0% found this document useful (0 votes)
183 views11 pages

Design of Lawrence Hargrave Drive Bridges

Darrell Meyers was the lead bridge designer for two curved bridges built along Lawrence Hargrave Drive between Clifton and Coalcliff in New South Wales, Australia. The bridges consisted of a 203m long, 7-span prestressed concrete incrementally launched bridge in the north and a 448m long, 5-span cast-in-situ balanced cantilever bridge in the south. The bridges required deep pile foundations, hollow concrete piers up to 26m tall, and variable-depth concrete box girder superstructures to carry the roadway up to 45m above the cliff face and sea level.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
183 views11 pages

Design of Lawrence Hargrave Drive Bridges

Darrell Meyers was the lead bridge designer for two curved bridges built along Lawrence Hargrave Drive between Clifton and Coalcliff in New South Wales, Australia. The bridges consisted of a 203m long, 7-span prestressed concrete incrementally launched bridge in the north and a 448m long, 5-span cast-in-situ balanced cantilever bridge in the south. The bridges required deep pile foundations, hollow concrete piers up to 26m tall, and variable-depth concrete box girder superstructures to carry the roadway up to 45m above the cliff face and sea level.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Design of Lawrence Hargrave Drive Bridges

Darrell Meyers Member Institute of Engineers Australian, Member International


Association for Bridge and Structural Engineering

Darrell Meyers is a Principal Engineer with Maunsell Australia and has over 17 years
experience in bridge design. His technical experience spans the majority of bridge
construction forms including precast segmental, balanced cantilever, incrementally
launched, precast girders, cast-insitu, steel boxes, trusses and cable stayed
structures.

Darrell was the lead bridge designer for the superstructure design of the balanced
cantilever bridge of the Lawrence Hargrave Drive Project. Darrell was also
responsible for the construction engineering and monitoring of balanced cantilever
and incremental launched bridges during the construction phase of the project.

Contact Details

Phone (02) 8295 3600


Fax (02) 9262 5060
Email [email protected]

c:\documents and settings\default\desktop\papers day 3\96 design and construction lhd cover page.doc
Design of Lawrence Hargrave Drive Bridges
Darrell Meyers, Principal Engineer, Maunsell Australia

SYNOPSIS

Over the last century Lawrence Hargrave Drive, between the costal townships of
Clifton and Coalcliff in New South Wales, has been plagued by rock falls and
landslips. After a thorough investigation of options the final solution developed by the
Alliance Team (RTA, Barclay Mowlem, Maunsell and Coffey) was to move the road
away from the cliff face. This solution involved the design and construction of two
back to back curved bridges, rockface stabilisation, retaining walls and road
widening. The northern bridge consists of a 7 span 203m long prestressed double
tee incrementally launched bridge. The southern bridge consists of a 5 span 448m
long cast in-situ balanced cantilever bridge. The bridges carry two traffic lanes and a
walkway up to 45m off the cliff face and up to 40m above the sea level. The project
was completed in 24 months and opened to traffic three months ahead of schedule.
The solution that was developed and refined by the Alliance team has demonstrated
how the Alliance process can be utilised to obtain an optimum cost effective
engineering solution. This paper highlights the design features of the curved
incrementally launched and balanced cantilever bridges.

Figure 1 – Lawrence Hargrave Drive Bridges

Design of Lawrence Hargrave Drive Bridges Page 1 of 10


1. BALANCED CANTILEVER BRIDGE

1.1 General

The 448m long balanced cantilever bridge consists of three 108m internal spans and
62m back spans. At the southern end of the bridge, the superstructure is supported
by a spread footing abutment perched on the cliff face, at the northern end the
superstructure is supported by the common pier with the incrementally launched
bridge.

The superstructure consists of a single cell 6m wide box girder supporting a 13m
wide deck slab. The depth of the box girder varies parabolically from 6m at the pier
to 2.5m at midspan. The hollow 6.0m x 2.8m piers are up to 26m tall and are
supported on six 1500mm diameter bored piles. The superstructure is integral with
the piers and supported by twin sliding pot bearings at the abutments and the
common pier.

