stilring SE Flussiggas
RfG Types A to D
The European Requirements for Generators (RfG) Code has introduced the classification of
Power Generating Modules by Types. There are four types, A to D, and they relate to the
registered capacity and connection voltage of the Power Generating Module. In Great Britain,
the Types are:
Type A: From 0.8 kW to < 1 MW and connected at < 110 kV
Type B: From 1 MW to < 10 MW and connected at < 110 kV
Type C: From 10 MW to < 50 MW and connected at < 110 kV
Type D: ≥ 50 MW or connected at ≥ 110 kV
Note that in different European countries, the capacity and voltage thresholds may differ.
The technical requirements in RfG are less onerous on the smaller Power Generating
Modules, and increase cumulatively for the larger Power Generating Modules, ie a Type B
Power Generating Module must meet the requirements for Type A and Type B. Some
requirements are common across all European countries. However, some requirements have
country-specific parameters, which have been set by national network operators. That means
that some of the parameters in Great Britain are different in Northern Ireland, and other
European countries.
Page 7
Recent Changes to Regulations
Requirements for Generators Drivers for the Requirements for Generators
The European Third Energy Package was The EU Network Codes aim to harmonise
adopted in July 2009, and has been law since technical and market rules to help to minimise
March 2011. The Third Energy Package refers barriers to energy trading. They also aim to
to a suite of legislation for both Electricity and prevent wide-scale technical events, and to
Gas. It has three key objectives: help to recover the system if there is such an
1. Enhancing sustainability and helping the event in the future. There has been a huge
European Union meet its increase in the amount of generation
decarbonisation obligations; connected to distribution networks – in Great
2. Ensuring security of supply in light of a Britain and across Europe. It has been
changing generation mix; and recognised that Distributed Generation can
3. Creating a single European Market for and needs to do more to provide support to
Electricity. the power system, so that generation
The Third Energy Package requires the supports system frequency, remains
development of European Network Codes. connected if possible and rides through faults
The Network Codes cover three areas: grid – rather than tripping off, and potentially
connection codes; market codes and system exacerbating any problems.
operation codes. One of the Codes is called The Requirements for Generators contains
Requirements for Generators (RfG). This sets technical requirements, which have been
out requirements which new generators will incorporated into EREC G98 and G99, so that
need to meet. generating units can provide such system
The RfG, which became a binding EU support. For example, there are requirements
regulation in May 2016, is available on the for:
EUR-Lex website. • All Type B, C and D Power Generating
A joint Distribution Code Review Panel (DCRP) Modules to stay connected to the
and Grid Code Review Panel (GCRP) distribution network when there is a
workgroup was charged with implementing fault on the transmission system;
the Requirements for Generators in GB. This • Type B, C and D inverter connected
included setting parameters that the RfG Power Generating Modules (eg solar PV,
leaves to national interpretation. The battery storage, wind turbines) to
workgroup proposed changes to the Grid provide support in the event of a
Code, Distribution Code and supporting network fault, using a technique called
Engineering Recommendations. The revised Fast Fault Current Injection (the design
documents were consulted upon with of synchronous machines means they
stakeholders by the GCRP and the DCRP. inherently provide support during
This work resulted in the publication of faults);
Engineering Recommendations G98 and G99, • All Power Generating Modules to
as well as revisions to the Distribution Code provide support in the event of a high
and Grid Code. These new EREC documents frequency event (Limited Frequency
apply to generation that is connecting to the Sensitive Mode – Over frequency); and
distribution network. The old EREC G83 and
EREC G59 should no longer be used after the • Type C and D Power Generating
27th April 2019. Modules to provide support for low
frequency events (Limited Frequency
Sensitive Mode – Underfrequency).
Page 8
Recent Changes to Regulations
These requirements have been introduced so
that generation of all sizes can help to provide
system support.
The new rules applies to all generation, not
just Distributed Generation.
Page 9
Key Terms for EREC G98 and G99
In the process of drafting EREC G98 and G99, the opportunity was taken to align with European
terms used (eg from the Requirements for Generators document) and to consolidate terms
previously used in GB documents. This means some new terms have been introduced, which are
used widely in the documents. The key terms are summarised on this page, and some are
explained further in break out boxes throughout the document or in the main text. Terms that
are particularly relevant for EREC G98 are indicated with a *.
Fully Type Tested* The whole Micro-generator / Power Generating Module is type tested,
rather than just part of the Micro-generator / Power Generating Module.
Micro-generating Plant* An electrical installation with one or more Micro-generators with nominal
currents in sum not exceeding 16 A per phase.
Power Generating Module Either a Synchronous Power Generating Module (SPGM) or a Power Park
(PGM) Module (PPM) - see below.
Synchronous Power An indivisible set of Generating Units—ie one or more units which cannot
Generating Module (SPGM) operate independently of each other—which generate electrical energy in
synchronism.
Power Park Module (PPM) Generating Units that are connected to the network either through power
electronics (eg solar PV or electricity storage devices connected through an
inverter) or asynchronously (eg some wind turbines are induction or
asynchronous generation). They have a single Connection Point to the
distribution network.
Power Generating Facility One or more Power Generating Modules connected to at one or more
(PGF) Connection Points. This is a Power Station in EREC G59.
Registered Capacity The normal full load capacity of a Power Generating Module less the MW
consumed when producing the same (ie auxiliary load). For Power
Generating Modules connected via an Inverter, the Inverter rating is the
Power Generating Module’s rating.
Page 10
A: A Guide to the UK Power Sector
In this section:
• An overview of the commercial structure of the power sector
• An introduction to the UK power sector and how it is changing
• A discussion about the various types of organisations that you may
come across while developing your Distributed Generation project
• A discussion on Network Innovation projects
• Guidance on where to find more information
Tip: Read the information boxes for definitions or explanations of terms that
may be new or unfamiliar.
Introduction
Understanding a little about the UK power There are many organisations involved in the
sector may be useful when discussing your UK power sector, which are introduced in this
Distributed Generation project. This section section.
aims to give some background explanation Apart from the physical structure of the power
about the UK power sector and how it is sector, there is also a commercial structure,
changing to meet the challenges of protecting which is discussed in this section.
the environment and changing Government
policy.
Transmission System
Transports electricity over long distances
across the country.
Electricity is transported at a high voltage
to reduce losses.
Systems
‘Grid Supply These arrows show the normal
Point’ direction of the flow of
electricity through the system.
Loads
Page 12
The Physical Infrastructure of the Power Sector
Changing electricity system Distributed Generation can result in electricity
In addition to the large power stations flows in both directions; from the distribution
connected to the transmission system, an network to customers, and from customers
increasing number of small power stations are with Distributed Generation back into the
being developed, often connected to distribution network. The system is no longer
distribution networks. Generation connected a “waterfall” system, with electricity flowing
to the distribution network is called from the large power stations in one direction
Distributed Generation. The diagram below towards customers. Instead, electricity flows
illustrates this changing electricity system. are more unpredictable.
Power Stations
A mix of energy sources, including
renewable and conventional sources.
Other
Distribution
Transmission System
Systems The direction of electricity
flow becomes more dynamic
and often less predictable
with the increase of
Distributed Generation. This
will require more active
Distribution System control of the networks.
Page 14
Key Organisations
If you are connecting your Distributed Electricity supply is a competitive market so
Generation to an IDNO’s network, the process you can choose and change your electricity
is almost identical to that if you are supplier.
connecting to a DNO. There are a few Aggregators
exceptions to this, which are discussed in Aggregators specialise in co-ordinating
Section C of this Guide. demand and generation (including storage) to
Transmission Owner (TO) provide demand response and other market
A TO owns and maintains the high voltage services. The Network Operators and
transmission system, known as the National Suppliers may buy demand response and
Electricity Transmission System, referred to in other grid balancing services from
this Guide as the transmission system. aggregators.
Transmission Owners are responsible for
making sure that transmission services are Energy Service Company (ESCO)
available to the System Operator (see A Government paper defines ESCOs as “a
explanation later in this section). The company that provides a customer with
Transmission Owners are as follows: energy solutions” rather than simply being an
electricity or gas supplier. ESCOs can enter
• National Grid Electricity Transmission
into long-term contracts to provide
(NGET) in England and Wales
information, installation, finance, operation
• SP Energy Networks (SP Transmission
and maintenance. There are various models
plc) in southern Scotland
the ESCO can take. ESCOs can work on a
• Scottish and Southern Electricity
performance contract, where they guarantee
Networks (Scottish Hydro Electric
energy savings and make charges based on
Transmission plc) in northern Scotland
the extent to which these savings are
(Scottish Hydro Electric Transmission
achieved. This model is typically used by
Ltd, or SHETL)
commercial and industrial customers. ESCOs
can also work for communities, servicing a
Private Networks
group of customers in the same local area.
Private networks are extensions of the existing
DNO network which are not owned by the ESCOs may develop into a household model,
DNO itself. The owners of private networks to provide energy efficiency savings and small
are distinct from an DNO because they do not scale generation for home owners, rather
need to be licenced and are unregulated. than just supplying electricity.
For example, private networks can be owned Generators
by hospitals, airports, industrial sites, etc. This Generators own, operate and maintain Power
Guide is not intended to address connections Generating Facilities which generate
to private networks. If you are connected to a electricity from various energy sources, eg.
private network, you should discuss your plans coal, gas, hydro and nuclear. Newer
with the network owner as soon as possible. generation technologies include wind, solar,
tidal and wave. See the end of this section for
Suppliers
links to more information on generating
Supply is the retail of electricity. Suppliers buy
technologies.
electricity in bulk from generators, and then
sell to consumers. They are responsible for
providing bills and customer services, and
arranging metering and meter reading.
Page 15
Key Organisations
To identify your DNO or IDNO:
If you already have a meter at your site, find the Example MPAN, with first two digits indicated
first two digits of your MPAN (Meter Point
Administration Number), which is shown on your
electricity bill, and may be shown on your meter.
This corresponds to your DNO or IDNO, see table
below.
If you do not have a meter at your site, you can contact the DNO whose geographic area you believe you
are in and they will be able to confirm. See the map on page 14.
