Design of Lawrence Hargrave Drive Bridges
Design of Lawrence Hargrave Drive Bridges
Darrell Meyers is a Principal Engineer with Maunsell Australia and has over 17 years
experience in bridge design. His technical experience spans the majority of bridge
construction forms including precast segmental, balanced cantilever, incrementally
launched, precast girders, cast-insitu, steel boxes, trusses and cable stayed
structures.
Darrell was the lead bridge designer for the superstructure design of the balanced
cantilever bridge of the Lawrence Hargrave Drive Project. Darrell was also
responsible for the construction engineering and monitoring of balanced cantilever
and incremental launched bridges during the construction phase of the project.
Contact Details
c:\documents and settings\default\desktop\papers day 3\96 design and construction lhd cover page.doc
Design of Lawrence Hargrave Drive Bridges
Darrell Meyers, Principal Engineer, Maunsell Australia
SYNOPSIS
Over the last century Lawrence Hargrave Drive, between the costal townships of
Clifton and Coalcliff in New South Wales, has been plagued by rock falls and
landslips. After a thorough investigation of options the final solution developed by the
Alliance Team (RTA, Barclay Mowlem, Maunsell and Coffey) was to move the road
away from the cliff face. This solution involved the design and construction of two
back to back curved bridges, rockface stabilisation, retaining walls and road
widening. The northern bridge consists of a 7 span 203m long prestressed double
tee incrementally launched bridge. The southern bridge consists of a 5 span 448m
long cast in-situ balanced cantilever bridge. The bridges carry two traffic lanes and a
walkway up to 45m off the cliff face and up to 40m above the sea level. The project
was completed in 24 months and opened to traffic three months ahead of schedule.
The solution that was developed and refined by the Alliance team has demonstrated
how the Alliance process can be utilised to obtain an optimum cost effective
engineering solution. This paper highlights the design features of the curved
incrementally launched and balanced cantilever bridges.
1.1 General
The 448m long balanced cantilever bridge consists of three 108m internal spans and
62m back spans. At the southern end of the bridge, the superstructure is supported
by a spread footing abutment perched on the cliff face, at the northern end the
superstructure is supported by the common pier with the incrementally launched
bridge.
The superstructure consists of a single cell 6m wide box girder supporting a 13m
wide deck slab. The depth of the box girder varies parabolically from 6m at the pier
to 2.5m at midspan. The hollow 6.0m x 2.8m piers are up to 26m tall and are
supported on six 1500mm diameter bored piles. The superstructure is integral with
the piers and supported by twin sliding pot bearings at the abutments and the
common pier.
RL 0.00 RL 0.00
L BEARINGS
L PIER D
L PIER C
L PIER B
L PIER 7
EXISTING SURFACE
CL PIER A
LEVEL
C
C
The horizontal geometry for the bridge was determined from a combination of
accessible pier locations on the rock platforms, road geometry requirements and
rockfall clearances. The resulting horizontal geometry from south to north consists of
a 500m radius right hand curve reducing to a 350m radius followed by a transition
into the reverse 150m radius curve of the incrementally launched bridge.
Vertically the bridge is on a constant 2.5% longitudinal grade. The super elevation is
a constant 3% through the curved spans and transitions in span 5 to the match the
reverse crossfall of the incrementally launched bridge.
The design criteria for the balanced cantilever bridge is framed on the provision of
the Austroads Bridge Design Code with the following modifications
• Design Load – T44 no HLP
• Shear and Torsion design – AASHTO LRFD Bridge Design and Construction
Specifications 2004
• Allowable tensile stresses in the piers during cantilevering – Eurocode
• Load factors during cantilevering – AASHTO LRFD Bridge Design and
Construction Specifications 2004
2. DESIGN FEATURES
2.1 Foundations
The foundations for the piers consists of six 1500mm diameter 15m long bored piles.
The piles are socketed into class 3 sandstone and class 2 shales beneath the coal
seam and required casing for construction. The piles support a 8.5x7.5x2.5m
reinforced concrete pilecap. The reinforcement in the piles, pilecaps and piers are
connected to the cathodic prevention system.
Providing access for the construction of the foundations was a major construction
achievement, requiring the construction of an access road down the cliff face and
along the shore line to the pier locations. During high seas, waves would break over
the access road preventing construction.