FROM CLIFTON TO COALCLIFF


OVERALL LENGTH OF DECK ON BRIDGE C
L = 449591

62000 108000 108000 108000 61216 BRIDGE GD3


CROSSFALL
GRADE 2.531% TRANSITION

SEA LEVEL SEA LEVEL


SOUTH ABUT

RL 0.00 RL 0.00
L BEARINGS

L PIER D

L PIER C

L PIER B

L PIER 7
EXISTING SURFACE

CL PIER A
LEVEL

SPAN 1 SPAN 2 SPAN 3 SPAN 4 SPAN 5


C

C
C

Figure 2 – General Arrangement of Balanced Cantilever Bridge

Design of Lawrence Hargrave Drive Bridges Page 2 of 10


1.2 Geometry Considerations

The horizontal geometry for the bridge was determined from a combination of
accessible pier locations on the rock platforms, road geometry requirements and
rockfall clearances. The resulting horizontal geometry from south to north consists of
a 500m radius right hand curve reducing to a 350m radius followed by a transition
into the reverse 150m radius curve of the incrementally launched bridge.

Vertically the bridge is on a constant 2.5% longitudinal grade. The super elevation is
a constant 3% through the curved spans and transitions in span 5 to the match the
reverse crossfall of the incrementally launched bridge.

1.3 Design Criteria

The design criteria for the balanced cantilever bridge is framed on the provision of
the Austroads Bridge Design Code with the following modifications
• Design Load – T44 no HLP
• Shear and Torsion design – AASHTO LRFD Bridge Design and Construction
Specifications 2004
• Allowable tensile stresses in the piers during cantilevering – Eurocode
• Load factors during cantilevering – AASHTO LRFD Bridge Design and
Construction Specifications 2004

2. DESIGN FEATURES

2.1 Foundations

The foundations for the piers consists of six 1500mm diameter 15m long bored piles.
The piles are socketed into class 3 sandstone and class 2 shales beneath the coal
seam and required casing for construction. The piles support a 8.5x7.5x2.5m
reinforced concrete pilecap. The reinforcement in the piles, pilecaps and piers are
connected to the cathodic prevention system.

Providing access for the construction of the foundations was a major construction
achievement, requiring the construction of an access road down the cliff face and
along the shore line to the pier locations. During high seas, waves would break over
the access road preventing construction.

2.2 Piers

The hollow rectangular piers measure 6.0m wide x 2.8m deep with a constant wall
thickness of 0.5m. The piers vary in height from 21m to 26m. The wall thickness
adopted took into consideration, cover requirements, reinforcement congestion, and
concrete placement and compaction methods.

The 6m width of the pier was adopted to match the width of the box girder. The
2.8m depth of the pier was a compromise between the conflicting stiffness
requirements for the cantilever construction method and the flexibility required for the
completed in service design.

Design of Lawrence Hargrave Drive Bridges Page 3 of 10


For the cantilever construction, the design criteria was to limit the tensile stresses in
the pier concrete below two thirds of the flexural tensile strength of the concrete.
This would prevent cracking of the pier concrete during construction to improve
durability and provide better control over pier and cantilever deflections. To limit the
tensile stresses below the design criteria limit a 3.2m deep pier section was required.
However this would have resulted in a pier section that was too stiff to accommodate
long term creep and shrinkage movements of the bridge, resulting in large moments
in the piers and high forces being transferred to the pier foundations. To
accommodate the creep and shrinkage movements a pier depth of 2.4m was
required to provide the required flexibility and minimise the forces transferred to the
foundations.

The compromise solution was a 2.8m deep pier section. To limit the tensile stresses
in the piers during cantilever construction 52 tonnes of kentledge was used to
counter balance the leading cantilever. To limit the moments in the piers and the
forces transferred to the foundations, the tips of the cantilevers in span 3 (mid bridge
final closure) were jacked apart 60mm to compensate for some of the predicted
creep and shrinkage movements. The details of the midspan jacking are provided in
section 2.4.