First 2 MPAN
Service Area Distribution Business
digits
10 Eastern England UK Power Networks– Eastern England
11 East Midlands Western Power Distribution (WPD) – East Midlands
12 London UK Power Networks (UKPN) – London Power Networks (LPN)
Page 16
Key Organisations
System Operator (SO) activities in the power sector:
Electricity cannot be stored at a large scale − Generation
and so demand has to be balanced with − Transmission (and
generation on a second by second basis by the interconnection, a transmission
System Operator. The SO makes requests of link with another country)
generators to increase or decrease output − Distribution
from their units, or may ask some large − Supply
customers to control their demand. NGESO is Generation licence requirements for
the System Operator in Great Britain. Distributed Generation are discussed in
Following a government consultation on Section D. The Connection Application:
greater separation between the System Generation Licensing.
Operator role performed by National Grid and
the rest of the National Grid group, National European organisations
Grid has established a new, legally separate The regulatory arrangements that apply
company to carry out the Electricity System across continental Europe are implemented
Operator function within the National Grid by National Regulator Authorities (NRA) in
Group, which is called the National Grid each member state of the European Union;
Electricity System Operator (NGESO). This Ofgem is the National Regulatory Authority
separation took place on 1st April 2019. for Great Britain. The regulations are required
Balancing Settlement Code company to comply with policy criteria determined by
the European Parliament and implemented
Elexon is the company that manages the through European Directives and Regulations.
balancing and settlement of electricity trading. To assist with this process in relation to
They do this by identifying where generators electricity networks, a number of bodies have
have not generated the amount of electricity
been set up that represent regulators and
they are contracted to produce, and suppliers’ transmission system operators. National
customers have not consumed the amount of Energy Regulators work with the Agency for
electricity that was expected. Out of balance the Cooperation of Energy Regulators (ACER)
parties are charged based on the additional and the Council of European Energy
cost to balance supply and demand (often by Regulators (CEER) on policy developments in
buying or selling electricity at short notice). different areas of electricity market
The Balancing and Settlement Code (BSC) liberalisation.
governs the operation of this balancing ENTSO-E, the European Network of
mechanism. Transmission System Operators for Electricity,
Regulator is a membership body for Transmission
System Operators (TSO). ENTSO-E promotes
The Office of Gas and Electricity Markets
cooperation across Europe’s TSOs. One of
(Ofgem) is responsible for:
ENTSO-E’s roles is drafting the European
• regulating prices and performance in the Network Codes, which includes the
monopoly elements of the electricity Requirements for Generators (RfG).
supply industry;
The UK’s membership in these agencies post-
• resolving disputes between different
Brexit will be subject to negotiations.
parties when necessary; and
• granting licences for the following
Page 17
Network Innovation and Industry Developments
Innovation Funding innovation strategy. The Electricity Network
New challenges and applications in energy Innovation Strategy sets out a jointly agreed
networks have motivated many projects that roadmap which demonstrates how innovation
aim to develop innovative tools and products can accommodate future whole-system
to improve the way networks operate and requirements and lead to benefits. The
customers are connected. document was first published on 29th March
Ofgem has a number of mechanisms that the 2018 and will be reviewed every 2 years at a
DNOs and other organisations can use to fund minimum. Further information is available on
electricity network innovation. The two main the ENA website.
mechanisms for network companies are called Transmission and Distribution Interfaces
the Network Innovation Allowance (NIA) and
Network Innovation Competition (NIC), which There has been a significant increase in the
apply to both electricity and gas distribution amount of connected Distributed Generation
and transmission. in the last few years. This has meant that the
DNOs, TOs and the SO have to change the way
• NIA is an allowance each network they work together, to maintain an economic
company receives to fund smaller scale and secure network. In order to address these
innovation projects which have the challenges, the Transmission Distribution
potential to deliver benefits to network Interface (TDI) Steering Group was established
customers. by ENA and its members. Network companies
• NIC is an annual competition, where recognise the need for distribution and
network companies compete for funding transmission companies to work together
for development and demonstration of more closely in order to consider how they can
network innovations such as new tackle the whole system impact of Distributed
technologies or novel operating and Generation and other technologies such as
commercial arrangements. storage.
Learning from these projects is shared In January 2017 the Open Networks Project
amongst all DNOs and TOs for the benefit of was launched by the ENA. The aim of the Open
the power sector as a whole. Incorporation of Networks Project is to transform the way
the learning into business as usual practices is electricity networks operate and provide the
laid out in the business plans of the individual first step towards creating a smart grid.
network companies. One of the areas that is under review is the
For more information, and details about management of Connection Offers for
individual projects, refer to the Smarter customers who are waiting to connect to the
Networks Portal, hosted by the Energy network, which involves improving the existing
Networks Association: interactivity and queue management policy.
Interactivity occurs at the application stage of
http://www.smarternetworks.org/ connection offers when two or more
Electricity Network Innovation Strategy applicants apply for the same connection. The
new proposals by the ENA allow network
Following a review of the NIA and NIC, Ofgem
companies to inform applicants that there is
proposed a number of changes to the
the possibility of connecting to their network,
innovation funding schemes. One of these was but is conditional on the project in front
the requirement on network companies to rejecting its offer. The ENA is also proposing
collaboratively produce an industry wide
Page 18
Network Innovation and Industry Development
that if the customer in front accepts the offer, New technologies
the network company is able to take that Active Network Management (ANM) schemes,
connection into account and provides a which have been trialled in innovation
revised offer with a new connection date. projects, are now being included as part of
Queue management allows network Business As Usual Connection Offers. ANM
companies to manage contracted connections uses control systems to manage Distributed
against the available capacity at the time by Generation in constrained areas. Note that
moving projects down the connection queue if ANM connections may only be available in
they have not met their agreed milestones by selected parts of the network.
a certain date. Similarly, projects can be
moved up the queue when capacity becomes Export limiting devices are also coming into
available and they have met their agreed use. These devices allow a limit to be set
milestones. above which the generation will not export.
This may allow generation to have a
The proposals formed the basis of a constrained connection, to reduce the need
consultation which closed on the 25th
for reinforcement. If you want to explore the
September 2020. The DNOs are currently use of these devices, seek guidance from your
planning implementation dates to take DNO. ENA has published Engineering
account of the proposals outlined by the ENA. Recommendation (EREC) G100, which
A full review of the work done so far in 2020 provides technical guidance on the connection
can be found on the ENA’s website below: of Customer Export Limiting Schemes that
operate in parallel with the distribution
https://www.energynetworks.org/electricity/
systems of licensed DNOs. This is available on:
futures/open-networks-project/workstream-
products-2020/ws2-customer-information- http://www.energynetworks.org/electricity/
provision-and-connections.html engineering/distributed-generation/
engineering-recommendation-g100.html
For 2020 the main areas of focus are on:
Energy storage is becoming increasingly
• Flexibility Services
prevalent in distribution networks. For more
• Whole Energy Systems information on network connected storage
• Customer connections (eg. batteries), refer to Chapter C: Getting
Connected—Energy Storage.
• DSO transition
The work is continuing in 2021.
Page 19
Where to Find More Information
There are some very good guides to the UK power sector available in the public domain. In
particular, if you want to read more on this subject, you may wish to read the following:
• A Guide: Sale of Power Opportunities for Distributed Generators; DTI (Department for
Trade and Industry);
• Guidance Note – The Electricity Trading Arrangements: A beginner’s guide; Elexon
www.elexon.co.uk/knowledgebase/about-the-bsc/
A good source of information on the organisations we have introduced are their own websites:
• Energy Networks Association —the industry body for UK energy transmission and
distribution licence holders and operators: www.energynetworks.org
• A list of IDNOs can be found on the Ofgem website:
www.ofgem.gov.uk/Networks/ElecDist/Policy/IDNOs/Pages/IDNOs.aspx
• Ofgem—The Regulator: www.ofgem.gov.uk
• National Grid —The Great Britain Electricity System Operator, and Transmission Owner in
England and Wales: www.nationalgrid.com/uk/Electricity/
• Elexon—The Balancing and Settlement Code Company: www.elexon.co.uk
For more information on ESCOs, the following document is a useful reference:
• Making ESCOs Work: Guidance and Advice on Setting Up and Delivering an ESCO; London
Energy Partnership, which is on the London Energy Partnership website: www.lep.org.uk
The following website gives more information on generation technologies:
• Energy Saving Trust: www.energysavingtrust.org.uk/Generate-your-own-energy
The GB Distribution Code, Annex 1 and Annex 2 documents and the associated GB Distribution
Code User Guide can be found in the link below:
• DCode: http://www.dcode.org.uk/
The GB Grid Code and the associated Guide can be found in the link below:
• GCode: www.nationalgrideso.com
Information about licence exceptions and private networks can be found:
• UK legislation: http://www.legislation.gov.uk/uksi/2001/3270/contents/made
Page 20
B: The Role of Distributed Generation
In this section:
• An introduction to the role of Distributed Generation
• A discussion on the drivers for Distributed Generation
• Some of the benefits and impacts of Distributed Generation
• References to some documents where you can find out more on these
issues
Introduction
As explained in Section A of this Guide, the • Technological innovation.
electricity industry is undergoing changes with
increasing amounts of Distributed Generation In this section, these drivers are discussed in
being connected to the system. There are a more detail. We will also introduce some of
number of drivers behind this: the benefits and challenges of Distributed
Generation.
• Environmental issues;
• New Government Policy; We refer to some useful documents and
• Security of supply; and reports for further reading on this topic.
Page 22
Benefits of Distributed Generation
(CHP). These can be sold to the supplier carbon support (eg. Feed-in Tariffs,
along with the energy generated. Renewables Obligation) and does not
Companies can use LECs to avoid paying have a long-term contract to provide
the Climate Change Levy tax. Short Term Operating Reserves (STOR)
to National Grid Electricity Transmission
• Embedded benefits of the generating
could be eligible to enter the Capacity
unit being connected to the distribution
Market, and receive payments for
rather than the transmission network,
delivering energy at times of system
eg. charge avoidance of Transmission
stress.
Network Use of System charges and
Balancing Services Use of System • EU Emissions Trading System (ETS) -
charges. Embedded benefits are applies to approximately 10,000 energy
changing, see chapter E. intensive users in the UK such as metal
industry, paper factories and refineries.
• Generators whose equipment has a
These large energy users have been
capacity greater than 3 MW (and/or the
allocated green-house gas allowances
ability to deliver in excess of +/- 15
for their operations. At the end of each
MVAr of reactive power) can enter into
year, they must ensure they have
agreements with NGESO to provide
enough allowances to cover their
Ancillary Services, for which they will be
emissions: they can buy additional
paid.
allowances or sell any surplus
• Generation that is not receiving low allowances generated from reducing
Page 24
C. An Overview of Getting Connected
In this section:
• The main tasks in the process of connecting Type A Power Generating Modules under
EREC G99
• An explanation of the terms Power Park Modules and Synchronous Power Generating
Modules
• Guidance on adding new generation to an existing installation
• The provision of information and customer service standards
• A discussion on connecting to an IDNO network
• Guidance on where to find more information
Introduction
This Guide describes the process for
connecting Type A Power Generating Modules FIND AN INSTALLER
under EREC G99. Installers must be competent.
