E-GP Strategy Plan Part2
E-GP Strategy Plan Part2
e-PPMU will have a project manager to coordinate all activities of design and
implementation including technical team coordination, monitoring of project
progress, capacity building and change management activities, contract
management of consultants and experts, and will be the principal liaison with the
e-Procurement System Developer. The mandate of the Project Manager is as
follows:
a) Ensuring that the e-Procurement project is clearly defined for all phases of the
project
b) Identifying the project risks and developing strategies to manage those risks
c) Determining the project requirements and budget accordingly
d) Effective management of all contracts related to the project
e) Effective coordination of Government Agencies and other stakeholders
involved in e-Procurement Implementation
f) Support and facilitate the design and development of e-Procurement System
g) Develop and update roadmap and strategy to guide project implementation.
h) Develop Project Charter to outline the project objectives, scope, identify the
main stakeholders and specify their roles.
39
i) Review the project schedule and resources
j) Review supplemental plans including risk management, communication,
project quality and change management plans
k) Prepare the terms of reference for major Consultants who will be engaged
during the project.
l) Advise on policy changes that may be required to implement the e-
Procurement.
The e-PPPMU will handle planning and preparation activities at the beginning
and will later become a technical support team to provide guidance, technical
assistance where required. The skill mix of the e-PPMU may include:
Following project team and organization structure will be put in place for the
implementation of e-Government Procurement:
b. Organization Chart
40
The e-Government Implementation Team will have 20 members including 1
Project Manager, 1 procurement expert, Communication Specialist, 1 Business
Process Reengineering and Change Management Experts, Trainers, Developers,
IT experts on Application, Database, System and security, Helpdesk staff and
support associates as required. Number of ICT related staff depends on the e-
Procurement System acquisition model. This will later evolve into an e-
Procurement Unit to be established as a permanent unit for the sustainability of e-
Procurement system management, support and rollout functions. Positions and
numbers of the administrative and technical workforce will be adjusted according
to the pace of progress and requirements on the implementation process.
41
Figure 7: e-Procurement readiness assessment.
42
The existing system, private sector integration, and legislation in Ethiopia appear
to be firmly established and recognized. ICT infrastructure and web services
established by the MCIT have progressed significantly over the last couple of
years and are now poised to successfully support a range of e-Government
services including e-Procurement. Other dimensions need significant
considerations and improvements.
The e-Procurement strategy also shall address policy issues about legal,
technical, administrative, capacity building, governance model, sustainability
model, human resources model, authentication, third-party services, operations
and maintenance models, and a roadmap with a clear action plan for the
implementation. Cabinet of Ministers endorses the e-Procurement strategy with
full ownership and commitment to the implementation of e-Procurement in
Ethiopia.
Ethiopia has already built some of the foundations required for the development
and adoption of an enhanced end-to-end e-procurement platform, some other
activities remain to be carried out. A version of e-Procurement system, which is
expected to be used as the national e-Procurement system is to be reviewed for
identifying the gaps and required enhancements, and business process
reengineering should be carried out, wherever possible, for enhancing the
efficiency in procurement process.
43
Step 2.1: Securing Budget
Mere automation of the paper-based procurement system does not give the
desired efficiency and leverage the available technology. It is important to
streamline the manual process and practices by business process reengineering
first, which help improve the efficiency gains benefits because of the streamlined
procurement process. The business processes should be based on the new
legislation and should be re-engineered to make the processes more simplified,
efficient, and get the benefits of modern technologies. This will require changing
the way the procuring entities prepare the bidding documents, bidders prepare
the bids, fees are collected for the bidding dossier purchase, bid securities are
handled, processes of evaluation and communication with the bidders and other
stakeholders is managed, contracts are managed, and complaints are handled.
44
guidelines, would have to be synchronized and harmonized with the Public
Procurement regulations, guidelines, manuals, and circulars.
It shall define the complete scope of the e-Procurement system and then define
the deliverables by the software supplier and prepare the bidding document for
national or international competitive bidding for the acquisition of an e-
Procurement system.
