Algorithms: Scheduling Algorithms For A Hybrid Flow Shop Under Uncertainty
Algorithms: Scheduling Algorithms For A Hybrid Flow Shop Under Uncertainty
Article
Scheduling Algorithms for a Hybrid Flow Shop
under Uncertainty
Christin Schumacher * and Peter Buchholz
Informatik 4—Modeling and Simulation, Department of Computer Science, TU Dortmund University,
D-44221 Dortmund, Germany; [email protected]
* Correspondence: [email protected]
Received: 30 September 2020; Accepted: 27 October 2020; Published: 31 October 2020
Keywords: scheduling; uncertainty; discrete event simulation; hybrid flow shop; scrap; local search;
tabu search; machine qualifications; clustering; shortest processing time
1. Introduction
In complex production environments in the automotive industry, machine schedules have to be
calculated by taking into account frequently changing customer demands and potential failures or
unanticipated delays. The calculation of high quality schedules in such an environment is a challenge
because the scheduling problem itself usually has significant complexity, tight time restrictions are
given, and uncertainty occurs in various production parameters. Even by neglecting uncertainty,
the resulting optimization problems are NP-hard and can only be solved exactly with acceptable
computation times of some minutes for small and unrealistic configurations. More applicable solution
methods for practical problem instances are heuristics and metaheuristics, because they require less
computation time and allow one to approximate the optimal schedule with deterministic models,
even for larger configurations. However, the parameters of the model have to be set according to
the current situation. This means that data from the running production are used to define the
actual scheduling problem; a statistical evaluation of past data allows for the determination of safety
margins to compensate for scrap or unplanned demands. Before schedules, which were calculated
by deterministic optimization methods, should be applied to a production with its statistical effects,
they should be tested in stochastic simulation models.
The objective of this paper is to provide combined solutions to various problems at the
machine scheduling level for a real application example from a supplier in the automotive industry,
which describes a two-stage scheduling problem with parallel machines per stage with uncertainty in
several parameters. The system layout of the application case can be found in Figure 1. The production
includes 11 unrelated parallel machines in the first stage. In the second stage, there are two
identical parallel machines. The restrictions and characteristics of the basic scheduling problem
are machine qualifications, i.e., not every job can be produced on every machine, jobs might skip stages,
and the production data show several uncertainties in demands and different production parameters,
which need to be handled to provide usefully applicable schedules that perform in production with
as few makespans as possible. A composition of forecasting, classification, discrete event simulation,
metaheuristic, and heuristic algorithms is developed to identify demand fluctuations, including
scrap rates, and to approve schedules for their use in a production environment. So, in contrast
to common scheduling approaches, various problems at the machine scheduling level have to be
considered in combination. First, based on the available data of past orders, risky jobs that are prone
to fluctuations just before or during the production phase are identified by clustering algorithms and
corresponding demands are adjusted. Furthermore, the distributions of scrap rates are estimated,
and the quantiles of the resulting distribution are used to increase quantities of produced items to
avoid costly losses due to unfulfilled demands. Second, we show how deterministic methods solving
the described optimization problem are developed from the scheduling problem and how parameters
are derived from the available data. Third, a detailed simulation model of the production has been
built (see Figures 2 and 7) using the software AnyLogic 8.5 [1]. By means of simulation, it is possible
to evaluate and improve schedules before they are applied in a real production environment.
M1
M2
M3
M4 M12
M5
unlimited
storage
M6 M13
M7
M8
M9
M10
M11
Figure 1. System layout of the hybrid flow shop in the application case.
Algorithms 2020, 13, 277 3 of 26
The structure of the paper is as follows. In the next section, we present a detailed description of
the two-stage hybrid flow shop problem with its restrictions. Related work is summarized afterwards.
Section 4 introduces several metaheuristic and heuristic algorithms to compute schedules for the
hybrid flow shop problem. Afterwards, in Sections 5 and 6, the available data from the production are
described and methods are presented to estimate all parameters of the optimization problem and to
calculate the appropriate production volume from the data. Then in Section 7, a detailed analysis of
the schedules, using simulation and the structure of the simulation model, are introduced. In Section 8,
results of example runs are presented, evaluating makespans and order fulfilment as key indicators.