2.3 Superstructure

The superstructure consists of a variable depth box girders illustrated in figure 3. The
box girder was designed using the provisions of the Austroads Bridge Design Code
for moment design and AASHTO for shear and torsion design.

The web thickness varied from 400 near the pier to 300 for the typical internal
segments. Careful consideration was given to the detailing of the reinforcement to
accommodate construction tolerances and placement requirements. Variable lap
hooked bars were used in the webs to accommodate the constantly changing depth
of the box. A shear key joint was used for the construction joint between the
segments.
CONTROL
LINE
13175

775
1000
3500 3500 1000 530 2500 320
1285 50
DOUBLE
RAIL
BARRIER
3%
VARIES
2500 -
6000

SPRAYED
BM/DGA
SURFACING
75mm THK.
C
L BRIDGE

6000

Figure 3 – Cross Section of Balanced Cantilever Bridge at Midspan

Design of Lawrence Hargrave Drive Bridges Page 4 of 10


2.4 Closure Pours

The five closures pours were constructed using different methods depending on
design, construction and program requirements. The closure pours were constructed
in the following order, span 2,1,4,5 & 3.

The span 2 closure pour was not on the critical path, however releasing the travellers
for piers A & B cantilever construction was critical. Therefore it was not viable to use
the travellers for the first closure and a custom suspended form was developed. The
system consisted of a pair of strong back beams to align and clamp the cantilevers
and support the exterior formwork shell.

The traditional method to construct the backspan (span 1) closure is to support the
abutment segments on falsework and stitch the cantilever to these segments. Due to
the unstable cliff face it was not practical to erect falsework for the construction of the
abutment segments. Therefore a system to construct the segments supported off the
cantilever was developed. The system utilised the strong back beams and exterior
formwork shell developed for the span 2 closure to create a mini half segment
traveller.

Figure 4 – Southern Abutment Closure Falsework

The span 4 closure was constructed using the southern pier A traveller with the
traveller rail beams being used for aligning and clamping of the cantilevers. Due to
the limited capacity of the traveller beams, kentledge and control of loads and
construction activities in the opposing travellers was critical and required careful
management.

Design of Lawrence Hargrave Drive Bridges Page 5 of 10


The span 5 closure used a combination of the strong back beams, suspended forms
and the pier A traveller. The construction sequence for the pier 5 closure was as
follows

a) The diaphragm segment was constructed over the permanent bearings


(50mm below final design position ref section 2.5) using the suspended
formwork system with the strong back beams fixed to the end span of the
incrementally launched bridge.
b) The diaphragm segment was temporarily stressed to the end of the
incrementally launched bridge using temporary stress bars creating a moment
connection off the end of the incrementally launched bridge.
c) The strong back beams were repositioned to support the suspended forms for
segment A13 and the segment was cast
d) Segment A11 was cast using the traveller off the cantilever after the span 4
closure was completed
e) The traveller was then launched into position for the A12 closure segment and
kentledge was added to the cantilever
f) The traveller rail beams were launched across the A12 closure segment and
stressed down just prior to commencing the concrete pour to minimise the
forces in the traveller rail beams due to thermal variations. The segment was
poured late in the evening when the temperatures had stabilised. Due to the
limited strength and stiffness of the traveller beams it was necessary to
progressively remove the kentledge on the cantilever as the closure segment
was cast to avoid overstressing the traveller rail beams
g) The following morning the continuity prestress was stressed and the
connection to the incrementally launched bridge was released. The
remaining continuity tendons were stressed as the closure segment concrete
gained strength. Finally the diaphragm segment was jacked into its final
position and the bearings grouted.