Page 26
Types of Power Generating Module
For example: A Power Generating Facility Another Power Generating Facility comprises
comprises three 400 kW Synchronous Power three 400 kW generating units (eg. wind
Generating Modules (SPGM). Although the turbines), which form a Power Park Module
capacity of the Power Generating Facility is 1.2 (PPM). The capacity of the Power Park Module
MW, the threshold for requirements is based is the total capacity of all of the generating
on the capacity of each Synchronous Power units, ie 1.2 MW. The Power Park Module
Generating Module. As each is 400 kW, each must meet the Type B requirements in EREC
SPGM must meet the Type A requirements in G99. There are further illustrations of
EREC G99. examples in Section 4 of EREC G99.
Page 29
Getting Connected—Main Tasks
There are different forms for Synchronous
Site Responsibility Schedule or Joint
Power Generating Modules and Power Park
Operational Agreement
Modules.
Some of these agreements will be in place
These forms are completed by the
before construction begins.
manufacturer of your Power Generating
Compliance Module. However, you (or your installer on
Power Generating Modules can: your behalf) should obtain these and submit
them to the DNO as part of the connection
• Be Fully Type Tested, or process.
• Comprise some Type Tested equipment, Installation and Commissioning
and/or use manufacturers’ information You should maintain close contact with the
(see break out box on page 37) to DNO throughout construction. This is so that
demonstrate compliance, and/or also you are aware of the timeline of any
require additional site testing. reinforcement works that they need to do,
Note that there may be a need to and you can plan your project with this in
demonstrate compliance with power quality mind.
standards even if other aspects are type Commissioning can only take place once the
tested. construction is complete. EREC G99 details the
If your Power Generating Module is: commissioning tests that you or your installer
needs to perform. For generating units
• Fully Type Tested, and covered by EREC G99, it is your obligation to
• registered with the Energy Networks undertake appropriate commissioning tests,
Association Type Test Verification which the DNO may choose to witness.
Report Register For a Fully Type Tested Power Generating
then your application should include the Module connected at LV, your DNO will not
Manufacturer’s reference number (the normally need to witness the commissioning
Product ID). In all other cases, you need to testing. However, your DNO may choose to
provide the DNO with a Compliance do so. If this is the case, they will state this in
Verification Report. The format of these their Connection Offer.
reports is given in Annex A.2 of EREC G99. If your commissioning tests are being
Page 30
Getting Connected—Main Tasks
witnessed by the DNO, you or your installer supplier to buy electricity that you export, it is
should discuss the scope of the testing with your responsibility to keep them informed of
the DNO from an early stage, and must submit the proposed commissioning programme. In
the scope, time and date of the testing at least particular they should know the date you
15 days before commissioning takes place. expect imports and exports across the
Informing the DNO connection to start.
You should notify the DNO at least 28 days Ongoing responsibilities
before commissioning the Power Generating Although the focus of this Guide is to inform
Module, and provide them with information you about the process of connecting your
on the installation and the full results of the generation to the distribution network, you
commissioning tests. This information is should be aware that once it is connected you
captured in two forms, both of which are have some responsibilities. This includes:
available in EREC G99 and on the ENA website:
• The Installation Document (Form A.3) • Keeping your generation equipment
• Site Compliance and Commissioning Test maintained by someone who is
Form (Form A.2-4), where required, eg. competent to do so;
if the interface protection is not Type • Performing periodic tests that are
Tested and needs to be tested onsite. required by the DNO. They will discuss
these with you;
If your commissioning is being witnessed by
• Informing the DNO if there are changes
the DNO, then these forms can be filled out
to the installation that affect the
and handed to the DNO representative
generating characteristics;
witnessing.
• Complying with Health and Safety
The forms include a declaration that the requirements;
installer must sign. This states that the • Inform the DNO if something happens
installation complies with EREC G99. that affects the compliance of your
Note: DNOs may have their own versions of Power Generating Module with EREC
these forms on their websites—a web search G99; and
• When you are decommissioning your
should help you locate the forms you need, or
generating unit(s), you need to send the
try contacting your DNO.
DNO certain information. This is detailed
Put commercial arrangements in place in EREC G99 Annex D.1.
If you have made arrangements with a Annex D.3 in EREC G99 is called “Main
Statutory and other Obligations” and
summarises the main obligations on
generators.
EREC G99 was introduced in May 2018. It is based on EREC G59, which was revised to take
account of a European Network Code called Requirement for Generators. Generation connecting
to the distribution network must connect under EREC G98 or G99.
Page 31
Getting Connected—Main Tasks
Changes to your Power Generating Module If you have an installation that was connected
under EREC G59 and you replace a major
If you need to replace a component of your
component you should notify the DNO if the
Power Generating Module, or its protection
change alters the operating characteristics of
system or interface protection, you must
the generating unit. If you replace all or part
notify the DNO before making changes. You
of the interface protection you should notify
and the DNO will need to reach agreement on
the DNO as they will need confirmation that
the significance of the change. If it is
the new protection complies with EREC G59
considered a small change, you will only need
and may want to witness the commissioning
to confirm the compliance of the affected
of the new protection.
component with EREC G99.
However, if it is a significant change (eg you If you replace a generating unit or Power
Generating Module that has been installed
increase the capacity of your Power
under EREC G59 you will need to discuss with
Generating Module), you will need to agree
the DNO whether the new equipment needs
with the DNO the approach to be taken with
to comply with EREC G59 or be upgraded to
the replacement equipment and in many
be fully compliant with EREC G99.
cases submit a new Standard Application Form
for the new equipment. For the addition of new Power Generating
Modules, see page 27.
Note: As of summer 2020, the EU is planning to remove the exclusions for storage in the
European Requirements for Generators (RfG) Code. This means that the technical requirements
that currently do not apply to storage connections in the RfG Code, would apply. The UK DNOs
are likely to take the same approach as the EU, which means that:
• EREC G98 / G99 would apply in full to storage connections and
• The capacity of storage devices would count towards RfG Type classification (Types A – D)
In aligning with the EU RfG Code changes, distribution requirements in the UK would also align
with recent changes in Grid Code requirements for transmission connected storage. In May 2020
Ofgem approved National Grid’s modification to the Grid Code (GC0096), which sought to
provide clarification on storage requirements in response to increasing interest and applications
for storage connections. The changes clarify requirements for storage, which recognise different
operating characteristics and capabilities of a wide range of storage devices, and are consistent
with existing industry codes.
Page 32
Customer Service and Provision of Information
There are a number of drivers for DNOs to Distributed Energy Resources (DER) Forum
provide a good level of service to customers. The DER Forums, hosted by the ENA on behalf
Price Control Proposals (RIIO-ED1) of DNOs, are events that are used to explore
Ofgem administers a price control regime issues and concerns around Distributed
which allows DNOs to earn a fair rate of Generation connections, including barriers to
return while limiting costs passed on to Distributed Generation and process issues.
customers. The current price control period They are open to anyone, and are attended by
is called RIIO-ED1, which runs until 2023. DNOs and developers. Details can be found on
The RIIO-ED1 proposals include a number of the ENA Events website.
mechanisms to incentivise DNOs to provide a Improvements made to DNO Services
good service to Distributed Generation
In recent years, there have been a number of
customers, including:
improvements to DNO services as a response
• A Time to Connect Incentive for minor
to these drivers and feedback, including:
connections customers (less than 70kW
and connected at LV); • Increased internal resources;
• An Incentive on Connections • Improved provision of information,
Engagement (ICE) - to encourage DNOs including more detailed breakdown of
to engage with and respond to the costs, web portals, decision support
needs of major connections customers tools/application hotline, and capacity
(which includes generation customers), “heat maps”, indicating areas that can
and includes a requirement on DNOs to more readily facilitate connections;
set out plans on what improvements • Holding stakeholder and customer
they plan to make in the next events; and
regulatory year, consisting of;
• Part 1: Plans for improvements • Exploring the possibility for discussions
for the forthcoming year; and prior to formal application (“connection
• Part 2: Reviews the progress in optioneering”). This process is being
the previous year. carried out in different ways by different
DNOs. Refer to your DNO for more
ICE workplans can be found on information.
individuals DNO websites
DNOs have promised to bring about continued
• The Broad Measure of Customer improvements, including:
Satisfaction (BMCS) surveys.
• Shortening connection timescales;
As part of the Incentive on Connections
Engagement (ICE), DNOs publish annual ICE • Enhancing the publicly available network
plans for stakeholder engagement. capacity information, eg. contracted
capacity reports;
Guaranteed Standards of Performance
• Publishing case studies; and
The guaranteed standards of Performance
are set out in Standard Licence Condition • Enhancing the connection application
15A. They include, for example, maximum and the wayleaves/consents processes.
timescales in which DNOs must provide you DNOs publish Distributed Generation 'Work
with a quotation (Connection Offer). Ofgem Plans' that outline progress against
has guidance documents about these improvement initiatives. Check your DNO’s
Standards on their website. Distributed Generation web pages.
Page 33
Getting Connected — Energy Storage
Storage devices for electrical energy are planning to use storage in conjunction with PV
becoming more prevalent, and can be used as (or other technologies) to offset consumption,
part of Distributed Generation schemes to the total connected generation is likely to be
allow generated electricity to be stored within above 16A / phase and EREC G99 applies.
the premises rather than exported to the However, DNOs have implemented a fast track
distribution network. application process, for domestic scale
storage. This involves submitting the G99 Form
DNOs treat storage as demand when its A1-2 : Application for connection of Fully Type
importing from the distribution network and Tested Integrated Micro Generation and
generation when its exporting to the Storage installations and reduces the
distribution network, and need to be aware of connection time from 45 days to 10 days or
storage because of the potential impact on less. If the storage is intended to be operated
their networks. Therefore, storage devices in island mode (during a power outage) the
need to meet the relevant connection fast track process is not applicable and the
requirements (EREC G98 or G99). If you are standard EREC G99 process applies.
