Mixed-Use Project Development Process: Features, Pitfalls and Comparisons With Single-Use Projects
Mixed-Use Project Development Process: Features, Pitfalls and Comparisons With Single-Use Projects
¹ Assistant Professor, School of Civil and Environmental Engineering, Nanyang Technological University, Singapore
² Quantity Surveyor, Shimizu Corporation, Singapore
Correspond to [email protected]
ABSTRACT: In many urban cities, mixed-use development is becoming increasingly essential for the creation of an
attractive and sustainable environment that promotes economic vitality, social equity and environmental quality. Due to
the differences in scale, scope and intent, certain aspects within the project delivery process of mixed-use are not the
same as “conventional” single-use projects. The objective of this paper is to highlight these aspects. Two cases in
Southeast Asia serve to illustrate the uniqueness and challenges of mixed-use. In conclusion, the differences between
mixed-use and single-use are evident in terms of the diversity of team members, the necessity of multiple market
analyses, and a multi-layer (versus singlesource) financing structure. Finally, issues concerning ownership tangles, land
assembly, planning and application procedures, investment criteria of institutions have been identified as major pitfalls.
Phases of
Development Mixed-Use Development Single-Use Development
Process
Experienced and diverse project development Single experienced architect/project manager
team acting as project team leader
Involvement of public sector agencies crucial Relatively minor/routine involvement of public
Project Both financial and non-financial development sector agencies
Initiation objectives must be well defined Common and obvious development objectives
Analyzing multiple markets / development Analyzing only a specific market potential;
potential and evaluating the overall market there is little concern on synergy since it is
synergy meant for single-use
Necessity to define alternative development Independent development program and
programs and strategies strategy
Feasibility Complex feasibility analysis to define and Simple pro-forma analysis and economic
Studies optimize the development programs modeling
and Financing Necessity to securing large, multi-layer Single source of financing is possible and
financial commitment and structuring financial financial arrangement is straightforward
arrangements between project owner and bank
Complex planning and design issues
Conventional architectural and structural
involving
design process
urban considerations
Planning and Urban considerations play a more limited role
Creation of interrelationships among design
Design in overall project planning and design
elements and also between project and the
Involvement of specialists is less profound due
surrounding environment
to simplicity of design
Significant involvement of specialists
Multiple contractors working in different Usually single contractor who has sole control
Construction parcels/phases; interfacing is critical of planning and coordination of site works
Interaction with more specialists/designers Fewer number of architects/design engineers
More varied and innovative approaches on Marketing approaches targeting specific use
marketing strategies for numerous uses only
Marketing and
Long term promotion is necessary to continue More effort on promotion before project
Operational
building interests among general public completion and relatively less thereafter
Management
Centralized control management systems for Single responsibility for property management
multiple uses agency
7. PITFALL OF MIXED-USE political groundwork through community outreach
DEVELOPMENTS AND efforts. In addition, gaining the support of local
RECOMMENDATIONS TO OVERCOME government and creating clear lines of communication
with government agencies can substantially shorten the
7.1 Ownership Tangles entitlement process. This point is clearly demonstrated in
Mixed-use development often involves multiple owners the KLCC project. In view of the massive and fast-track
whose priorities regarding design, governance, and development program that the project developer KLCC
changes in use or ownership can be in conflict both Holdings had undertaken, the Kuala Lumpur City
during development and after the project is complete. Government decided to assist the project by providing
Reactive resolutions are time consuming, costly, and dedicated building plan inspection staff and facilities to
potentially fatal to the project. Although a mixed-use expedite approvals. Without such close interactions
project could have only one project developer, it would between the design team and the relevant statutory
still need to be structured for many different property bodies, initial phases of the project almost certainly
owners. It is necessary to organize project and legal would not have been completed as quickly as they were.
documentations for future changes based on each use.
Extra efforts are required upfront, but this is ultimately 7.4 Institutional Investors’ Criteria
the most cost-effective strategy. Shared physical Institutional investors are sometimes reluctant to invest
boundaries, as well as various common building systems in mixed-use schemes because they are perceived to offer
poor long-term investment prospects, and are typically
and amenities, make different components dependent on not large enough to generate the scale of profit sought by
one another for completion. In the long run, it usually is this type of investors. However, some developers have
better to create distinct systems, wherever possible, to successfully attracted investors by structuring multiple
avoid reliance on another owner. Nevertheless, even with investment opportunities into their projects for investors
distinct systems, it is desirable to have a single party that with different levels of investment horizons and return
handles one-stop development and management for all expectations. A project, for example, may offer modest
phases of the development. This would reduce returns to investor in the first few years, when the project
coordination time and multiple ownership complexities faces its greatest uncertainty, and increasing returns to
associated with having too many parties executing the middle and long-term investors as the property
master plan [6]. appreciates in value.
REFERENCES
[1] Flynn, L., “Developing a Winning Combination”,
Building Design and Construction, Vol. 44(3), pp. 26-32,
2003.
[2] Bell, J., “A Mixed-use Renaissance”, Mortgage
Banking, Vol. 5(8), pp. 66, 2004.
[3] Royal Institute of Chartered Surveyors, Mixed Use
Development: Concept and Realities, RICS Research,
1996.
[4] Schwanke, D., Mixed-Use Development Handbook,
Urban Land Institute, Washington, D.C., 1987.
[5] Royal Institute of Chartered Surveyors, Mixed Use
Development: Issues and Practice, RICS Research, 1998.
[6] Culp, L., “Mixed Results for Mixed-Use”, National
Real Estate Investor, Vol. 45(8), pp. 24, 2003.
[7] Bell, J., “Mixed-use Property Review E Pluribus
Unum: The Synergies of Mixed Use”, Midwest Real
Estate News, April, pp. 35-57, 2000.