Our findings are summarized in the conclusions, which also outline some steps for future research.
7. Jobs do not need to be dispatched in the same order in all stages. Thus, no fix permutation is
considered.
8. There are infinite buffers in front, between and at the end of the two stages.
9. Processing times pilj of one product of job j are described by independent stochastic distributions
separated by machine, stage and job, i.e., machines are unrelated. Especially in the first stage,
processing times differ by machine (RM(1) ), in the second stage, they are machine-independent
(PM(2) ).
10. For setup times si , stochastic distributions over all machines and jobs per stage are available.
11. For scrap rates rij , job- and stage-related stochastic distributions are available for both stages.
Scrap parts are those parts which do not pass the quality check.
12. Available parts on stock stock ij are included to fulfill the demand.
13. The objective is to minimize the makespan Cmax , where Cmax is the maximum completion time
and Cij defines the completion time of a job j on stage i, where Cmax = max Cij .
i ∈ M,j∈ N
14. Order quantities of the job’s demandij underlie uncertainty and may change even during the
week when the job is produced, which results in varying production volumes productionvolumeij .
The needed processing time for one job is the productionvolumeij ∗ pilj .
According to Pinedo [5] and Ruiz and Vázquez-Rodríguez [6], this problem can be formalized
in the Graham et al. [4] notation as FH2, ( RM(1) , PM(2) ) | M j , skip | Cmax . In addition, several
uncertainties in the model parameters as listed above have to be included, which are not formalized in
Graham et al. [4] notation.
In addition, these other parameters of the Graham et al. [4] notation are needed in the
following sections:
• Ssd : sequence-dependent setup times
• avail: block times for machines
• rm: block times for machines at the start of the production time
• lag: overlapping or gaps between the processing of jobs in successive stages
• prec: priority relationships between jobs, i.e., one jobs needs to begin production before another
job can be started
Following Ruiz et al. [2] and to support a more homogeneous notation for machine scheduling
studies, the variables xiljk and x are introduced. With these variables, the schedules can be described
to their fullest extent with x = ( xiljk )i∈ M,l ∈ Mi ,j,k∈ N . The binary variable for the precedence relations
xiljk is defined as
(
1, if job j precedes job k on machine l at stage i,
xiljk :=
0, otherwise.
3. Related Work
A large number of papers on scheduling in hybrid flow shops are available. Overviews can
be found in Ruiz and Vázquez-Rodríguez [6], Ribas et al. [7], and Komaki et al. [8]. In the
following, a selected number of studies that deal with problems related to our problem (see Section 2)
are discussed.
Jabbarizadeh et al. [9] test three constructive heuristics for the problem FHM,
(( PM(k) )ck=1 ) | M j , Ssd , avail | Cmax . Based on Kurz and Askin [10], they assign the jobs in
the processing stages i > 1 in the order of completion times of the previous stage. They evaluate
that Shortest Processing Time (SPT) provides better results than Longest Processing Time (LPT).
Algorithms 2020, 13, 277 5 of 26
A heuristic based on the algorithm of Johnson [11] gave the best results in their study. In the field of
metaheuristics, a version of simulated annealing, which is a local search algorithm with the acceptance
of setbacks, outperforms a genetic algorithm. In each step, the position of a randomly selected job in
the first stage is changed. In the following processing steps, the jobs are dispatched according to the
Earliest Completion Times (ECT) using the completion times of the previous step.
Ruiz et al. [2] present a study dealing with an enormous number of realistic components
in the problem FHM, (( RM(k) )ck=1 ) | M j , Ssd , rm, lag, prec, skip | Cmax . Yet the study only
compares constructive heuristics and finds that NEH, a heuristic first published for flow shops by
Nawaz et al. [12], provides the best solutions.
Low et al. [13] compare for FH2, ( RM(1) , 1(2) ) | M j | Cmax sixteen combinations of heuristics.