Page 34
Getting Connected — IDNO’s Networks
The process for connecting your Distributed host network, which could be a DNO or
Generation to an IDNO’s network follows IDNO. If your generation project would
EREC G99, and is therefore similar to cause certain network parameters to
connecting to a DNO’s network. IDNOs are exceed defined limits, such as voltage or
licensed entities and are bound by some of export to the host network, the IDNO and
the same licence conditions as DNOs, host network will explore options for
including certain performance standards such accommodating your project. This
as timescales for responding to requests for discussion will take place between the
quotes. The majority of what is included in IDNO and the host network, and will not
this guide applies to both DNO and IDNO involve you directly. However, the IDNO
connections. may then discuss different options with
you for the most appropriate generation
However, there are a few key differences for a
project to be connected.
Distributed Generation connection to an IDNO
• Formal Agreements: IDNOs will not
network:
necessarily insist on the same set of
• Provision of Information: IDNOs have a
formal agreements that the DNOs will.
reduced set of licence conditions
Agreements such as the connection and
compared with DNOs, and they are not
adoption agreements may not be
obliged to provide the same documents
required.
for customers. IDNOs are not required to
To determine whether you are connected to a
produce Long Term Development
DNO or IDNO network, refer to the guidance
Statements nor Connection Charging
methodologies and statements. on page 16.
• Interaction between the IDNO and the
Host Network: When an IDNO receives an
application for connection for Distributed
Generation, they design and build the
network infrastructure and connect to the
Page 35
Where to Find More Information
Other useful documents and links
• Independent Connections Providers (ICPs): see the Lloyds Register website information on
the National Electricity Registration Scheme (NERS)
• Metering Codes of Practice
• The IET Wiring Regulations (British Standard 7671) are available to buy on the IET website
• Ofgem’s information about how to get an electricity connection for a new building or site
Page 36
Where to Find More Information
Health and Safety considerations
Safety is very important in the design of generation connections. Some of the safety
requirements for Distributed Generation connections are set out in EREC G99. This document
references the Regulation that informs these requirements, the Electricity Safety, Quality and
Continuity Regulations (ESQCR) 2002, and also lists the relevant British Standards.
You can find out more about Health and Safety aspects of Distributed Generation connections
on the following websites:
• The Electrical Safety Council (ESC): www.esc.org.uk
• The Energy Networks Association—Safety, health and environment:
www.energynetworks.org/electricity/she/overview.html
Supply Issues
Your DNO is obligated to maintain the power quality on their network within a set of defined
limits. These include maintaining voltage at the required levels. This is so that customer
equipment is not damaged. If you have a voltage complaint you should contact your DNO.
Your DNO should respond to your complaint within 5 working days, or visit within 7 working
days. If work is required to correct the issue, the DNO should complete this within 6 months.
Manufacturers’ Information
Manufacturers’ information is a term used in EREC G99. Along with Type Testing and onsite
tests, it is another way of demonstrating compliance of a Power Generating Module with EREC
G99 by providing information. The information is supplied by the manufacturer to the
customer, who should send it to the DNO. The suitability of the information is agreed between
the generator and the DNO.
Once the DNO is satisfied that the manufacturers’ information they have received accurately
represents the performance of the generating unit, it may be assigned a reference ID. If your
generating unit already has manufacturers’ information available and a reference ID, you can
use this reference ID in your compliance forms.
Page 37
D. The Connection Application:
Connection Application Process
In this section :
• How to apply to your DNO to install Power Generating Modules
• Details of the connection offer that the DNO will produce for your connection
• How to notify the DNO that your Power Generating Modules have been installed and
commissioned in accordance with EREC G99
Introduction
This section of the Guide describes the installation, please refer to the section at the
application process for the connection of your beginning of this guide entitled “Distributed
Power Generating Modules to the distribution Generation Connection Guide: Is this the right
network. This includes the application for Guide for my project?”.
connection form, and the connection offer There is more information on the connection
from the DNO. application process in the Guide for EREC G99
This section also explains the forms that your Type B – D Power Generating Modules,
installer will need to provide to the DNO, including:
including: • Wayleaves for new connections;
• compliance forms, and • Interactive connection applications; and
• notifications once the units are • The Statement of Works process and
commissioned. recent developments in this area.
This section is written for installations where These are unlikely to be relevant for
the Power Generation Module to be installed connecting Type A Power Generating
is categorised as being Type A in EREC G99, Modules, but if these do impact your project,
and where the output is greater than 16A per refer to the EREC G99 Types B to D Guide for
phase. If this does not apply to your more detailed information on these topics.
Page 38
The Standard Application From
The standard application form contains a network.
comprehensive list of data requirements to The standard application form is used as an
assist the DNO with carrying out system iterative document, developed as the
studies to assess your connection. You should connection and commission process develops.
do your best to provide as much of this It is used to record information about your
information as possible as part of your generating units that needs to be provided to
connection application to ensure your quote is the DNO before commissioning, to comply
as accurate as it can be. If you have difficulty with the requirements set out in the
with filling out this form, you can discuss this Distribution Code DDRC.
with your DNO or an adviser such as an When the application has been submitted to
engineering consultant to assist you. the DNO, they will assess the impact of the
You or your installer should submit the generation on their network. Where
application form to the DNO before any necessary, they will carry out design work, eg.
generation equipment is installed, as the DNO for network reinforcement. This will be
needs to assess the possible impact of your detailed in your Connection Offer.
generating equipment on the distribution
The offer will also contain details of the costs It is possible that there will be other
for the DNO to undertake any work. Further Distributed Generation in development in the
information about these costs is given in same area of the network. If this is the case,
Section E: Costs and Charges. your application may affect, or be affected by,
another connection application. In this case
Page 39
The Connection Offer
all the relevant applications are referred to as Interactive connection applications are
“interactive”. The DNO will tell you in writing considered on the basis of ‘first come first
if your connection application is interactive served’. The DNO uses the date and time that
with one or more others. The Connection your Connection Application was made to put
Offer will also specify that it is interactive with your Connection Offer in priority order
other applications. compared to other applicants. For more
information on interactive applications, see
the EREC G99 Types B to D Guide.
Connection Conditions
The DNO may include certain conditions or If NGESO is involved in your project (eg. if your
restrictions in order for the connection to be DNO has requested a Statement of Works for
put in place. Your Connection Offer will any transmission system works required), then
include details of these, and if you need to they can impose conditions on your
know more information then you can discuss connection. Your DNO must ensure that
this with your DNO. You will have to agree to NGESO conditions are met before they allow
these conditions in order to accept the connection.
Connection Offer. Reactive Power Import / Export
Flexible Connection Offers The apparent power at any point on the
The DNO will decide if a connection is viable network is the product of the voltage and
by considering the worst case scenario for the current at that point. The apparent power is
network. If the connection of your generation made up of two components, the real power
would cause equipment ratings or statutory and the reactive power. It is likely that real
limits to be exceeded, then the DNO would power is the electrical power you are more
not allow the connection without addressing familiar with. It is measured in Watts (W), and
the issues identified. The DNO may decide is the useful power that we import into our
that the best thing to do is to reinforce the houses to run our electrical goods. However,
existing network so that it can cope with new there also needs to be a balance of reactive
power flows. However, this could be power on the network. It is the DNO’s
prohibitively expensive for your project. responsibility to ensure that the distribution
network can cater for both real and reactive
In these cases, or where the customer has power. Your generating unit will be capable of
requested, the DNO may offer a connection controlling the amount of reactive power that
with certain restrictions, such as setting a it absorbs or produces. All PGMs need to
maximum level for export, or restricting comply with G99 reactive power capabilities.
generation export under certain network It may be possible to mitigate negative effects
conditions. This could involve entering into a that your generator might have on the
specific commercial arrangement. network (eg. rise in system voltage) by
Even with a standard Connection Agreement, controlling the amount of reactive power you
in rare operational scenarios it may be produce or absorb. This may allow you to
necessary for the DNO to curtail the operation connect a higher capacity generator. You can
of a generator in order to, for example, discuss this option with your DNO.
maintain safety or power quality.
Page 40
Compliance Forms
If your Power Generating Module is Fully Type This is done by submitting a Compliance
Tested and registered with the Energy Verification Report for each Power Generating
Networks Association (ENA) online Type Test Module. The format of this report is given in
Verification Report Register, it will have a Appendix A.2 of EREC G99. There are several
manufacturer’s reference number (or Product options (Forms A.2-1, A.2-2, A.2-3), depending
ID on the ENA website). This means that the on the size of your Power Generating Module,
Power Generating Module meets the and the type (synchronous, asynchronous,
requirements of EREC G99, and the inverter connected). These forms should be
manufacturer has submitted information to submitted prior to arranging commissioning.
the ENA that demonstrates this. You should In some cases (eg. where interface protection
include the reference number on your
is not Type Tested) you will need to
application form, and do not need to submit
demonstrate elements of compliance on site.
anything further to demonstrate compliance.
You can do this at the time of commissioning
Otherwise, your Power Generating Module (see below). In this case, there is a Form A.2-4
may comprise a mixture of type tested in EREC G99 called “Site Compliance and
components, components where the Commissioning test requirements for Type A
compliance is demonstrated using
Power Generating Modules”, which sets out
manufacturers’ information, and components
the format of recording the relevant test
that will need to be tested on site. In this case
you (or your installer) need to submit results. Where the DNO witnesses
information to indicate how you are intending commissioning, this can be submitted to the
to demonstrate compliance with EREC G99. DNO on the day. Otherwise, this should be
submitted to the DNO within 28 days.
Other Requirements
The declaration that your installer (or you) of these standards. If you appoint a
signs on the Installation Document requires competent installer (see Section C: An
them to confirm that they’ve installed your Overview of Getting Connected), they should
Power Generating Modules in accordance know about these standards and make sure
with EREC G99. It’s important that you use an that your installation meets with all the
installer who is familiar with the requirements relevant standards.
Page 42
E. Cost and Charges:
Overview of Charges
In this section:
• An introduction to connection costs
• The basis of DNO connection charges for infrastructure
• Other elements of connection charges and where to find indicative
costs and examples
• Generation Distribution Use of System charges and metering arrange-
ments
Tip: Read the boxes for definitions or explanations of terms that may be new or
unfamiliar.