45
manuals of the country from annual procurement plan preparation, e-
advertise, e-Clarification, e-Amendment, e-submission and
modifications, e-evaluation, e-complaint handling, e-notice to signing of
contract, Visualization of procurement performance based on Open
Contracting Data Standard (OCDS),
Complaint and dispute management
E-catalog
All procurement methods prescribed by the prevalent procurement
proclamation
E-contract management
E-Procurement performance measurement and Monitoring
E-invoicing, payment, bid security, advance and performance
guarantees (through banks and other options)
Interface with Integrated Financial Management System (IFMIS),
company registrar’s office, banks, tax, and other e-services relevant to
e-Procurement
User activities under administrative workflow and system audit trails
Online help with visual presentations
Procurement System filling all gaps and following the International best
practices. (recommended)
In the Ethiopian context, MCIT and BDU e-Procurement systems were assessed.
Use of home-grown system help enhance the local capacity and will be cost-
effective not only at the beginning but also in long run leveraging the local content
and local technical capacity. Refer to sub-section 1.6 for an analysis of the MCIT
and BDU e-Procurement Systems based on their system demonstration. MCIT’s
e-Procurement system is agreed to be enhanced for use as the National e-
Procurement system. MCIT shall transfer all the Intellectual Property Rights (IPR)
of the e-procurement system software to the FPPA for using as the National e-
Procurement System.
46
Step 3.2: Data Center Preparation
Building the data center involves installation of power solutions and power
backup, precision air-conditioning, fire alarm system, digital closed-circuit
television, surge suppressor, access control system, water detection system,
dehumidifier, pest repellent, data rack, raised flooring, electrical and civil works,
and passive components like network cables, patches, and so on, procurement of
data center and mirror center servers, network equipment, storage, power
solution, Internet connectivity, and required system software and licenses.
FPPA shall use the data center at the MOFEC as the primary data center and
temporarily, backup will be hosted at the National Data Center operated by the
MCIT. Operation, maintenance and any enhancements of the e-Procurement
System are the responsibilities of the FPPA and shall be carried out in
coordination with the MOFEC and MCIT. FPPA shall ensure the hosting
environment, e-Procurement system and data to be highly secured, and available
for access around the clock.
Establishment of the Disaster Recovery site is a critical factor. The FPPA shall
develop a policy on risk, reliability and performance requirements for such hosting
primary and disaster recovery environments.
Automation of the paper-based procurement system is not panacea and does not
give desired efficiency and leverage the available technology. Change
Management (CM) is intended to provide a holistic framework to manage the
change in the functional, technical, organizational or regulatory aspects. Change
management is one of the important activities to be carried out at all levels of
user environments for the successful adaptation of the e-Procurement system.
For public procuring entities, the new rules and practices in the electronic
environment will require changes to the way they work, for example, in use of
new procedures, as well as the technology mandates. For some, the appropriate
technology will already be in place. For others, that are operating public
procurement in a purely manual manner, there is a need to take necessary
change actions in a short time to ensure e-Procurement system can be properly
implemented.
The scope of the change management extends to the people, process and
technology as these relate to the e-Procurement system. Changes envisaged are
enterprise-wide and span the following areas:
a) Design and acceptance of new business processes and practices
47
b) Re-structuring shaping of institutions
c) Work ethics
d) New performance measures
e) Changed roles and responsibilities
f) Training
g) Changed policies and procedures
h) New services and information flows to clients
i) Devolved power management
j) Regular communication
k) Emotional change management—Emotional readiness is very
important for success.
Developing leadership at political, social, different levels of
government bureaucracy, private sector bidding community
Managing resistance in public procuring entities and bidding
community
b. Capacity building
The training and capacity building programs shall be designed for all categories
of personnel including Executives, Policy Officials, Procurement professionals,
auditors, bidders, and other players in the procurement function. FPPA shall
coordinate with Ethiopian Chamber of Commerce and Sectorial Association for
providing capacity programs to bidding community.
Benchmark study visits for the selected key users in few of the countries
where e-Procurement system is already implemented shall be conducted for
gaining knowledge and learn the best practices from the experience on the
implementation of e-Procurement system. Such visits will be carried out at the
preparatory stage of e-Procurement implementation process, so that the
knowledge gained from other countries could be used for the success of the
e-Procurement implementation in Ethiopia.
