MISK Method Statement Status Log
MISK Method Statement Status Log
Action by
Sl.No# Description Method Statement Check List Inspection and Test Plan Risk Assessment Submission Date Status Code Status Remarks
(To be Submitt)
Mechanical System
2 Installation of AHU's/FAHU's/PU's Technical Development Under Revision with TD ü ü ü 25-Feb-21 TD Submission on 25-Feb-2021
3 Testing & Commissioning of AHU's/FAHU's/PU's Technical Development After Submittal approval TD As coordinated with BSS QC, for Testing criteria, need manufacturer
recommendation catalogue
5 Testing & Commissioning of FCU's Technical Development After Submittal approval TD As coordinated with BSS QC, for Testing criteria, need manufacturer
recommendation catalogue
7 Testing & Commissioning of Split A/C's Technical Development After Submittal approval TD As coordinated with BSS QC, for Testing criteria, need manufacturer
recommendation catalogue
12 Installation of Refrigerant Copper Pipes & Insulation Technical Development ü ü ü ü 20-Feb-21 With BSS No Update
13 Testing & Commissioning of Refrigerant Copper Pipes & Insulation Technical Development Cancelled Since, no commissioning for Pipes, testing included with the Piping MOS
Electrical System
1 Testing & Commissioning of Wires and Cables Technical Development ü ü ü ü 6-Jan-20 With BSS No Update
2 Testing & Commissioning of Wiring Devices Technical Development Cancelled ü ü Cancelled 6-Jan-20 With BSS No Update As per BSS QC; No MOS & Risk Assessment; Only Test Plan and Checklist
3 Testing & Commissioning of Grounding and Bonding Technical Development Cancelled ü ü Cancelled 9-Jan-20 With BSS No Update As per BSS QC; No MOS & Risk Assessment; Only Test Plan and Checklist
4 Testing & Commissioning of Lightning Protection System Technical Development Cancelled ü ü Cancelled 9-Jan-20 With BSS No Update As per BSS QC; No MOS & Risk Assessment; Only Test Plan and Checklist
6 Installation and Testing of Structured Cabling System Technical Development Cancelled Not in TDC Scope
7 Testing & Commissioning of Structured Cabling System Technical Development Cancelled Not in TDC Scope
9 Technical Development Cancelled As discussed with Elec QC & DAR; Combined submission by SAJCO with
Testing & Commissioning of Medium Voltage Cables
Underground Distribution
With TD for revision as per latest internal comments on the content
10 Installation and Testing of Busways Technical Development Under Revision with TD ü ü ü 3-Mar-21 TD
uniqueness
With TD for revision as per latest internal comments on the content
11 Testing & Commissioning of Busways Technical Development Under Revision with TD ü ü ü 3-Mar-21 TD
uniqueness
With TD for revision as per latest internal comments on the content
12 Installation and Testing of 13.8 KV Switchgears Technical Development Under Revision with TD ü ü ü 3-Mar-21 TD
uniqueness
13 Testing & Commissioning of 13.8 KV Switchgears Technical Development ü ü ü ü 28-Feb-21 TD Test reports formats under preparation
MISK - MEP Method of Statement Master List
Action by
Sl.No# Description Method Statement Check List Inspection and Test Plan Risk Assessment Submission Date Status Code Status Remarks
(To be Submitt)
Mechanical System
13 Testing & Commissioning of Refrigerant Copper Pipes & Insulation Technical Development
Electrical System
1 Installation and Testing of Grounding and Bonding Technical Development NA NOT SUBMITTED NA waiting for Project Specifications
2 Installation and Testing of Lightning Protection System Technical Development NA NOT SUBMITTED NA waiting for Project Specifications
3 Technical Development
4 Technical Development
5 Technical Development
6 Technical Development
7 Technical Development
8 Technical Development
9 Technical Development
10 Technical Development
11 Technical Development
12 Technical Development
13 Technical Development
14 Technical Development
15 Technical Development
16 Technical Development