They do not consider skipping stages. To form a production sequence for the first stage, Low et al. [13]
use the following methods: random sequence, SPT using processing times of the first stage, LPT using
process times of the second processing stage, and Johnson’s algorithm. Once the queue is created,
for each method, the jobs are assigned to the machines of the second processing stage with four
different rules. They find that the modified Johnson, rule by planning the second stage according to
the Earliest Completion Times (ECT) of the first stage, C1j performs best.
For FHM, (( PM(k) )ck=1 ) | Ssd , skip | Cmax Naderi et al. [14] conduct job sequencing and machine
assignment in the same step. All stages i are scheduled according to the Earliest Completion Times
(ECT) of the stage i itself and they take the arrival times at the stages into account, if i > 1, which result
from Ci−1j . In comparison to other constructive algorithms for their problem and for their test
data, this constructive algorithm gives the best results. The paper also uses Iterated Local Search,
which outperforms the other tested metaheuristics, like genetic algorithms, up to a number of
80 jobs. Since their problem takes sequence-dependent processing times into account, the problem in
combination with applying these algorithms corresponds to unrelated machine problems.
In Burdett and Kozan [15], several constructive heuristics are compared with simulated annealing
(SA) and a genetic algorithm (GA) for the computation of schedules for flow shops with non-unique
jobs. Again, SA and GA outperform constructive heuristics but GA does not, in general, do better than
SA. Burdett and Kozan [16] analyze flow shops with resource constraints where limited resources have
to be assigned and a schedule has to be computed simultaneously. They show that an evolutionary
algorithm gives good results for this class of scheduling problems. The models in the papers differ from
our models in several aspects, e.g., they do not consider machine qualification, stochastic demands
and scrap.
Dios et al. [17] compare 24 constructive heuristics for FHM, (( PM(k) )ck=1 ) | skip | Cmax and the
evaluation of their experiments shows that two SPT-based and one LPT-based heuristic generate the
best schedules according to Cmax . They do not take unrelated machines into account.
Logendran et al. [18] use tabu search for FFM, (( PM(k) )ck=1 ) | batch, skip | Cmax . Since the
study works with batch, the algorithm contains many details that cannot be used for this work.
Kaczmarczyk et al. [19] apply tabu search to FFM, (( PM(k) )ck=1 ) | block, skip | Cmax . For their
sequence of jobs, they swap two jobs in each iteration. The positions of the two exchanged jobs are
saved in the tabu list. To schedule the created sequence, the earliest available machine on every stage
is chosen for the job and the stages on which the job has to be produced.
De Siqueira et al. [3] modify a variable neighbourhood search of Geiger [20] for the problem
FHM, (( RM(k) )ck=1 ) | M j , skip | Cmax . To change the solutions, one of the six neighborhood
strategies is applied randomly:
Thus, no study provides local search and tabu search algorithms for the problem of our paper,
which is specified in Section 2. Furthermore, the above mentioned approaches are all based on a
fully parametrized deterministic model. One way to optimize stochastic models is the use of sample
average approximations, which are used by Almeder and Hartl [21] with variable neighborhood
search to optimize a two-stage flow shop problem describing a real world production process
in the metalworking industry. In contrast to our problem, the number of machines is smaller,
machine qualification and setup times are not required, and the behavior of orders seems to be
more homogeneous. In this case, production data are not used to determine model parameters.
Instead, the sampling averaging of simulation results is used to determine the parameters of the
optimization problem, which are analyzed with similar methods to the ones that we apply, but tabu
lists do not seem to be used.
Burdett and Kozan [22] studied buffering in the area of machine scheduling for a parallel machine
environment with one stage. They add idle times to the schedule, which depend on the variance of the
processing times of the jobs. Uncertainties regarding demand are taken into account by limiting the
number of jobs that can be produced in a given production period or by completely blocking resources
for unexpected demand. Their study differs from our study since the variance of the processing times
in our application case plays a minor role, whereas scrap rates have high influence on the demand.