Introduction
There are two categories of charges made by Charges for Connection to the electricity
the DNO: distribution system. All DNOs’ statements
follow the same format, and are available on
• Connection charge: this is a one-off
charge made by the DNO, which their websites. This document contains:
primarily covers the cost of work and • The DNO’s connection charging
equipment associated with connecting methodology (i.e. how they calculate
your generating project to the their charges);
distribution network. This includes a
• The DNO’s connection charging
portion of reinforcement costs.
statement (i.e. what the charges are);
• Use of System charges: these are
• An indication of the costs of providing a
ongoing charges, which primarily cover
connection quotation / budget estimate;
operation and maintenance costs and
and
include an element to cover the costs of
ongoing network development including • Other relevant information for
general reinforcement. connecting customers.
DNOs are obliged to publish documents The basis and elements of connection charges,
describing the basis of their connection as well as indicative costs and examples are
charges and their charging methodology. discussed in this section.
They also present the different elements of Use of System charges are levied by the DNO
connection charges, and indicative costs for on the supplier, so as a generator you will not
works and equipment of significant cost. This be charged these directly. However, this
will help you to understand the charges they section is included for your information, as
quote you. This information is contained in Use of System charges may appear as an item
the DNOs Statement of Methodology and on your bill.
Page 43
Connection Charges—Infrastructure
The connection provides an electrical path • It may be necessary to install switchgear
between your generation installation and the at a substation some distance from your
DNO’s network. Any work required to project site. This could be due to the
establish this connection will result in some increase in fault level caused by the
initial costs, which will be charged to you connection of your generator, or to
upfront as part of the connection charge. create a new protection zone.
The work required to provide this path can be • Equipment such as reactors or static VAR
broken down into two categories: compensators may be needed for times
when the voltage may rise, eg. when
1. New infrastructure (or extension) must
your generating equipment is exporting
be installed to provide an extension of
the existing network. This is from the at times of light demand.
point of connection on the existing The asset costs that are included in the
network up to the new point of supply. connection charge include:
2. Some reinforcement of the existing • Any extension to the network
network infrastructure may be required • A portion of reinforcement costs
to accommodate your planned
generation capacity. DNOs are obliged to publish a document
describing the basis of their connection
These are illustrated in the figure below and charges and their charging methodology. You
the point of connection is defined in the can refer to this document to see what
Glossary. portion of reinforcement costs you will be
Reinforcement work is usually required to charged for. These are available on DNO
increase the electrical capacity of those parts websites.
of the network which form part of the In some cases, Distributed Generation may
electrical path from the generating equipment have an effect on the transmission network. In
to the network. However, some this case your DNO may need to request a
reinforcement work does not fit this
Statement of Works from NGESO. Refer to the
description, for example: G99 Types B—D Guide for more information.
Before: After:
Distribution Distribution
Network Point of Network
connection
Point of Loads
Loads supply
Existing network
Distributed
Extension (new infrastructure) Generation
Reinforcement
Page 44
Connection Charges—Other Elements
Elements of charges The connection charging methodology is
governed by the Distribution Connection and
As well as charges for the reinforcement,
Use of System Agreement (DCUSA) and is
there are other elements that are covered in
subject to open governance so any party
the connection charge. These can include the
materially affected by it can propose a change
following:
to it. The process for doing this is laid out
• System / feasibility / fault level studies within the DCUSA itself. See the DCUSA
• Provision of Wayleaves website for more information:
www.dcusa.co.uk
• Additional meetings with the DNO or
site visits The Distribution Charging Methodologies
Forum exists to enable parties to discuss ideas
• Administration for improving the methodology possibly prior
Note that not all DNOs apply charges for all of to submitting a formal change proposal.
these items, and that not all of these items Estimating costs and getting a quotation
will be relevant for your project.
As mentioned, you can obtain indicative costs
Indicative costs and examples for works and equipment from DNO
Equipment costs and charges for services vary documents. To obtain a more accurate
across DNOs; it could therefore be misleading picture of the connection costs for your
to list indicative costs in this Guide. If you project, you can:
want to get an idea for indicative costs, the • Ask the DNO for a budget estimate
best place to look is the DNO’s Statement of
methodology and charges for connection. • Obtain an estimate of connection costs
You can find this on the DNO’s website. from a specialist engineering consultant
Aside from giving indicative costs for You should exercise care in interpreting
connection charges, these documents typically budget estimates. DNOs use reasonable
contain other useful information, including endeavours to identify remote reinforcement
guidance on the connection process and costs associated with the proposed
examples of various connections and their connection at this stage. However, it is
associated cost breakdown. It is updated possible that not all of the reinforcement
annually. costs will be included at this time.
Page 45
Connection Charges—Other Elements
Payment of connection charges If your connection does not proceed, it is
Connection charges are paid either: possible that some of the connection charge
will be refundable depending on if the DNO
• in full at the time that the connection has performed the work. You should inform
offer is accepted; or your DNO as soon as possible if you decide not
• in staged or phased payments, as per a to go ahead with your project.
payment schedule.
Staged payments are typically used for
generation projects which are greater than a
certain size, eg. in project value or duration.
The staged payments cover committed
expenditure by the DNO.
Charging Futures Forum: The Charging Futures Forum is a programme that co-ordinates
significant reform of electricity network access and electricity network charging arrangements.
Ofgem is the chair of the programme, and members include generators, network operators,
large customers, industry bodies and universities. The programme includes holding a quarterly
forum and teams called Task Forces, which review specific issues in detail. For more information
see the Charging Futures Forum website.
Requested in the early stage of a project, and Requested when electrical requirements have been
generally only for larger capital projects finalised
The DNO doesn’t require much information The DNO requires a lot of information from you
from you
Based on a desktop study—the DNO is unlikely Based on detailed design work, and may require
to carry out detailed designs or studies other input such as site surveys
DNO may charge DNO may now charge (see Assessment & Design
fees)
Assuming that you ask the DNO to undertake all of the work involved in your connection,
the timescale for the DNO to provide a budget estimate is 10 working days.
Page 46
Use of System Charges
Use of System (UoS) charges cover operation, charging methodology and a statement of
repair and maintenance of network assets, what the chares are for both generation and
and also any reinforcement to the network demand customers. You can find these on
that might be necessary that is not covered by DNOs’ websites.
the connection charge. You can find out more about the Common
All generators with equipment connected at Distribution Charging Methodology (CDCM)
LV and HV are subject to UoS charges under and EHV Distribution Charging Methodology
the Common Distribution Charging (EDCM) from DNOs’ websites, Charging
Methodology (CDCM). Generators with Arrangements section on Ofgem website, and
equipment connected at EHV are subject to Charging Methodology section on the Energy
UoS charges under the EHV Distribution Networks Association website.
Charing Methodology (EDCM). Distribution Use of System charges have been
These charges can be negative for generation and are subject to two of Ofgem’s Significant
(ie credits). Please see the table below for Code Reviews – the Targeted Charging Review
definitions of the terms LV, HV and EHV. (TCR) and the Access and forward-looking
charges review. Significant changes are
DNOs are obliged to publish documents about
underway. For more information see the next
their UoS charges. These cover their UoS
two pages.
HV (High Voltage) In general: 1 kV—22 kV. In practice, this means 6.6, 11 or 20 kV.
EHV (Extra High Voltage) In general this covers connection to the distribution network at or above
22 kV. In practice this means 33 or 66 kV, (or 132 kV in England and
Wales only). Some DNOs may define this slightly differently. See the
definition of EHV for your local DNO.
Page 47
Changes to Use of System Charges
Ofgem Targeted Charging Review Ofgem’s decision is that the distribution
Ofgem has been reviewing certain elements residual charge will change from one based on
of Transmission and Distribution Use of energy demand to a fixed charge levied on all
System charges (DUoS), in a Targeted households and businesses. The charges will
Charging Review (TCR) Significant Code be applied to final demand users (i.e. not
Review (SCR). This is because they had including generation-only or storage-only
concerns that the current framework for connections). The fixed charges will be applied
charging may result in inefficient use of the in bands, according to agreed capacity or
networks and unfair outcomes for consumers. energy demand and voltage level.
The SCR was set up in response to changes in
generation, with an increasing amount of For the distribution residual charge, there will
generation from smaller sources. More no longer be a link to time of consumption
businesses and households are generating through the application of red / amber / green
their own electricity onsite, but still rely on charging periods, although this will continue
the grid for part of their supply. for the forward-looking element of DUoS
charges. This means that customers will no
The review was launched in August 2017 and longer be able to switch to behind-the-meter
Ofgem published their decision in December generation to reduce the residual element of
Use of System charges.
2019. The outcome of the review will result in
significant changes to Use of System charges,
This change is likely to impact on demand
which will affect all users.
customers with onsite generation. This is
The review considered two main elements of because customers with onsite generation
charges: consume less from the grid, thus reducing the
1. Residual charges energy-based charge under the old
2. Non-locational embedded benefits arrangements. However, the final impact on
Residual charges are designed to recover bills will depend on how suppliers pass on
sufficient network costs, so that network charges to their customers.
companies can recover their allowed revenue Embedded Benefits
as determined in price controls with Ofgem.
They were not intended as charges to send Embedded benefits are historic charging
signals for how the network should be used. arrangements that had favoured Distributed
Generation with a capacity of less than 100
Residual charges currently make up around MW, in terms of receiving revenue. There
50% of DUoS charges (although this varies were four non-locational embedded benefits:
between DNOs) and 10-15% of a typical
electricity bill, and are currently largely based 1. Transmission Demand Residual (a
on energy consumption from the network. payment to Distributed Generation): this
Under the old arrangement customers who was the largest benefit of the four and
reduced their demand from the network with was removed in June 2017.
onsite generation could reduce (or avoid) 2. Transmission Generational Residual:
paying these charges, despite still using the subject of this Targeted Charging
network, and these avoided costs were Review.
recovered from other customers.
Page 48
Changes to Use of System Charges
3. Balancing Services Charges – payments Electricity Network Access and Forward-
from Suppliers: subject of this Targeted Looking Charges
Charging Review.
Ofgem launched the Electricity Network
4. Balancing Services Charges – avoided
Access and Forward-Looking Charges
charges: currently an avoided charge for
Significant Code Review (SCR) in December
Distributed Generation (for capacity <
2018. The scope of the review includes:
100 MW) – the Targeted Charging
Review concluded that this will be • Access rights for transmission and
addressed by a Balancing Services Task distribution users – consider
Force. improvements to non-firm access
options, time-profiled access rights and
shared access in the same local area.