2.2 Piers
The hollow rectangular piers measure 6.0m wide x 2.8m deep with a constant wall
thickness of 0.5m. The piers vary in height from 21m to 26m. The wall thickness
adopted took into consideration, cover requirements, reinforcement congestion, and
concrete placement and compaction methods.
The 6m width of the pier was adopted to match the width of the box girder. The
2.8m depth of the pier was a compromise between the conflicting stiffness
requirements for the cantilever construction method and the flexibility required for the
completed in service design.
The compromise solution was a 2.8m deep pier section. To limit the tensile stresses
in the piers during cantilever construction 52 tonnes of kentledge was used to
counter balance the leading cantilever. To limit the moments in the piers and the
forces transferred to the foundations, the tips of the cantilevers in span 3 (mid bridge
final closure) were jacked apart 60mm to compensate for some of the predicted
creep and shrinkage movements. The details of the midspan jacking are provided in
section 2.4.
2.3 Superstructure
The superstructure consists of a variable depth box girders illustrated in figure 3. The
box girder was designed using the provisions of the Austroads Bridge Design Code
for moment design and AASHTO for shear and torsion design.
The web thickness varied from 400 near the pier to 300 for the typical internal
segments. Careful consideration was given to the detailing of the reinforcement to
accommodate construction tolerances and placement requirements. Variable lap
hooked bars were used in the webs to accommodate the constantly changing depth
of the box. A shear key joint was used for the construction joint between the
segments.
CONTROL
LINE
13175
775
1000
3500 3500 1000 530 2500 320
1285 50
DOUBLE
RAIL
BARRIER
3%
VARIES
2500 -
6000
SPRAYED
BM/DGA
SURFACING
75mm THK.
C
L BRIDGE
6000
The five closures pours were constructed using different methods depending on
design, construction and program requirements. The closure pours were constructed
in the following order, span 2,1,4,5 & 3.
The span 2 closure pour was not on the critical path, however releasing the travellers
for piers A & B cantilever construction was critical. Therefore it was not viable to use
the travellers for the first closure and a custom suspended form was developed. The
system consisted of a pair of strong back beams to align and clamp the cantilevers
and support the exterior formwork shell.
The traditional method to construct the backspan (span 1) closure is to support the
abutment segments on falsework and stitch the cantilever to these segments. Due to
the unstable cliff face it was not practical to erect falsework for the construction of the
abutment segments. Therefore a system to construct the segments supported off the
cantilever was developed. The system utilised the strong back beams and exterior
formwork shell developed for the span 2 closure to create a mini half segment
traveller.
The span 4 closure was constructed using the southern pier A traveller with the
traveller rail beams being used for aligning and clamping of the cantilevers. Due to
the limited capacity of the traveller beams, kentledge and control of loads and
construction activities in the opposing travellers was critical and required careful
management.
CL PIER 7
STRONGBACK
BEAMS
HARDWOOD
PACKERS
REAR
BALANCED CANTILEVER TIEDOWN
BRIDGE
TEMPORARY
PACKERS
A13N A14N
SUSPENDED TEMPORARY
FORMS PACKERS
The final solution involved jacking off the top flange in the middle of the box. Rather
than trying to cast the struts into the thin top flange, a blockout was left around the
struts. Once the closure segment was cast, the struts were removed, the continuity
tendons were stressed and the blockout completed.
The construction method for casting the backspan closure segments resulted in, the
majority of the self weight of the closures segments being taken by the cantilever.
Therefore, insufficient permanent load was on the bearings to prevent uplift under
certain load combinations. To overcome the problem, the ends of the cantilevers
were built 50mm low and after completion of the backspan, the diaphragm segment
was jacked vertically into its final position and the bearings grouted. Relaxation of
the induced bearing reaction due to the effects of creep was considered in
determining the amount of jacking required. Other options such as filling the box with
mass concrete were considered but found to be uneconomical.
The 75 tonne ‘NRC’ travellers were purchased second hand from overseas. The
concept development of the box cross section was based on the geometry of the
travellers, to minimise the amount of modifications required. The Contractors
engineers modified the travellers to simplify the hold down arrangement and
minimise the number of deck penetrations. The travellers were also upgraded to
meet Australian safety requirements. The top and bottom tendons layouts were
arranged to avoid the traveller penetration requirements.
The pier heads were sized to suit the minimum back to back traveller configuration
with the rear frames overlapping and braced together. After the completion of the
first segments the cross bracing between the travellers was released, the travellers
launched and the rear frames installed for independent operation. The typical
segments were 4.95m long with weight varying from 80 to 150 tonnes.