In addition, we can use significant historical data of demand developments to adjust the demand
according to the articles through clustering.
Our approach is also related to approaches that combine simulation and optimization [23].
Regarding the different possibilities in this area to combine optimization and simulation, our study is
allocated in the category of first computing a schedule for a deterministic model, which is evaluated
afterwards in the detailed simulation model. In a further step, schedules can be enhanced based on the
simulation results. Juan et al. [24] introduced this technique as simheuristics.
In application scenarios, the model has to be built, i.e., parameters have to be estimated and
demands have to be forecasted. For parameter estimation and modeling from available data, standard
methods of input modeling, as summarized, for example, in Law [25], may be applied. Classification
of products according to their future demands is more demanding. Murray et al. [26] have examined
an application case of order classification in production planning, but they use k-means clustering in
order to group customers into segments. The main difference to the problem analyzed in this paper is
in the position in the supply chain. Customers are the first layer in a supply chain because they are
causing the demand for orders. The demand becomes more distorted and volatile when customers’
order quantities are planned through the different stages of the supply chain [27]. We consider a
problem which is more at the end of a supply chain, so the so-called bullwhip effect can be intense.
To forecast demands, regression or time series can be applied. There is no one method with an optimal
parameter set that is best to predict demand in different settings; instead, algorithms are developed to
select good parameters Kück and Scholz-Reiter [28] or to even select the optimal prediction method
together with the parameters, as carried out by Scholz-Reiter et al. [29]. According to our results and
in order to generate a robust schedule, it is sufficient to oversupply the demand for high-risk jobs,
which are identified by clustering algorithms.
Although we do not develop new optimization techniques, the originality of our study is that,
to the best of our knowledge, it combines the statistical analysis of production data with heuristic
and metaheuristic optimization methods to the specific problem of this paper and the subsequent
detailed simulation of a real production problem. The experiments give insights into the behavior of
different local search metaheuristics and indicate as expected that local search metaheuristics are able
to improve the makespan significantly compared to schedules resulting from simple heuristics like
SPT. Moreover, local search and tabu search metaheuristics to the best of our knowledge have not been
adapted to the specific problem of this paper in the literature before.
Algorithms 2020, 13, 277 7 of 26
4. Computation of Schedules
Taking the findings of Section 3 into account, we choose to apply SPT, local searches and tabu
searches, and ECT schedules the jobs for the basic model described in Section 2. We also apply
algorithms for the restriction of machine qualifications, skipping stages, and unrelated machines.
At first, the first stage is scheduled with one of the algorithms, which then is combined with ECT in
each case to schedule the second stage. Thus, we obtain Algorithms 1–4, which were already presented
in our conference paper Schumacher et al. [30].
To create an initial solution, we generate feasible schedules with SPT (Algorithm 1), which uses
ECT (Algorithm 2). With Algorithm 1, jobs are ordered according to their increasing average
processing times in stage 1 and after that they are scheduled successively to stage 1 on the machines,
which becomes available. When the scheduling of all jobs to stage 1 is finished, stage 2 is scheduled
with Algorithm 2 according the job completion times of stage 1.
1. Order jobs on stage 2 according to their completion times C1j . If a job is not processed
on stage 1, set C1j := 0. Of course, if a job should not be processed on stage 2, the job is
not in the sequence for stage 2. If two jobs have the same completion time C1j , order
these jobs alphanumerically. Save queue in PrioList.
2. Whenever a machine in stage 2 becomes available, select next unscheduled job j
of PrioList that is qualified for the given machine and schedule j on the available machine.