The decision reached by Ofgem on items (2)
and (3) above are as follows. The Transmission • Distribution Network Use of System
Generation Residual, which was previously a charges – consider detailed changes to
payment for transmission connected the network models used to set
generation, will be set to zero. And Distributed charges, the extent of local granularity
Generation will no longer be able to receive (split DNO areas into more granular
payments from suppliers for avoided zones eg based on primary substation
Balancing Services Charges. The removal of groups), the basis on which users are
these Embedded Benefits will affect all grid charged (eg consider seasonal variation
connected generators who currently benefit in charges).
from these as a revenue stream. • Distribution connection charging
Next Steps boundary – consider a “shallower”
upfront connection charge.
Ofgem has directed Distribution and
• Transmission Network Use of System
Transmission Licensees to carry out the work
to make revisions to the relevant industry charges – consider detailed changes to
codes to enact these changes. The Embedded the network models used to set
Benefits changes are to be implemented in charges, application of TNUoS charges
2021, and the Transmission Residual Charge to Distributed Generation, and the basis
and the Distribution Residual Charge in 2022. on which users are charged (eg consider
The Energy Networks Association (ENA) seasonal variation in charges).
Project Initiation Document sets out how the Ofgem is undertaking detailed development
network companies are proposing to deliver and assessment of these options and intends
the changes. to publish their work for consultation in
autumn 2020, with a “minded to” decision
For more information, refer to the Ofgem expected by the end of 2020. Refer to the
webpage on the Targeted Charging Review. Ofgem website for more information. There is
There is also information on the Charging also information on the Charging Futures
Futures website. website.
Page 49
Metering Requirements, Parties and Charges
Metering requirements sends the information to a central
system for balancing and settlement
You may require separate meters for
measuring your import and export. There are You can choose to contact your supplier about
two categories of meter: the provision of meters, or contract directly
with a Meter Operator. If you use HH
• Half Hourly (HH)
metering, it is your responsibility to appoint a
• Non-Half Hourly (NHH) Meter Operator. You will have to enter into a
They are described in the box on the next Meter Operator contract with a meter
page. supplier. The contracts normally last for five
years, and the Meter Operator will:
The type of meter will affect:
• Provide, install and maintain your meter;
• the meter charges you pay; and and
• what category of UoS charges apply. • Collect data from your meter via a
Section L of the Balancing and Settlement communications link such as a
Code (BSC) dictates the type of meter you will telephone line he provision of meters is
require. If you are classed as a ‘Small Scale open to competition. Details of Meter
Third Party Generating Plant’ (currently Operators and their contact details can
defined as less than 30kW capacity), you can be found on the Association of Meter
choose to have a NHH meter. Otherwise, you Operators website:
have to have a HH meter, if metering export. www.meteroperators.org.uk
HH meters can provide metering data for each There are Codes of Practice which detail
half hour period, and so can be useful for technical requirements for Metering Systems.
understanding your electricity import or These can be found on Elexon’s website.
export at different times of the day. However,
they have significant costs associated with Charges
them. The cost of Meter Operator agreements and
Parties involved the costs associated with the communication
to collect data from your meter can be in the
NHH meters are the responsibility of the order of several hundred pounds a year. You
supplier. They will appoint the following should consider obtaining quotations from a
Supplier Agents: number of Meter Operators.
• Meter Operator: installs and maintains Note: in practice suppliers may pay the owner
the meter of some smaller Distributed Generation a fixed
• Data Collector: retrieves the data amount (eg. £/year) instead of installing
recorded by the meter and calculates meters and making payments based on units
your actual or estimated volume of exported. This is something you can discuss
energy consumption with your supplier.
• Data Aggregator: sums up volumes of
energy consumed for each supplier and
Page 50
Metering Requirements, Parties and Charges
NHH meters record total energy passing through the meter, but do not record the times
the energy is transferred. Typically the recorded data would be collected a few times a
year, eg. every quarter. In contrast, HH meters measure and record energy passing
through the meter for each half hour period. The data they record is typically collected
remotely every day, for example by a telephone line.
Domestic properties are being encouraged to have a smart meter installed. Smart meters
record total energy passing through the meter every HH. The introduction of smart
meters should improve consumer awareness of energy consumption and will allow for
the introduction of time of use tariffs .
Data from meters is used to determine charges and rewards. For example, to calculate:
• Imbalance charges for balancing and settlement
• Distribution or Transmission UoS charges
• Renewables Obligations Certificate rewards
Page 51
F. Selling Electricity:
Smart Export Guarantee (SEG)
In this section:
• An introduction to the Smart Export Guarantee (SEG) Incentive
• Eligibility and Accreditation
• Deployment caps and how they work
• Guidance on where to find more information
Tip: Read the information boxes for definitions or explanations of terms that
may be new or unfamiliar.
Introduction
Smart Export Guarantees (SEGs) are a financial A number of domestic Combined Heat and
incentive to support distributed and small- Power (CHP) units are also supported through
scale renewable energy generation, up to a FITs under a Micro CHP pilot scheme. The
capacity of 5 MW. Micro CHP pilot will support up to 30,000
installations with an electrical capacity no
SEGs are available for the following generation greater than 2 kW.
technologies:
• Anaerobic digestion (AD) This section will detail the structure of the
• CHP and Micro-CHP tariffs and will explain how to get accredited
• Hydro with SEGs.
• Solar PV
• Wind
Important Point: The SEG scheme for generators opened on the 1st January 2020. The SEG
scheme replaces the Feed-in Tariff (FIT) scheme that closed on the 31st March 2019 but works
differently to FITs.
There are two sources of financial benefit from FIT payments which are:
• Generation tariff: A fixed unit for each unit of electricity generated.
• Export tariff: A guaranteed price for each unit of electricity exported to the grid.
The SEG scheme obliges electricity suppliers to offer an export tariff rate to an eligible generating
unit.
Generators cannot receive SEG payments as well as FIT payments for exported electricity.
However, if the generator continues to receive FIT generation payments and opts out of
receiving FIT export payments then they are eligible to receive SEG export tariff payments.
Page 52
Tariff Structure
The main financial benefit from a generation Metering Requirements
project under the SEG scheme is the export All new installations that wish to export
tariff, which is a guaranteed price for each unit renewable energy to the grid must have an
of electricity exported to the grid. export meter installed. The export meter must
It is an obligation for licensed energy suppliers be capable of taking half-hourly
to offer eligible generation projects an export
measurements and have an export MPAN
tariff rate. The electricity suppliers decide the
(Meter Point Administration Number). The
SEG export tariff details i.e. the rate and the
export meter must be located at the point
length of the contract. However, although
wholesale electricity prices can fall below zero where the installation connects to the
due to changes in demand, electricity network. Smart meters are capable of
suppliers must always offer a tariff which is measuring half-hourly export energy so will
greater than zero. not need physically changing.
Page 53
Eligibility and Accreditation
Renewable Energy generators under 5 MW https://www.ofgem.gov.uk/publications-and-
are eligible for SEGs. updates/smart-export-guarantee-guidance-
generators
Accreditation steps:
For installations that are greater than 50 kW,
For wind or solar PV generation up to and
you will be required to demonstrate that the
including 50 kW, and for micro CHP, the
installation is suitably certified. Each electricity
accreditation process is as follows:
supplier will have their own requirements for
demonstrating certification, but these are
1. Install your generating unit—you must
expected to include the EREC G99 Installation
demonstrate that the installation and
Document and proof of ownership.
installer are suitably certified by using a
Microgeneration Certification Scheme
For all AD and Hydro installations, you are
(MCS) installer (see below);
required to provide evidence that the
2. Install a smart meter to measure export
installation is suitably certified for a capacity
energy every half-hourly;
up to and including 5 MW.
3. Apply for a SEG with your electricity
supplier, and provide them with any
For AD installations, an additional step is
documentation to demonstrate
required to gain accreditation, which involves
compliance so that they can verify your
submitting separate and ongoing
eligibility;
documentation to Ofgem, in the form of
4. Your electricity supplier will then be
Quarterly sustainability declarations and
responsible for the level of payment you
Annual feedstock declarations. More
will receive for the electricity exported,
information is available on Ofgem’s website:
for which you will be required to provide
https://www.ofgem.gov.uk/publications-and-
export meter readings.
updates/guidance-anaerobic-digestion-
See Ofgem’s website below for more guidance generators-seg-sustainability-criteria-and-
into receiving SEG payments: reporting-requirements
Page 54
Eligibility and Accreditation
Multi-technology sites: Electricity suppliers have an obligation to accept a request for SEG
payments from a generator that is exporting from an eligible site. However, if the export meter
records the energy exported from a combination of eligible and non-eligible SEG sources at the
same site, an electricity supplier does not have to make payments. You should check the
options and terms from different electricity suppliers carefully.
Extensions to SEG installations: The capacity of a generation unit of one particular technology
can be increased. However, if the installed capacity of the generating unit exceeds 5 MW then
the electricity supplier does not have to make SEG payments for the export that exceeds 5
MW. If you choose to install extra capacity at your site from a different technology source,
then the electricity supplier will recognise this as a separate eligible source and will be able to
make payments for the capacity of this technology up to 5 MW. For example, a 7 MW PV solar
array and a 3 MW wind farm would be eligible for SEG payments for 5 MW PV and 3 MW wind.
Local Flexibility Markets: As part of the ENA Open Networks Project, a workstream dedicated
to Flexibility Services (WS1A) is looking at the best way to implement markets for flexibility
services offered by Distributed Generation. Where co-located with demand, Distributed
Generation can offer Flexibility Services to the network by adjusting onsite demand and
generation in order to keep the network balanced, relieve congestion, and release network
capacity. This allows more Low Carbon Technologies (LCT), such as renewable generation, to
connect to the network. The DNOs created the ENA Flexibility Commitment in December
2018, which is the first step towards expanding the Flexibility Markets to local level.
For more information refer to the ENA’s website:
https://www.energynetworks.org/electricity/futures/flexibility-in-great-britain.html
And look for details of Flexibility Services on your DNO’s website.
Page 55
Where to Find More Information
For more guidance and the most up-to-date information on the Smart Export Guarantee, please
see the following organisations’ websites:
• Ofgem – About Smart Export Guarantee (SEG)
https://www.ofgem.gov.uk/environmental-programmes/smart-export-guarantee-seg/
about-smart-export-guarantee-seg
• Department for Business, Energy and Industrial Strategy (BEIS) — The future for small-scale
low carbon generation: Smart Export Guarantee – government response
https://www.gov.uk/government/consultations/the-future-for-small-scale-low-carbon-
generation
Page 56
F: Selling Electricity-
Contracts For Difference
In this section:
• An introduction to renewable electricity incentives
• Contracts for Difference
• The Renewables Obligation closure
• Guidance on where to find more information
Tip: Read the information boxes for definitions or explanations of terms that
may be new or unfamiliar.