Different levels of training program shall be conducted to address the capacity
needs of different users involved in the procurement processes (i.e., training
programs for procuring entity procurement users, bidders including
professional association members, evaluation committee members,
accounting officers, bank users, oversight agency users, etc.). Training
programs will be in the form of regular courses as well as ad hoc trainings on
demand basis. Training programs shall be conducted at the all-administrative
levels of public procurement.
48
For the effective adaptation of the e-Procurement system by its key users and
make the e-Procurement system successful, initial support on its operation,
maintenance, implementation management is very important. For this, a
helpdesk with adequate resources under the project management team shall
be established.
49
willingness and commitment of leadership in the organization to take up e-
procurement, the level of use of information and communications technologies by
the procurement-process-related personnel, and diversity of procurements
carried out by those agencies.
50
Procurement guidelines, and other international best practices. The audit should
be carried out at the last stage of pilot implementation and before the operational
acceptance of the e-Procurement system, so that the software developer delivers
the fully robust system. Nationwide roll-out should be carried out only after the
third-party audit and fixing all the issues encountered and identified during the
pilot implementation and through the audit.
Following options may also be mandated to raise revenue to fund the operations,
maintenance, and support of the sustainability of the e-Procurement system
through:
a) Transaction or service fee from awarded Bidders,
b) Forfeited security and guarantee amounts,
c) Other Value-Added Services (VAS) like classified Bid notifications through
email or mobile alerts, additional storage for documents, fees for duplicate
contract completion certificate, delivery of paper copy of bidding
documents, trainings on request, etc.
d) Bidders registration and renewal for the use of e-Procurement System,
e) Bidding document download
f) Subscription on number of categories from the e-catalogue, etc.
Fees if charged for the use of an e-Procurement system shall be reasonable in
order not to deter bidders.
A common issue is where the government keeps the door open to paper bids
even while it is implementing e-procurement. Allowing parallel option of traditional
hardcopy bidding process only slows the rate of take-up of the systems and can
defeat the purpose of promoting e-procurement. The case for parallel bidding
options shall be at best discouraged in bidding process. At the beginning,
procuring entities may indicate the procurements to be carried out electronically
or manually in the Annual Procurement Plan, but it should also be noted that not
all items can be subjected to e-procurement at the time of pilot implementation.
51
3. Fit-for-purpose e-Authentication shall be allowed
52
procedures after necessary Business Process Reengineering (BPR) of the
manual procurement processes and practices;
c) Amendments shall be made to standard bidding documents and conditions
wherever required to suit e-Procurement;
d) Recognition of online procurement methodologies such as e-Bidding, e-
evaluation, e-Framework Agreements and Contracts, e-Quotations, e-
Auctions and e-Reverse Auctions, e-Catalog, e-Invoicing, e-Audits, and
procurement contracts management using e-Contract Management
functions of e-Procurement System;
e) Mandating centralized online bidder registration as a pre-requisite for
participating in government procurement through the e-Procurement
system, and submission and processing of bid responses through the e-
Procurement system.
f) Protecting the rights and responsibilities of users, bidders, procuring
entities, FPPA, PPPDS, oversight agencies, operation and maintenance
agency, and other stakeholders while using e-Procurement system, e-
Procurement system shall publish its Terms and conditions of use of e-
Procurement system, Disclaimer of consequences of using e-Procurement
system, policy of data protection and confidentiality, intellectual property
rights, codes of practices, and authenticity of electronic transactions and
digital records and documents as legal evidence, etc.
Private sector participation in Ethiopia looks like it is working pretty well. Private
sector consultation is carried out through the Public-Private Consultative Forum
established that an MOU between Ministry of Trade and Ethiopian Chamber of
Commerce, and interactions take place in regular frequency. Chamber of
commerce is enthusiastic and interested to collaborate in the introduction of e-GP
in the country. A business activation strategy shall be developed in collaboration
with the Chamber of Commerce to incorporate existing suppliers and may also
work with the service industry that supports business applications. The
development of a viable business activation strategy is critical in getting the buyer
community embrace the reform.
8. Risk Management
The e-Procurement system is to be delivered on the basis of a public sector-wide
service, and as such has potential key risk issues from both an internal and from
a client perspective. Active risk management will ensure that procuring entities
and Providers are able to benefit from this service in the knowledge that the
systems and the practices employed provide an appropriate degree of reliability,
efficiency and security. The management of this project and a smooth
implementation is essential to maintain public confidence and the integrity of the
53
service. To this extent, the risk management framework provides a structured
format that reinforces good management practices and aims to minimize
unexpected outcomes. Implementation challenges for this e-procurement project
will come from both inside and outside of government and can include, among
others:
There are also significant design and ownership risks. The scope of government
procurement is extensive and varied, ranging from the acquisition of minor items
such as office supplies through to major construction, telecommunications, defense,
hospital supplies and complex services. This supply side, or government
procurement, affects thousands of suppliers, thousands of line items and is usually
managed by thousands of procurement stakeholders within government.
Categories of Risk
54
CHAPTER 3: E-PROCUREMENT IMPLEMENTATION ROADMAP
4
Engage FPPA Short term Finalize Business, Technical
developer / and functional specifications
suppliers Finalize phases for rollout
Advertise for e-Procurement
system Implementation
55
Consultant
Evaluate and award e-
Procurement Implementation
contract
Initiate change management in
pilot agencies
Establish training facility
Establish help desk / service
center and advertise to public
and private sectors
5
Management FPPA Short term Engage e-Procurement
and Technical Project Manager
reporting Establish reporting formats,
terms of reference and meeting
schedules for e-Procurement,
Steering Committee and Project
Technical Committees
Establish project milestones
and KPIs
Establish contract management
oversight requirements
Establish risk management and
reporting
6
Operational FPPA Short term Revise existing procurement
e- operational policies and
Procurement harmonize with digital
regulations environment
or Develop new operational
guidelines regulations and guidelines as
required for digital environment
Establish e-signature and e-
document policies for the use in
e-Procurement
7
Human Develope Short term Developer to bring procurement
Resource r, FPPA synchronize officials in batches through
Enablement d with roll- training facility immediately
out before rollout
56
8
Data Centre MOFEC, Medium If required, create an integrated
Disaster MCIT term Data Centre with additional
Recovery and hardware, software and new
Site FPPA architecture
57
1.2 Implementation Timelines - Phases
58
ANNEX I: ETHIOPIA E-PROCUREMENT READINESS ASSESSMENT
The overall Level of Readiness (LoR) on nine (9) components was assessed as
moderately satisfactory level with the score of 2.97 out of 4.
60
Table 9: e-Procurement Readiness Score Matrix
The overall Level of Readiness (LoR) on nine (9) components was assessed as
Moderately Satisfactory level with the score of 2.97 out of 4.
61
1) Component 1: Government Leadership
The lead agency will define the need for management and technical expertise
and funding as well as coordination and collaboration across government. The
Cabinet-level sign-off and lead agency establishment are important first steps to
establish leadership, coordination and effective outcomes as well as the
mechanism by which the requisite expertise can be assembled. The lead agency
will require resources and expertise not just in technical areas but also to
undertake change management.
62
2) Component 2: Human Resources
63
• Standard Bidding Documents (SBDs) for most of the procurement
methods are available, but those documents are not consistently used
across the government.
4) Component 4: Policy
From the survey responses it was revealed that there are no widely publicized e-
Procurement strategy and policy of the government in terms of e-Procurement to
be made compliant to the prevalent legislation.
• At the policy level, the government has made decision on the introduction
of e-Procurement in the country.
• Ethiopian e-Governments Strategic Implementation Plan 2020
incorporates the implementation of e-Procurement.
• Open Contracting Data Standards (OCDS) policy is still not in place.
• Governments have some level of policy on ICT and pharmaceutical
procurement.
Ethiopia currently follows the Directive issued by the Ministry of Finance and
Economic Development Pursuant to Article 78/2 of the Ethiopian Federal
Government Procurement and Property Administration Proclamation no 649/2009
and Article 19 of the definition of powers and duties of the Executive Organs of
the Federal Government of Ethiopia Proclamation No 471/2005/6 (as amended).
A new proclamation is at the draft stage and expected to be issued soon.