Based on this initial solution, six algorithms of Algorithms 3 and 4 optimize the solution. Both can
be computed with one of the variants “shift” or “swap”. With “shift”, one randomly selected job
in each iteration is positioned elsewhere in the existing schedule. In contrast, “swap” exchanges
the positions of two randomly selected jobs. After one of these moves and the consideration of the
eligibility restrictions for machines and stages, the resulting new schedule is compared with the old
schedule and checked for improvement by computing and comparing makespans. Random Descent
generates a new solution out of the existing one and if this solution performs better, regarding Cmax ,
the new solution is the starting point for the new testing of solutions. In contrast, Steepest Descent
first tests for one job j the solutions in the neighborhood of the current solution, which are created
by shifting or swapping that job to all the other machines that are eligible for that job. Furthermore,
Algorithm 4 can be executed with or without tabu list (tabu ∈ {true, f alse}). If tabu list is used,
the algorithms avoid testing a solution x again which has already been tested and is currently part
of the tabu list. So, the tabu list contains elements x, which have been tested before. If there is no
improvement in the makespan within a predefined amount of iterations, Algorithms 3 and 4 terminate.
By choosing all possible combinations of method ∈ {shi f t, swap} and tabu ∈ {true, f alse} in Algorithm
4, we have four variants of that algorithm. By computing the two possibilities method ∈ {shi f t, swap}
Algorithms 2020, 13, 277 8 of 26
in Algorithm 3, we have two further algorithms to evaluate. So, in total, with SPT, we get seven
different optimization algorithms for the basic model of Section 2.
(a) Duplicate xn := x.
(b) Randomly choose a job j on stage i = 1. For this job ∃!xilkj = 1. According
to xilkj = 1 define l and k.
(c) Randomly choose a machine ln ∈ Eij .
(d) if method = shi f t
x := xn , Cmax ( x ) := Cmax ( xn ).
termination := iterations.
else
termination := termination − 1.
(a) Duplicate xn := x.
(b) Initialize set S := {}.
for all jobs j on stage 1.
if method = shi f t
T = T ∪ S.
if | T | > t
Set termination := 0.
for all schedules xn ∈ S.
x := xn , Cmax ( x ) := Cmax ( xn ).
termination := iterations.
else
termination := termination − 1.
4. return x with Cmax ( x ).
Algorithms 2020, 13, 277 10 of 26
5. Parameter Uncertainty
All algorithms presented in the previous section are assumed to have full access to the information
about the problem. However, this is rarely found in practical scenarios. Usually, information about
a system includes uncertainty and some parameters like processing times underlie statistical fluctuation.
Some of the parameters can be described by statistical models like distributions or stochastic processes,
whereas for other parameters like machine breakdowns only very little information is available.
If uncertainty is modeled by stochastic distributions, a stochastic optimization problem can be
formulated; see Van Hentenryck and Bent [31]. The complexity of solving stochastic optimization
problems is higher than the complexity of solving the related deterministic models. For realistic
stochastic hybrid flow shop problems, even the analysis of a single configuration cannot be evaluated
analytically with exact methods. Instead, for optimization of such models, stochastic discrete event
simulation has to be coupled with metaheuristic optimization methods; see Juan et al. [32]. Stochastic
simulation needs a lot of computation time for function evaluation and metaheuristic optimization
methods often need numerous function evaluations. Therefore, the computation of nearly optimal
schedules and the evaluation with simulation in every iteration with a random initial schedule can
exceed available computation time in production planning of mostly only a few minutes. In order
to decrease the computation time, it is more efficient to compare different near-optimal schedules
from deterministic optimization models using a detailed simulation model. Furthermore, any model
approximates the real system, so that the best solution for the simulation model or deterministic model
is not automatically the best schedule for the real-world system. Finding a high-quality schedule
which is robust against small changes in the parameters or the description of the random variables is
more important.
In production systems, a large amount of data from business information systems are often
available. These data can be utilized to model uncertainty. We have to differentiate between internal
parameters of the production system on the one hand, like processing times, setup times, scrap rates,
and the availability of machines and external parameters, which are mainly described by the varying
demand, on the other. We begin with the internal parameters that, to some extent, are under the control
of the company and can be measured in the production system. This, of course, does not imply that
uncertainty can be deleted from the system but it is often possible to apply standard methods from
input modeling to generate a distribution that appropriately models the field data or to use the cleaned
data as an empirical distribution.