CL PIER 7
STRONGBACK
BEAMS

HARDWOOD
PACKERS

REAR
BALANCED CANTILEVER TIEDOWN
BRIDGE

INCREMENTALLY LAUNCHED BRIDGE


TEMPORARY
STRESSBARS

TEMPORARY
PACKERS
A13N A14N
SUSPENDED TEMPORARY
FORMS PACKERS

Figure 5 – Details of Falsework for Segment A13

Design of Lawrence Hargrave Drive Bridges Page 6 of 10


The final span 3 closure involved the jacking apart of the two halves of the bridge
prior to casting the final closure segment. A number of options were investigated for
the midspan jacking. The initial option was to jack in the four corners of the box
section and bury the struts into the section, similar to the approach used on Mooney
Mooney Bridge. However the webs were not thick enough to accommodate the
required strut dimensions, reinforcement and cover. Other options considered using
corbels or brackets to support the struts external to the box section.

The final solution involved jacking off the top flange in the middle of the box. Rather
than trying to cast the struts into the thin top flange, a blockout was left around the
struts. Once the closure segment was cast, the struts were removed, the continuity
tendons were stressed and the blockout completed.

2.5 Vertical Jacking

The construction method for casting the backspan closure segments resulted in, the
majority of the self weight of the closures segments being taken by the cantilever.
Therefore, insufficient permanent load was on the bearings to prevent uplift under
certain load combinations. To overcome the problem, the ends of the cantilevers
were built 50mm low and after completion of the backspan, the diaphragm segment
was jacked vertically into its final position and the bearings grouted. Relaxation of
the induced bearing reaction due to the effects of creep was considered in
determining the amount of jacking required. Other options such as filling the box with
mass concrete were considered but found to be uneconomical.

2.6 Provision for Travellers

The 75 tonne ‘NRC’ travellers were purchased second hand from overseas. The
concept development of the box cross section was based on the geometry of the
travellers, to minimise the amount of modifications required. The Contractors
engineers modified the travellers to simplify the hold down arrangement and
minimise the number of deck penetrations. The travellers were also upgraded to
meet Australian safety requirements. The top and bottom tendons layouts were
arranged to avoid the traveller penetration requirements.

The pier heads were sized to suit the minimum back to back traveller configuration
with the rear frames overlapping and braced together. After the completion of the
first segments the cross bracing between the travellers was released, the travellers
launched and the rear frames installed for independent operation. The typical
segments were 4.95m long with weight varying from 80 to 150 tonnes.

Design of Lawrence Hargrave Drive Bridges Page 7 of 10


3. INCREMENTALLY LAUNCHED BRIDGE

3.1 General

The incrementally launched bridge consists of a 7 span, 203m long double tee post
tensioned cross section. The 13.8m wide deck is constructed on a tight 150m radius.
The 6m x 1.7m piers range in height from 8.1m to 20.4m. The shorter piers (piers 1 &
2) are solid and the taller piers are hollow with a constant 0.5m wall thickness. The
piers are supported on bored piles or spread footings. The 1050 diameter piles
ranged in length from 9 to 17m and are socketed into class 3 sandstone. Due to
topography and access constraints, asymmetric pile arrangements were required to
support the piers.
FROM CLIFTON
TO COALCLIFF

GD2 OVERALL LENGTH ON C.L. 202831

6 x 30000 = 180000 22831

C
L PIER 7 C
L PIER 6 C
L PIER 5 C
L PIER 4 C
L PIER 3 C PIER 2 C PIER 1 C
L NORTH
ABUTMENT
2.531%

EXISTING
SURFACE
LEVEL

SPAN 6 SPAN 7 SPAN 8 SPAN 9 SPAN 10 SPAN 11 SPAN 12

Figure 6 – Elevation of Incrementally Launched Bridge


13775

SPRAYED
SPRAYED BM/DGA BM/DGA
SURFACING 75 THK. SURFACING 75
C
L BRIDGE THK.
LEVEL 2. 775 1000 3800 3800 1000 530 2500 370
DOUBLE RAIL TRAFFIC LANE TRAFFIC LANE
CONTROL

HANDRAIL
BARRIER
LINE

1285
3% FALL
250

CHAMFERS
2500

1000x200
2500

3665 3000 3000 3745

13410

Figure 7 – Cross Section of Incrementally Launched Bridge

3.2 Design Criteria

The design criteria for the incrementally launched bridge was based on the
provisions of Austroads Bridge Design Code with T44 only loading. The design
assumptions for launching included

• 10% friction in the casting yard with the segments cast on slip foil
• 2-4% friction for launch bearings (lubricated PTFE over stainless steel)
• 50-70% friction between the gripper plates and the concrete

The range of friction values required calculations of upper and lower bound solutions
to ensure adequate jacking and braking capacity was provided for launching.

Design of Lawrence Hargrave Drive Bridges Page 8 of 10


3.3 Geometry Considerations

The geometry of the incrementally launched bridge was determined by road design
criteria, construction requirements, topography, rockfall and aesthetic considerations.

The 2.5m depth of the section was chosen to match the depth of the balanced
cantilever at the common pier. The outer faces of the beams were spaced to match
the width of the balanced cantilever bridge. These two considerations provided a
smooth transition between the two bridges.

The depth of the section and the available area for the casting yard determined the
maximum spacing of the piers. The topography and rockfall clearances provided the
positions for the piers and the incremental construction method required a constant
radius and constant longitudinal gradient. Sight widening requirements for the 150m
design radius determined the width of the bridge. A constant 3% superelevation was
provided with the superelevation rollover provided in span 5 of the balanced
cantilever bridge.

3.4 Launching

Two Eberspacher jacks were used to launch the bridge. The jacks consist of a
vertical ram to lift and engage the structure mass and a thrust ram to push the
structure. The typical cycle for the launching was

• lift the structure 10mm off the braking saddle with the vertical ram
• push the structure forward 300mm with the thrust ram
• lower the structure down on to the braking saddle
• return the jack and repeat the cycle

The launching process relies on the friction generated between the soffit of the
girders and the gripper plate of the vertical jack. The friction force in turn is a function
of the dead load reaction of the structure over the launch jack. Generally sufficient
friction can be generated to push the structure, with exceptions being the initial and
final launch stages where the dead load reaction over the launch jacks from the
structure is minimal. For these situations the structure has to be pulled using
stressbars attached to the structure and the launch jack.

Figure 8 – Stored Energy in Bearings Fig 9 – Pulling Brackets Final Launch

Design of Lawrence Hargrave Drive Bridges Page 9 of 10


For the final launch stage the reaction on the braking saddle also needs to be
monitored to ensure sufficient friction is generated to prevent the structure from
sliding back down the gradient due to the combined effects of gravity and the stored
energy in the deflected piers and elastomeric bearings. During the final launch, when
the pulling rods were being used, the bridge deck was back launched 50mm after the
forward stroke to release the stored energy in the piers and elastomeric bearings, to
ensure the friction generated by the braking saddle was adequate to hold the
structure.

The measured launch bearing friction co-efficient was in the range of 2.4 to 3.0%.

3.5 Prestress

The prestress arrangement for the double tee cross section consisted of straight top
and bottom tendons. The prestress was installed and stressed in the casting yard
with no additional continuity prestress required. To minimise congestion and the
number of couplers required, 50% of the tendons were anchored at each segment
construction joint. The typical prestress for the internal span consisted of two 19
strand tendons in the bottom and four 19 strand tendons in the top of each tee
section.

4. CONCLUSION

The design of the twin bridges of the Lawrence Hargrave Drive Project utilised the
skills and experience of all members of the Alliance Team. The final solution, two
curved back to back bridges provided a solution to the century old rockfall problem
that has plagued this section of Lawrence Hargrave Drive between Clifton and
Coalcliff.

This paper has highlighted some of the design features and the rationale behind the
solutions adopted for the key elements of the curved balanced cantilever and
incrementally launched bridges of the project.

Figure 10 – Lawrence Hargrave Drive Looking North

Design of Lawrence Hargrave Drive Bridges Page 10 of 10

You might also like