Introduction
This section of the Guide focuses on Feed in There are various other power trading options
Tariffs with Contracts For Difference (CFD). for Distributed Generation, including:
This is the main financial incentive mechanism
• Selling your electricity on the wholesale
for larger schemes of low carbon generation.
market or to an electricity supplier
It has replaced the Renewables Obligation
(RO), which closed to new applications in • Levy Exemption Certificates (LECs)
March 2017. The RO closure does not affect • Embedded benefits
generation that was already accredited before
the relevant closure date. • Ancillary services
This section introduces the CFD mechanism, • EU Emissions Trading System (ETS)
and explains how you, as a generator, can These have been discussed briefly in Section
benefit. Key elements of the CFD scheme are B. The Role of Distributed Generation:
introduced. The application process for a CFD Benefits of Distributed Generation, which also
is much more complex than for the SEG points to further reading on these topics.
scheme. You are referred to relevant Beyond that, they are outside of the scope of
websites and documents for more this Guide.
information.
Page 57
Contracts for Difference (CFD)
• Ofgem: regulates National Grid as the
Introduction
EMR Delivery Body and determines
A Contract for Difference is a bilateral contract disputes.
between a generator and the Low Carbon
Contracts Company (LCCC, the CFD Eligibility
counterparty), which is government owned. A There are a number of eligibility criteria for
generator with a CFD is paid the difference the CFD, including:
between the “strike price” and the “reference
• Meet qualification requirements, eg.
price”. The strike price is an agreed price for
evidence of planning permission,
electricity reflecting the cost of investing in
counter signed connection offers,
low carbon generation. The reference price is
generation type;
a measure of the GB market price for
electricity. • Not considered an excluded applicant
eg. in receipt of another subsidy; and
CFDs require generators to sell electricity into
the market as usual. But to reduce their • Provision of other information / data,
exposure to market prices, the CFD provides a eg. incorporation information (details of
variable “top up” payment. When the strike different parties involved).
price is higher than the reference (market) CFD Allocation
price, the generator receives a payment. At
times when the market price exceeds the CFDs are awarded in rounds. During a round, if
strike price, the generator is required to pay the specified budget for CFDs is not exceeded,
back the difference, thus protecting all qualifying applicants will be awarded CFDs.
consumers from over-payment. If the budget is exceeded, the Delivery Body
will run an auction to allocate CFDs.
Parties involved
Rounds 1 and 2 took place in 2015 and 2017
A number of parties are involved in the CFD respectively, and CFDs have been allocated. In
mechanism. They include, with examples of Round 1 there were 27 successful applicants,
their roles: with project installed capacities ranging from
• Government: writes the policy, specifies 6 to 714 MW, and strike prices ranging from
the eligibility criteria and sets the £50 to £119.89 (in 2012 prices). In Round 2
budgets and rounds. there were 11 successful applicants, with
project installed capacities ranging from
• Low Carbon Contracts Company (LCCC):
50 kW to 1,386 MW, and strike prices ranging
signs the CFD and forecasts CFD
from £40 to £74.75 (in 2012 prices). Round 3
payments.
is now complete and Round 4 is opening in
• National Grid (Electricity Market Reform 2021.
(EMR) Delivery Body): runs the system
National Grid publishes a Contract for
for users to register, submit and manage
Difference Interactive Guidance document
applications; assesses the eligibility of
which provides details on the CFD process.
applicants; and runs the CFD allocation
Also see BEIS and the EMR Delivery Body
process.
websites for the latest information.
• EMR Settlement Ltd (Settlement Services
Provider): collects metering data,
calculates payments and manages the
settlement of payments between
generators and suppliers.
Page 58
Renewables Obligation
The Renewables Obligation (RO) closed to all The grace periods are available on Ofgem’s
new generating capacity on 31 March 2017. website.
This was previously the main incentive Operators that are successful in their grace
mechanism for larger renewable generation. period application will have the opportunity to
The closure does not affect capacity apply for accreditation under the RO after the
accredited before the relevant closure date, 31 March 2017.
which will continue to receive full 20 year
support until the end of the scheme in 2037. For more information on the closure of the
RO, refer to Ofgem’s website.
There are a number of grace periods, which
allow generators to gain accreditation under
the RO in certain circumstances after 31
March 2017. The availability of grace periods
differs across England and Wales, Scotland
and Northern Ireland .
Page 59
Glossary of Terms
Adoption Agreement: An agreement between a developer of Distributed Generation and a Distribution
Network Operator (DNO) and / or an Independent Connections Provider (ICP) concerning the transfer into
DNO ownership of infrastructure supplied and installed by an Independent Connections Provider (ICP).
Aggregator: An organisation which specialise in co-ordinating demand and generation (including storage)
to provide demand response and other market services. Network Operators and Suppliers may buy
demand response and other grid balancing services from aggregators.
Ancillary Services: Services such as the provision of reactive power support and black start capability by a
Generator to NGESO as part of an Ancillary Services Agreement with NGESO.
Apparent Power: The apparent power (measured in Volt-Amps or VA) at any point on the network is the
product of the voltage and current at that point. The apparent power is made up of two components, the
real power and the reactive power.
Auxiliary equipment: Any apparatus not directly a part of the boiler equipment or Generating Unit, but
required for the boiler equipment or Generating Unit's functional operation.
Balancing and Settlement Code (BSC): The Code which determines the rules governing the Balancing
Mechanism and settlement process for electricity trading in Great Britain. A BSC Panel has been charged
with overseeing the management, modification and implementation of the BSC rules, as specified in
Section B of the BSC. The Balancing and Settlement Code Company (ELEXON) supports the BSC Panel.
Balancing Mechanism: NGESO has a licence obligation to manage the Transmission System and, and
needs to have an arrangement in place for the scenario where more energy is generated than consumed,
or vice versa. Unchecked, this would result in system frequency falling or rising to an unacceptable
degree. The balancing mechanism provides a means by which NGESO can buy or sell additional energy
close to real-time to maintain energy balance, and also to deal with other operational constraints of the
Transmission System.
Capacity: See Registered Capacity.
Capacity Market: A market that aims to ensure security of electricity supply by providing a payment for
reliable sources of capacity.
Connection Agreement: An agreement setting covering the conditions under which your generating
equipment is allowed to be physically connected to the DNO network and remain connected and
energised while the network is operating normally.
Contestable: That part of the connection works which is open to competition.
Contracts for Difference (CFD): A bilateral contract between a generator and the Low Carbon Contracts
Company (LCCC, the CFD counterparty).
Climate Change Levy (CCL): Part of a range of taxation measures designed to help the UK meet its legally
binding commitment to reduce greenhouse gas emissions. This levy / tax is chargeable on the industrial
and commercial supply of taxable commodities for lighting, heating and power by consumers in the
following sectors of business: industry, commerce, agriculture, public administration and other services.
Connection and Use of System Code (CUSC): Contractual framework for connection to and use of the
National Electricity Transmission System.
Declared Net Capacity (DNC): Unless the energy source for your generating unit is wind, solar, wave or
tidal, then the declared net capacity is equal to the maximum power available for export on a continuous
basis minus any power imported by the station from the network to run its own site. For wind, solar, wave
and tidal, the declared net capacity is this value multiplied by a constant as follows: wind, 0.43; solar, 0.17;
wave or tidal, 0.33.
Page 60
Glossary of Terms
Distribution Code: The code required to be prepared by a DNO pursuant to condition 21 (Distribution
Code) of a Distribution Licence and approved by the Authority (The Gas and Electricity Markets Authority -
Ofgem) as revised from time to time with the approval of, or by the direction of, the Authority.
Distributed Generation (DG): A generating unit which is connected to a distribution network rather than
to the transmission system. Distributed Generation is generally smaller than generating units connected
to the transmission system as the maximum operating voltage of distribution networks is 132 kV in
England and Wales and 33 kV in Scotland.
Distribution Network: The distribution network is the system that comprises the equipment between the
transmission system and the customer’s service switch. In England and Wales the distribution networks
are the lines with a voltage less than or equal to 132 kV. In Scotland the distribution network is composed
of lines with an operating voltage of less than 132 kV.
Distribution Network Operator (DNO): A holder of a Distribution Licence, the DNO owns, operates and
maintains a Distribution network and is responsible for confirming requirements for the connection of
Distributed Generation to that network.
Embedded Generation: Another term used for Distributed Generation. See above.
Embedded Benefits: Embedded benefits are historic charging arrangements that had favoured Distributed
Generation with a capacity of less than 100 MW, in terms of receiving revenue. These are changing after a
review by Ofgem (refer to Chapter E for more information).
Energy Service Company (ESCO): A Government paper defines ESCOs as “a company that provides a
customer with energy solutions” rather than simply being an electricity or gas supplier.
EU Emissions Trading System (ETS): Formerly referred to as the EU Emissions Trading Scheme, the EU
Emissions Trading System (EU ETS) is one of the key policies introduced by the European Union to help
meet its greenhouse gas emissions reduction target. It is a Europe-wide cap and trade scheme that
started in 2005. The EU ETS covers electricity generation and the main energy-intensive industries.
Exemption Order (Generation License): Certain generating units that are not obliged to hold a generation
licence under the terms of Statutory Instrument 2001 No. 3270, The Electricity (Class Exemptions from the
Requirement for a Licence) Order 2001.
Extra High Voltage (EHV): This term is not defined in the Distribution Code, which only defines High
Voltage (HV) and Low Voltage (LV). In general EHV refers to a voltage above 22kV. In practice this means
33 or 66kV, or 132 kV (England and Wales only). Refer to your DNO’s definition.
Extension: It is sometimes necessary to extend the DNO’s distribution network in order to provide a
connection for a new user (demand or generation customer).
Fault Level: Prospective current that would flow into a short circuit at a stated point in the system.
Fully Type Tested: The whole Power Generating Module is type tested, rather than just part of the Power
Generating Module.
Generation Licence: A licence granted or to be granted under section 6(1)(a) of the Act - Statutory
Instrument 2008 No. 2376. This licence is obtained from Ofgem.
Generator: A person who generates electricity under licence or exemption under the Electricity Act 1989.
Grid Code: The code which the GB System Operator (NGESO) is required to prepare under its Transmission
Licence and have approved by the Authority (Ofgem) as from time to time revised with the approval of, or
by the direction of, the Authority.
Page 61
Glossary of Terms
Grid Supply Point (GSP): Any point at which electricity is delivered from the national electricity
transmission system to the DNO’s Distribution system.
Harmonics: A component of a periodic wave with a frequency that is a multiple of the frequency of the
original wave.
High Voltage (HV): A voltage exceeding 1000 V AC or 1500 V DC between conductors, or 600 V AC or
900 V DC between conductors and earth. In general DNOs consider that HV are voltages in the range of
1 kV to 22 kV.
Independent Connections Provider (ICP): Companies that have been thoroughly assessed and granted
the necessary accreditation to provide new connections in competition with the DNOs.
Independent Distribution Network Operator (IDNO): A holder of a distribution licence, an IDNO designs,
builds, owns and operates a distribution network, which is an extension to existing DNO network. They
typically build network for new developments such as business parks, retail and residential areas and
leisure facilities.
Interface Protection: The electrical protection required to ensure that the generation is disconnected for
any event that could impair the integrity or degrade the safety of the Distribution Network.
Large Power Station: A power station which is connected to a system in:
• National Grid’s Transmission Area with a Registered Capacity of 100 MW or more;
• SP Transmission plc’s Transmission Area with a Registered Capacity of 30MW or more; or
• Scottish Hydro Electric Transmission plc’s Transmission Area with a Registered Capacity of
10MW or more.
Levy Exemption Certificates (LECs): These exemptions favour energy efficient technologies or sustainable
power units; good quality Combined Heat and Power (CHP) and renewable electricity could be granted,
under certain conditions, Levy Exemption Certificates (LECs) for each kWh of electricity generated and the
LECs could be used to obtain Climate Change Levy (CCL) Exemption, and therefore avoid paying the CCL
tax applied on energy supplied to industrial and business users. Directly related to the Climate Change
Levy (CCL) as some supplies are excluded or exempt from the levy while others have a reduced or half-
rate.
Low Voltage (LV): A voltage normally exceeding 50 V AC between conductors and earth or 120 V DC
between conductors but not exceeding 1000 V AC or 1500 V DC between conductors or 600 V AC or 900 V
DC between conductors and earth.
Medium Power Station: A Power Generating Facility with a registered capacity of 50 MW or more but less
than 100 MW in England and Wales (by definition, there are no medium power stations in Scotland). In
EREC G99 this is known as an Embedded Medium Power Station.
Micro-generator: A source of electrical energy and all associated interface equipment able to be
connected to an electric circuit in a Low Voltage electrical installation and designed to operate in parallel
with a public Low Voltage Distribution Network with nominal currents up to and including 16 A per phase.
National Electricity Transmission System Operator (NETSO): Operates the electricity transmission system
in England, Wales and Scotland (see System Operator).
National Grid Electricity Transmission (NGET): Owns the electricity transmission network in England and
Wales. NGET is a member of the National Grid group of companies.
National Grid Electricity System Operator (NGESO): Operates the transmission system in England, Wales
and Scotland (takes the role of the NETSO). NGESO is a member of the National Grid group of companies.
Page 62
Glossary of Terms
Ofgem: The Office of Gas and Electricity Markets.
Point of Connection: The interface at which the Power Generating Module or Generator’s Installation is
connected to a Distribution Network, as identified in the Connection Agreement.
Point of Supply: The point at which the Distribution Network is to be connected into the customer site.
Protection Settings: The provisions for detecting abnormal conditions in a System and initiating fault
clearance or actuating signals or indications.
Power Exchange: Market and clearing services for the UK Wholesale Power Market are provided by EPEX
SPOT (part of the APX Group) and Nord Pool Spot AS (NPS), which operates under the name N2EX. N2,
the UK market offering, will initially be a marketplace for Physical UK Power contracts and launch a
platform for financial futures contracts further into 2009: a physical market and a futures market. From
the outset N2 will operate as a physical power exchange providing platforms for the trading of UK Power
contracts. This can be divided into three product areas: the Spot Market, the Prompt Market and the Day
Ahead Auction Market (DAM).
Power Generating Facility (PGF): One or more Power Generating Modules connected to at one or more
Connection Points. This is a Power Station in EREC G59.
Power Generating Module: Either a Synchronous Power Generating Module or a Power Park Module.
A Synchronous Power Generating Module is an indivisible set of Generating Units (i.e. one or more units
which cannot operate independently of each other) which can generate electrical energy such that the
frequency of the generated voltage, the generator speed and the frequency of network voltage are in a
constant ratio and thus in Synchronism.
A Power Park Module is one or more Generating Units (including storage devices) generating electricity,
which is either asynchronously connected to the network or connected through power electronics, and
has a single connection point to a Distribution Network.
Power Generating Facility: One or more Power Generating Modules connected to a Network at one or
more Connection Points. This is also known as a Power Station in some regulatory documents.
Reactive Power: Reactive power (measured in Volt-Ampere reactive, or VAr) is a component of apparent
power (see apparent power definition above).
Real Power: Real power (measured in Watts, or W) is a component of apparent power (see apparent
power definition above). It is likely that real power is the electrical power you are more familiar with. It is
the useful power that we import into our houses to run our electrical goods.
Registered Capacity: The normal full load capacity of a generation set as declared by the generator less
the MW consumed when producing the same. For a customer with own generation this will relate to the
level of output they expect to export to the DNO’s Distribution System.
Registered Data: Data referred to in the schedules to the Distribution Data Registration Code.
Reinforcement: Reinforcement work is usually required to increase the electrical capacity of those parts
of the network which are affected by the introduction of new generation or demand. Other work might
include upgrading the switchgear at a substation some distance from the proposed generation project,
due to the increase in fault level caused by the connection of generating equipment.
Renewable Obligation Certificates (ROCs): A green certificate issued to an accredited generator for
eligible renewable energy generated within the UK and supplied to customers within the UK by a licensed
electricity supplier. ROCs are issued for each MWh of eligible renewable output generated, the amount of
ROCs received depend on the technology of the generating station.
Page 63
Glossary of Terms
Retail Price Index (RPI): General purpose measure of inflation used in the UK.
Reverse Power Flows: Power flows in the opposite direction to those associated with the consumption of
electricity by users.
Site Responsibility Schedule: Also called a Joint Operational Agreement. A schedule defining the
ownership, operation and maintenance responsibility of equipment and Apparatus at the Point of Supply
of the DNO.
Supplier (Electricity Supplier): Electricity suppliers purchase electricity (on the market or in contracts) and
sell electricity to customers (commercial, industrial and domestic).
Transmission Network (System): A system of electricity lines and equipment owned by the holder of a
Transmission Licence and operated by the GB SO, which interconnects Power Stations and substations. In
England and Wales the transmission system is the equipment principally rated above 132 kV while in
Scotland they are those principally at or above 132 kV.
System Operator (SO): The operator of the transmission networks, the System Operator balances supply
with demand on a minute by minute basis.
System Voltage: The voltage at which an electrical network is operated.
Thermal Rating: The current-carrying capacity of a cable, an overhead line or any other item of electrical
infrastructure, which is determined by the heating effect arising from electrical losses.
Type Tested Equipment: Equipment that has been tested in accordance to ensure that it meets the
requirements of EREC G98 or G99. Using type tested equipment simplifies the connection and
commissioning process.
Use of System (UoS): The use of a transmission or distribution system by a generator, supplier, customer
or an interconnected party for the purposes of transporting electricity.
Voltage Flicker: Voltage flicker is a deviation in system voltage, where power is not completely lost.
Flicker may be defined as the sensation experienced by the human eye when illumination levels change as
a result of the change in voltage.
Voltage Fluctuation: Fluctuations in the supply voltage that can be caused by a fluctuating load, and which
in turn cause flicker.
Voltage Unbalance: Occurs where there exists a difference in voltage magnitude between phases and/or
a shift in the phase separation from 120° (for a three-phase system).
Page 64
References
Standards and other documents:
Balancing and Settlement Code (BSC) is available free of charge on Elexon’s website
Connection and Use of System Code (CUSC) is available free of charge on National Grid’s website
Distribution Code of Great Britain—available free of charge on the Distribution Code website
Engineering Recommendation G59, relating to the connection of generating equipment to the distribution
systems of licensed Distribution Network Operators. This is not applicable to generation connecting
after the 27th April 2019.
Engineering Recommendation G81 is called “Framework for design and planning, materials specification,
installation and records low voltage housing development installations and associated new HV/LV
distribution substations”. It can be found free of charge on the Energy Network Association’s website
Engineering Recommendation G98: Requirements for the connection of Fully Type Tested Micro-
generators (up to and including 16 A per phase) in parallel with public Low Voltage Distribution Networks
on or after 27 April 2019— available to download on the DCode website or ENA.
Engineering Recommendation G99: Requirements for the connection of generation equipment in parallel
with public distribution networks on or after 27 April 2019— available to download on the DCode website
or ENA.
Electricity Safety, Quality and Continuity Regulations (ESQCR) 2002, Section 22: Statutory Instrument
Number 2665, available free of charge
Grid Code of Great Britain — available free of charge on National Grid’s website
IET Wiring Regulations (British Standard 7671) are available to buy on the IET website
Metering Codes of Practice
Requirements for Generators is available free of charge on the EUR-Lex website.
Requirements for micro-generating plants to be connected in parallel with public low-voltage distribution
networks (BS EN 50438) is available to buy on the BSI website
Statutory Instrument 2001 No. 3270, The Electricity (Class Exemptions from the Requirement for a
Licence) Order 2001
Statutory Instrument 2008 No. 2376, The Electricity (Applications for Licences, Modifications of an Area
and Extensions and Restrictions of Licences) Regulations 2008
Page 65
References
Useful websites:
ENTSO-E www.entsoe.eu
Lloyds Register www.lr.org/sectors/utilities/schemes/ners.aspx
Microgeneration Certification www.microgenerationcertification.org
Scheme
National Grid www.nationalgrid.com/uk/Electricity/
Ofgem www.ofgem.gov.uk
Renewable Energy Association www.r-e-a.net
Page 66
References
Relevant reports and guides:
Upgrading our energy system: smart systems and flexibility plan; BEIS; 2018
Page 67
Revisions
1.0 October 2020 Minor revisions have been made. Changes include:
• General Updates
• Update of V2G
• Update to RfG requirements for storage
• Update to ENA Open Networks Project
• Update to Chapter F
• Update to Type Testing
• Update to Ofgem Targeted Charging Review
• Update to BSUoS
Page 68