The availability and quality of production data vary considerably. In Table 1, we analyzed
scenarios where data are available in different levels of detail, and show how these data can be used
in deterministic and stochastic models. Another issue to consider are effects of outliers. Due to their
high values, it is more realistic for models to use the median instead of the mean for processing
times and setup times to compute more realistic schedules by using the deterministic optimization
model. In contrast, for scrap rates, it is recommended to use the mean value or some quantile to avoid
underproduction. If the needed data are available, the highest category of detail of Table 1 should be
used for the models. It is possible that job-related and machine-related distributions, even for machines
of the same type, like in our application case, differ significantly. Differences result from detailed
machine conditions even if machines are nearly identical. For example, in Figure 3, the processing
times of similar jobs on different machines of one type are presented.
Algorithms 2020, 13, 277 11 of 26
Mean value
M1
Machine
M2
M3
External uncertainty, which is part of the problem in this paper, caused by varying demands, is out
of the control of the producer. Future demands can be predicted based on historical data. In particular,
at the first levels of a longer supply chain, uncertainty in demands grow in volatility and amount
throughout the levels [27]. Figure 4 gives an example of demands over twelve weeks of one specific
job and the same production date from a supplier in the automotive industry. The value in the last
week in each time series shows the demand that has to be finally supplied to the customer. The other
observations illustrate the development of the previously mentioned amount from the customer for
the same date.
In the example of Figure 4, the demand grows in the last week considerably. Thus, if a schedule
has been computed with the data of one week in advance, the production will produce less than is
needed. Moreover, during the planned week itself, changes occur for high-risk jobs. Fluctuation in
demands is, of course, job specific and it is not necessary or possible to model every job in detail.
Hence, we first perform a cluster analysis based on historical data to distinguish between low, medium
and high-risk jobs. A high-risk job changes its demand often and significantly in the weeks before and
in the week of production, whereas for low-risk jobs, ordered quantities and final demand are very
similar. For high-risk jobs, we use over-provisioning to avoid situations where the demand cannot be
satisfied. The method is specified in the next section.
Algorithms 2020, 13, 277 12 of 26
• the probability that the demand of a job grows by 500 or more parts in the last week based on
historical data (emp_prob);
• the average increase in demand per job (only counted if the demands are increased)
(mean_pos_di f f );
• and the variance of the variation coefficient for the demands of the last three observations of the
previously ordered amount. (var_vark_last_3).
Following the elbow method, see Leskovec et al. [34], k-means should be applied for our
application case with four clusters. After analyzing the data, we computed the four clusters as
shown in Figure 5 and defined the jobs of cluster 3 and 4 (marked in light red in Figure 5) as high-risk
jobs. The demand for high-risk jobs is multiplied with job-related safety factors, namely SF2ij , where
1 ≥ SF2ij ≥ 2. The safety factor is used to keep the slot for the higher demand in the schedule
demandij −stock ij
reserved. Instead of only planning with the (1−rij )
for high-risk-articles, the production volume
demandij −stock ij
for risky jobs is extended in this first step to (1−rij )
· SF2ij , where SF2ij ≥ 1 for high-risk jobs j.
Algorithms 2020, 13, 277 13 of 26
The demands of non high-risk jobs are multiplied with SF2ij = 1. These considerations are also finally
included in Figure 6.
8
6
mean_pos_diff
4
2
0.00 0
var 0.05
_va 0.10
rk_ 0.15 0.8 1.0
las 0.20 0.4 0.6b
t_3 0.25 0.2 p ro
0.0 em p _
Figure 5. Clusters for identification of high-risk jobs (calculated with the method of [30]).
The same procedure of reserving slots for required higher amounts in the schedules can also
be applied to other non high-risk job demands, e.g., if products are sensitive about producing less
than the required demand. So, for these jobs, this method for overproduction compared to demandij
can be applied. The demands can be multiplied with another safety factor, namely SF1. This bears
the possibility to include the knowledge of experienced production planners, e.g., about sensitive
demands. A production planner may decide which value to use for the safety factor. At this point, it is
important to note that an earlier completion, which can be the cause of slots being reserved for too
long in the schedule, is easy to handle with our algorithms presented in Section 2. Such a schedule
causes, at most, only a slightly extended storage cost. In contrast, an unexpected longer slot for jobs
would result in drastic delays in the schedule and elaborate rescheduling. With this method, changes
in the demand and production quantities can be considered in optimization and simulation models
for scheduling.