64
• High enthusiasm shown under this category of readiness assessment is
because of the New Procurement proclamation being drafted guided by
the full decentralization of the procurement to spending agencies
• Cyber security policy and e-Transaction Policy are in place
7) Component 7: Standards
Standards for using government email accounts is not there. Symptomatic of this
65
is the common usage of Gmail / yahoo business addresses amongst government
officials.
• There is standard authority and there are various technical groups working
under the authority
• Government has published standard for government services
interoperability.
• PPPDS and other agencies still do not use any procurement category and
item classification standards like UNSPSC, CPV.
• E-signature policy is based on PKI infrastructure, but such infrastructure is
not yet ready for use.
• There are recommended standards for ICT and some other common use
items.
• Use of SBDs are not consistent across the procuring entities.
Within the private sector, there is extensive capability amongst larger businesses
in the use of computers in their businesses, and they showed enthusiasm for the
introduction of e-procurement.
The private sector is enthusiastic about the e-GP System and seems ready for
the adoption of e-GP system including making the necessary investment to
ensure connectivity, although there could be challenges to enhance the ICT
capacity of the small businesses.
66
Key observations from the e-GP Readiness Assessment:
• There is standard authority and there are various technical groups working
• Private sector consultation is carried out through the Public-Private
Consultative Forum established that a MOU between Ministry of Trade
and Ethiopian Chamber of Commerce, and interactions take place in
regular frequency
• Capacity building initiatives in procurement is not adequate
• E-Procurement is wholeheartedly welcomed by the business community
despite ICT access challenges in case of small business.
• Chamber of commerce is enthusiastic an interested to collaborate in the
introduction of e-GP in the country
E-GP System should address the spirit and requirements of the public
procurement based on new procurement law and international best practices.
The assessment of this component is based on the use of e-Procurement
systems developed and used by MCIT and BDU.
Key Observations:
67
5. Information Network Security Agency (INSA)
6. Public Procurement and Property Disposal Service (PPPDS)
7. Ethiopian Roads Authority (ERA)
8. Addis Ababa University
9. Bahir Dar University
10. Hawassa University
11. Mekelle University
12. Jimma University
13. Pharmaceuticals Fund and Supply Agency (PFSA)
14. Engineering Procurement Directorate, ERA
68
ANNEX 2: STRATEGIC OBJECTIVES, KEY PERFORMANCE INDICATORS AND
TARGETS
69
the procurement end of 2022/23.
processes within,
and where
appropriate
across agencies
and sectors.
2.2 To maximize Percentage of total 50% of expenditure
value for money expenditure on on Goods works
for government Goods, works (repairs and
expenditure by (repairs and maintenance) and
enhancing the maintenance) and Services in the Pilot
buying power of Services procured PES procured under
the public sector. under e- e-Procurement
Procurement contracts by the end
contract of 2021/22.
70
Increase in audit Increase in the audit
coverage coverage by x%
2.4 To make Reduction in 20% reduction in
effective use of Transaction Cost average transaction
human resources Savings for Goods, costs by the end of
in the Works and Services 2019/20.
procurement as a measure of the
process. human resources
being freed up for
deployment
elsewhere
3. Economic 3.1 To promote Percentage of 80% by end of
Development competition Tenders and Award 2020/21.
(Competitive among suppliers Notices Published in
ness, while maintaining e-Procurement
investment reliable sources of Portal by the
climate) supply. agencies registered
in e-Procurement
System.
The average Increase of 50% in
number of bids bid numbers by the
received end of 2020/21.
71
and tender documentation
documentation published, on the e-
published procurement web site
electronically by the end of two
years (by the end of
2022).
This should
be measured by
requiring PEs to
report annually to
FPPA on the total
number of tenders
issued and awarded.
10% of expenditure
on Goods and
Percentage of services should be
Expenditure on supported by e-
common Goods and Framework
Services supported Agreements by the
by e-Framework end of 2021.
Agreements
80% of all
Percentage of procurement
Payments made transactions paid
through e-Payments through the e-
under e- Payment mechanism
Procurement provided by the e-
System Procurement System
by the end of year
Three (by the end of
2021).
There are both financial and non-financial targets estimated. Targets and key
performance indicators are defined for each of the strategic objectives identified.