3.1 General
The incrementally launched bridge consists of a 7 span, 203m long double tee post
tensioned cross section. The 13.8m wide deck is constructed on a tight 150m radius.
The 6m x 1.7m piers range in height from 8.1m to 20.4m. The shorter piers (piers 1 &
2) are solid and the taller piers are hollow with a constant 0.5m wall thickness. The
piers are supported on bored piles or spread footings. The 1050 diameter piles
ranged in length from 9 to 17m and are socketed into class 3 sandstone. Due to
topography and access constraints, asymmetric pile arrangements were required to
support the piers.
FROM CLIFTON
TO COALCLIFF
C
L PIER 7 C
L PIER 6 C
L PIER 5 C
L PIER 4 C
L PIER 3 C PIER 2 C PIER 1 C
L NORTH
ABUTMENT
2.531%
EXISTING
SURFACE
LEVEL
SPRAYED
SPRAYED BM/DGA BM/DGA
SURFACING 75 THK. SURFACING 75
C
L BRIDGE THK.
LEVEL 2. 775 1000 3800 3800 1000 530 2500 370
DOUBLE RAIL TRAFFIC LANE TRAFFIC LANE
CONTROL
HANDRAIL
BARRIER
LINE
1285
3% FALL
250
CHAMFERS
2500
1000x200
2500
13410
The design criteria for the incrementally launched bridge was based on the
provisions of Austroads Bridge Design Code with T44 only loading. The design
assumptions for launching included
• 10% friction in the casting yard with the segments cast on slip foil
• 2-4% friction for launch bearings (lubricated PTFE over stainless steel)
• 50-70% friction between the gripper plates and the concrete
The range of friction values required calculations of upper and lower bound solutions
to ensure adequate jacking and braking capacity was provided for launching.
The geometry of the incrementally launched bridge was determined by road design
criteria, construction requirements, topography, rockfall and aesthetic considerations.
The 2.5m depth of the section was chosen to match the depth of the balanced
cantilever at the common pier. The outer faces of the beams were spaced to match
the width of the balanced cantilever bridge. These two considerations provided a
smooth transition between the two bridges.
The depth of the section and the available area for the casting yard determined the
maximum spacing of the piers. The topography and rockfall clearances provided the
positions for the piers and the incremental construction method required a constant
radius and constant longitudinal gradient. Sight widening requirements for the 150m
design radius determined the width of the bridge. A constant 3% superelevation was
provided with the superelevation rollover provided in span 5 of the balanced
cantilever bridge.
3.4 Launching
Two Eberspacher jacks were used to launch the bridge. The jacks consist of a
vertical ram to lift and engage the structure mass and a thrust ram to push the
structure. The typical cycle for the launching was
• lift the structure 10mm off the braking saddle with the vertical ram
• push the structure forward 300mm with the thrust ram
• lower the structure down on to the braking saddle
• return the jack and repeat the cycle
The launching process relies on the friction generated between the soffit of the
girders and the gripper plate of the vertical jack. The friction force in turn is a function
of the dead load reaction of the structure over the launch jack. Generally sufficient
friction can be generated to push the structure, with exceptions being the initial and
final launch stages where the dead load reaction over the launch jacks from the
structure is minimal. For these situations the structure has to be pulled using
stressbars attached to the structure and the launch jack.
The measured launch bearing friction co-efficient was in the range of 2.4 to 3.0%.
3.5 Prestress
The prestress arrangement for the double tee cross section consisted of straight top
and bottom tendons. The prestress was installed and stressed in the casting yard
with no additional continuity prestress required. To minimise congestion and the
number of couplers required, 50% of the tendons were anchored at each segment
construction joint. The typical prestress for the internal span consisted of two 19
strand tendons in the bottom and four 19 strand tendons in the top of each tee
section.
4. CONCLUSION
The design of the twin bridges of the Lawrence Hargrave Drive Project utilised the
skills and experience of all members of the Alliance Team. The final solution, two
curved back to back bridges provided a solution to the century old rockfall problem
that has plagued this section of Lawrence Hargrave Drive between Clifton and
Coalcliff.
This paper has highlighted some of the design features and the rationale behind the
solutions adopted for the key elements of the curved balanced cantilever and
incrementally launched bridges of the project.