To choose the appropriate scrap rate per job and stage for our application case, different quantile
values of the available empirical probability distribution per job and stage are considered. Figure 6
shows a histogram for the scrap rate of an exemplary job. For every job, we use the same quantile
value. Afterwards, per job, the scrap rates rij are computed as a function of the quantile value and the
probability distribution.
In practice, it is not realistic that the production volume productionvolumeij is completely
produced without failure. So, for every job, we have to increase the production volume to finally get
the demand that is to be produced. All analyzed factors influencing the demand in the production
process in our application case result in the following formula to calculate the appropriate production
quantity productionvolumeij :
demandij − stock ij
productionvolumeij = · SF1ij · SF2ij (1)
(1 − rij )
Algorithms 2020, 13, 277 14 of 26
Amount of observations
• In the first stage, there are two cranes and one crane needs to be used for every setup process
of a machine. The first crane can only reach a defined group of machines in the first stage and
the second crane can only reach the other machines. Therefore, the machines in the first stage
in the model are divided into two different groups and only two machines can be set up at the
same time if they do not belong to the same group, i.e., if they do not need the same crane for the
setup process.
• Produced products, which are transported by conveyors to a quality check station in the first
stage, can cumber each other. This can cause time losses in the production process.
• If there are not enough parts available from the first stage for producing the amount of the second
stage, the production volume of the second stage has to be reduced.
• To transport the products, which were produced at the first stage, to the second stage, they are
carried on small load carriers, where a certain number of produced parts fit in one small load
carrier and a certain number of small load carriers fits on one trolley, which transports the products
to the second stage. Both the packing and the logistics process flow between the two stages are
considered.
• Detailed modeling of the connection of logistics and production between the first and second
stages.
• Shift times: One of the two machines at the second stage does not produce at night and both
machines at stage two do not produce on weekends.
• There are four quality checking stations, where scrap parts are identified. All stations are modeled
in the simulation model with separate job-related distributions for scrap parts.
Algorithms 2020, 13, 277 15 of 26
Figure 7. Structure of simulation model for the application case of the paper in AnyLogic 8.5.
Algorithms 2020, 13, 277 16 of 26
Since the machine qualifications are already considered in the algorithms of Section 4,
an additional validation in the simulation model is not needed.
For an almost realistic analysis of a schedule, simulation has to be used. However, a simulation
run under realistic conditions is costly and should not be applied to evaluate clearly sub-optimal
schedules that appear during optimization. Thus, schedules are first generated by the algorithms
of Section 4 from the deterministic model and the best solutions from the deterministic model are
subsequently analyzed with simulation. In a simulative analysis, several replications are performed to
achieve confidence intervals of a predefined width for Cmax . The variance of the estimator for Cmax is
also an indicator of the robustness of the schedule; a small variance indicates a predictable behavior,
which is important in an industrial environment. Uncertainties resulting from scrap (see Section 5)
are analyzed by counting the number of runs where the required demand is produced and the runs
that fail to produce enough. The latter situation has to be avoided whenever possible in the given
case study.
8. Results
To select one of the schedules created by the seven algorithms, described in Section 4, that should
be applied in the application case and to select the most preferable algorithm for the application case
over a defined time horizon, we derive all the algorithms with the historical demands and process data
of the production. On the one hand, we evaluate the Cmax values for the algorithms. On the other hand,
we test different values for the quantile to reduce and evaluate the risk of producing less demands than
the customer order (Sections 5 and 6) and simulate the calculated schedules with our simulation model,
described in Section 7. For the evaluation of different security factor levels, e.g., for SFij , we refer to
Schumacher et al. [30].
The specific characteristics of the evaluation data for the application case are as follows: