Project III Notes
Project III Notes
BE in Structural Engineering
Preliminary Design of Building Structures
2007/8
1 Dr C. Caprani
BE Structural Eng – Project III
Contents
1. Introduction ......................................................................................................... 5
1.1 Course Outline ................................................................................................. 5
1.2 Syllabus............................................................................................................ 8
1.3 Programme....................................................................................................... 9
1.4 Studying......................................................................................................... 10
1.5 General Report Advice .................................................................................. 12
1.6 Report Requirements ..................................................................................... 14
1.7 Reading Material ........................................................................................... 16
1.8 Some Introductory Problems ......................................................................... 18
2. Overall Structural Behavior............................................................................. 19
2.1 Primary function of a structure...................................................................... 19
2.2 Structural Members ....................................................................................... 24
2.3 Structural Systems ......................................................................................... 28
2.4 Stability of Buildings..................................................................................... 40
2.5 Allowing for Movement ................................................................................ 53
3. Structural Materials and Structural Form..................................................... 63
3.1 Choice of Structural Material ........................................................................ 64
3.2 Choice of Structural Form ............................................................................. 74
4. Precedence Studies ............................................................................................ 78
4.1 Introduction.................................................................................................... 78
4.2 Dulles Airport ................................................................................................ 79
4.3 Alamillo Bridge ............................................................................................. 80
4.4 Patera Building System ................................................................................. 81
4.5 Sydney Opera House – Podium..................................................................... 83
4.6 Sydney Opera House – General .................................................................... 84
4.7 Robert Maillart – Beam Bridge ..................................................................... 85
4.8 Pompidou – Lateral Stability......................................................................... 86
2 Dr C. Caprani
BE Structural Eng – Project III
3 Dr C. Caprani
BE Structural Eng – Project III
4 Dr C. Caprani
BE Structural Eng – Project III
1. Introduction
Goals
In other words, you will learn to carry out a complete preliminary design of a
structure.
The detailed design of elements is covered in your other modules such as concrete
and steel design.
5 Dr C. Caprani
BE Structural Eng – Project III
Preliminary Design
“In the initial stages of the design of a building structure it is necessary, often at
short notice, to produce alterative schemes that can be assessed…”
– ISE Green Book
Therefore, it should be:
• simple;
• quick;
• conservative, and;
• reliable.
Lengthy analytical methods should be avoided.
It is often based upon vague and limited information on matters affecting the
structure such as imposed loads, nature of finishes, dimensions.
It is needed to:
• obtain costs estimates;
• compare alternative schemes for architectural and functional suitability;
• obtain initial estimates for computer analysis, and;
• check a completed detailed design.
6 Dr C. Caprani
BE Structural Eng – Project III
We will develop methods of analysing and designing structures that meet the above
requirements.
Note that even though detailed design does not feature, it should be clear that
knowledge of it is central to preliminary design.
7 Dr C. Caprani
BE Structural Eng – Project III
1.2 Syllabus
The topics covered in this subject include the following:
- Relevant Literature
- Economic Structural Scheme Design
- Load Types and Scenarios
- Stability of Structures
- Mechanisms of Load Transfer
- Tributary Lengths, Areas, and Loadwidths
- Analysis of Portal Frame Structures
- Structural Materials
- Movement/Expansion Joints
- Preliminary Loading
- Load Takedown
- Car Park Layout Design
- Preliminary Analysis
- Preliminary Design of Elements
- Example Scheme Designs
8 Dr C. Caprani
BE Structural Eng – Project III
1.3 Programme
This subject is examined by continuous assessment. Case Study reports are the basis
for marking.
9 Dr C. Caprani
BE Structural Eng – Project III
1.4 Studying
This subject is different to others. It is simply not possible to “cram” for, due its
nature. Here is some advice to help you achieve your best.
• Teaching:
o Learn from experienced engineers, through discussion and reading;
o Lectures on course material;
o Case-Studies and presentation.
Remember, contrary to what your education to-date may lead you to believe:
o Engineering is not an exact science;
o There are no “right” answers.
This will become apparent in the coming weeks!
10 Dr C. Caprani
BE Structural Eng – Project III
So How Do I Learn?
The three best pieces of advice (and past students agree) are:
1. Attend lectures: simple, but for subjects like this, year-on-year poor results
and attendance show a strong correlation.
2. Take lots of notes: a lot will be said – try not miss important points.
3. Ask lots of questions: both from you lecturers for this subject and from other
lecturers or engineers you have access to.
• Personally:
o Be prepared to present to the class and speak clearly and loudly;
o Learn to accept criticism in front of the class – in this way, everybody
learns from each other’s mistakes;
o Contribute your fair share to the Case Study groups.
11 Dr C. Caprani
BE Structural Eng – Project III
What is expected
Overall:
- Understand structural behaviour (bending, axial, membrane action etc.)
- Appreciate allowances needed for lateral loads and thermal expansion
- Apply preliminary design rules of thumb (span/15, 50N etc.)
- Pay due regard to the ‘Key Principles’
In particular:
- Lots of quick well-annotated sketches (“picture says a 1000 words”)
- Appropriate sections/elevations/details e.g. RC column bar arrangement
- Appreciation of your ‘numbers’ (2T16 in a 500×500 RC Column?!)
- Use an appropriate top-down approach to your scheme, for example:
1. stability/expansion joints
2. column/beam layout
3. approx sizes of important members
4. load takedown
5. prelim design of typical members
- Confidence in your knowledge and an ability to ‘customise’ design
recommendations without compromising on strength requirements
12 Dr C. Caprani
BE Structural Eng – Project III
General Advice
- Make sure your structure is stable in all 3-dimensions before moving on.
- Carry any expansion joints all the way through the structure down to ground level
- remember they are being designed as totally separate structures that are very
close to one another.
- Follow the “advice” in the problem, e.g. “minimum structural intrusion is
expected” means don’t put a column there unless absolutely necessary.
- Try visualising the structure and your solution. Play around with solutions in your
head or on the paper before committing to one in particular.
13 Dr C. Caprani
BE Structural Eng – Project III
Reports that do no conform to the following may or may not be accepted for
submission, at the discretion of the lecturer.
General
• Submit one report per group;
• Reports should be covered (clear plastic to front) and bound with slide-on
spine binder.
• Clearly identify the group letter on the front cover sheet;
• Each group member is to sign the front cover of the report;
• Each group member should retain a copy of the report for reference.
Content
• The report should consist of annotated sketches;
• In some cases a little text is appropriate: keep it to a minimum;
• In some cases a few calculations are appropriate; again keep to a minimum;
• Answer the question: do not provide irrelevant details!
Format
• Sketches are to be done on lightly squared paper, e.g. calculation pads;
• Any calculations are to be done on lightly squared paper also;
• The use of CAD is not recommended – it is better to improve your sketching;
• Text (excluding annotations) should be typed in the following style: Times
New Roman, size 14 font; Justify alignment, and; double line spacing.
Length
• The report should be between 5 and 10 pages in length.
14 Dr C. Caprani
BE Structural Eng – Project III
Submission
• Reports are to be submitted at the time stated on the problem;
• Late submissions will not be accepted – clients in the real world do not accept
tardiness so start preparing for it now!
Presentation
• The report is to be photocopied onto acetate for presentation;
• The group must be ready to present and defend the report in class.
15 Dr C. Caprani
BE Structural Eng – Project III
Codes:
British Standards – BS8110, BS5950, BS5268, BS5628, BS6399
Eurocodes – EC1, EC2, EC3, EC4, EC5, EC6
Magazines:
Journal of the Institution of Engineers of Ireland
Institution of Civil Engineers: The New Civil Engineer (NCE) magazine
Company Magazines, e.g. Arup Journal
Books:
Homebond Manual – don’t underestimate the complexity of a house
Library – some of the best are:
William Addis –
• Structural engineering: the nature of theory and design
16 Dr C. Caprani
BE Structural Eng – Project III
Trade Organisations:
Corus, The Concrete Centre, The Brick Development Association (Google them).
Bunf:
Suppliers’ manuals (companies are very happy to send out their stuff to you)
• Kingspan/Tegral – industrial buildings
• Breton/Flood Flooring/Concast etc – precast concrete structures, precast slabs
• Bat – for timber connectors
People:
Your work placement company projects – talk to engineers you worked with.
Web:
Almost everything to be found.
Talks:
Come to the talks organized by the IStructE, IEI etc. – look out for notices.
17 Dr C. Caprani
BE Structural Eng – Project III
Easy:
A bit harder:
Tricky:
18 Dr C. Caprani
BE Structural Eng – Project III
In the following structures identify the possible loads that need to be designed for.
19 Dr C. Caprani
BE Structural Eng – Project III
20 Dr C. Caprani
BE Structural Eng – Project III
21 Dr C. Caprani
BE Structural Eng – Project III
22 Dr C. Caprani
BE Structural Eng – Project III
23 Dr C. Caprani
BE Structural Eng – Project III
• Materials:__________________________________________________________
24 Dr C. Caprani
BE Structural Eng – Project III
• Materials:__________________________________________________________
Flat Slab
Beams Under
Columns Under
Slab
Panel
25 Dr C. Caprani
BE Structural Eng – Project III
• Materials:__________________________________________________________
Steel
R.C.
P.S.C.
Timber
Masonry
Structural
Glass
26 Dr C. Caprani
BE Structural Eng – Project III
Membrane action
By definition, ‘regular beam’ action becomes ‘deep beam’ action when span/depth
ratio goes less than about 2.
• Because: __________________________________________________________
27 Dr C. Caprani
BE Structural Eng – Project III
(i) Trusses
Material Comment
Steel
R.C.
P.S.C.
Timber
Masonry
Structural Glass
28 Dr C. Caprani
BE Structural Eng – Project III
(ii) Frames
All members
contribute
Frame action is what happens in Vierendeel Girders (named after Belgian engineer):
29 Dr C. Caprani
BE Structural Eng – Project III
Material Comment
Steel
R.C.
P.S.C.
Timber
Masonry
Structural Glass
(iii) Arches
F×sinθ
F×cosθ
30 Dr C. Caprani
BE Structural Eng – Project III
• Generates substantial horizontal thrust. This is the dominant limitation to the arch.
Horizontal thrust is equal to the horizontal component of the axial force in the arch at
the point where it meets the support.
It is difficult to design foundations to take significant horizontal force unless they are
in rock. Possible solutions are:
• provide a tie (tied arch);
• use an elliptical or half-circular arch so that θ = 90o.
31 Dr C. Caprani
BE Structural Eng – Project III
Pull from
deck
Suspension Bridge
32 Dr C. Caprani
BE Structural Eng – Project III
Fabric (cloth) has no flexural strength, i.e., it has no strength in bending. It buckles in
compression. Its only strength is in tension.
Fabric is subject to 2-way axial force action, i.e., membrane action. However, it is
different from a deep beam in that (a) it takes no compression and (b) the fabric
deforms in response to load into a 2D catenary shape. These deformations are large
compared with the geometry of the structure (think of a 10 m beam deflecting 2 m!).
This change in shape changes the load path further, and hence the shape, and hence
the loadpath… This phenomenon is known as geometric non-linearity.
Advantages/Disadvantages:
• very light self weight;
• great spans with ease (30 m in Berlin zeppelin hanger);
33 Dr C. Caprani
BE Structural Eng – Project III
• it stretches;
• it has different strengths parallel and perpendicular to the weave;
• it must be stretched (prestressed);
• snow will tend to drift;
• long-term durability is improving as fabric technology improves.
This principle has been used as ‘shuttering’ in buildings made from reinforced
concrete!
Roofs can have a hyperbolic paraboloid shape, i.e., parabola in one direction and
hyperbola in the other (saddle shape). This shape is structurally efficient. The load is
carried predominantly by membrane action.
34 Dr C. Caprani
BE Structural Eng – Project III
The saddle dome ice hockey stadium in Calgary, Canada is a hyperbolic paraboloid
and is made of prestressed concrete sections 600 mm deep.
Compression
Depth of Tension
fold
A folded plate is stronger than a flat plate as it acts like a beam/slab, taking tension in
the lower members and compression in the upper members (if simply supported).
Structurally, the depth of the fold is more important than the depth of the members.
To see this in action make a paper model and load it. Note that it only spans one way
to any extent.
35 Dr C. Caprani
BE Structural Eng – Project III
These are in effect a form of 3D truss system – a series of struts and ties. They are not
particularly efficient although the inclined members do reduce the effective clear
span of the roof truss.
Roof truss
Effective span of
roof truss
Tension
36 Dr C. Caprani
BE Structural Eng – Project III
B
C
D E
__________________________________
__________________________________
37 Dr C. Caprani
BE Structural Eng – Project III
______________________________________________________
A B
4m
10 m
______________________________________________________
6. Free standing wall: how is the horizontal wind load transferred to the piers?
_______________________________________________
38 Dr C. Caprani
BE Structural Eng – Project III
_________________________________________________
9. Indicate the types of support (fixed, pinned or sliding) you would specify at each
support point on the arch bridge:
39 Dr C. Caprani
BE Structural Eng – Project III
Introduction
Gravity → Columns
y
x
Even without loads in the lateral directions, bracing is required due to the
inaccuracies of actual construction: buildings may not be perfectly plumb.
40 Dr C. Caprani
BE Structural Eng – Project III
The frame on the left is in equilibrium, but is not stable (try to balance a pen, even on
its ‘fat’ end!). The frame on the right is stable due to the addition of the diagonal
member, even thought this additional member does not contribute to the vertical load
carrying capacity of the structure.
In this, (a) and (b) are termed ‘braced’ frames whilst (c) is referred to as a ‘sway’, or
unbraced frame. A single braced bay can stabilize a row of bays:
41 Dr C. Caprani
BE Structural Eng – Project III
Definitions:
- Braced Frame:
o load resisted through bending of large in-plane elements.
- Unbraced or Sway Frame:
o load resisted through moment connections of framework –
generally not used unless absolutely necessary due to the expense
of the moment connections and the larger deflections.
x, y
x, y
42 Dr C. Caprani
BE Structural Eng – Project III
When considering walls as bracing, remember they can only take in-plane loads:
43 Dr C. Caprani
BE Structural Eng – Project III
The wind load that needs to be resisted must take the following path:
1. Wind hits façade (glazing or brickwork);
2. Façade spans between floors vertically;
3. Floors transfer load to the braced elements through diaphragm action;
4. Bracing takes load from each floor to ground.
44 Dr C. Caprani
BE Structural Eng – Project III
Identify the elements providing the load path in the following structures:
45 Dr C. Caprani
BE Structural Eng – Project III
46 Dr C. Caprani
BE Structural Eng – Project III
47 Dr C. Caprani
BE Structural Eng – Project III
Are the following stable? – sketch the various load paths to check.
48 Dr C. Caprani
BE Structural Eng – Project III
In Practice
Actual structures have bracing systems that look along the lines of the following:
49 Dr C. Caprani
BE Structural Eng – Project III
50 Dr C. Caprani
BE Structural Eng – Project III
A portal frame structure (usually used in industrial estates etc.) is the most ordinary
of buildings, yet is complex for lateral stability.
Write some notes on why this is, and sketch the required stability elements on the
attached end gable. The end gable is not a portal frame.
51 Dr C. Caprani
BE Structural Eng – Project III
52 Dr C. Caprani
BE Structural Eng – Project III
Important: Advice on joint spacing can be variable and conflicting, but here goes:
50 m 50 m
Concrete 60 – 70 m
25 m: exposed RC 25 m: exposed RC
Simple: 100 m
Steel – commercial 50 – 100 m
Continuous: 50 m
Masonry 40 – 50 m
53 Dr C. Caprani
BE Structural Eng – Project III
Extracts
54 Dr C. Caprani
BE Structural Eng – Project III
Corus
55 Dr C. Caprani
BE Structural Eng – Project III
56 Dr C. Caprani
BE Structural Eng – Project III
57 Dr C. Caprani
BE Structural Eng – Project III
Movement joints
Used to divide structural elements into smaller elements due to local effects of
temperature and moisture content.
Material Spacing
Clay bricks On plan: up to 12 m c/c (6 m from corners);
Vertically: 9 m or every 3 storeys if h > (12 m or 4 storeys)
Concrete blocks 3 m – 7 m c/c
Steel roof sheeting 20 m c/c down the slope
Examples
Joint in an RC slab:
Joint in a roof:
58 Dr C. Caprani
BE Structural Eng – Project III
Kansai Airport:
The building moves three-dimensionally in repose to potential stress from temperature
shrinkage, earthquakes and uneven setting. In order to make the structure capable of
absorbing deformation, expansion joints have been placed in 11 locations, at
approximate intervals of 150m along the length of the 1.7km structure. The joints are
450-600mm in width.
59 Dr C. Caprani
BE Structural Eng – Project III
Effect on Stability
“The positions of movement joints should be considered for their effect on the overall
stability of the structure” – Cobb
60 Dr C. Caprani
BE Structural Eng – Project III
Example
40
110
A B
40
55 55
61 Dr C. Caprani
BE Structural Eng – Project III
Note:
• Double columns at interface – there are now 2 separate structures built very
closely beside each other;
• Stability of each structure – clearly structure A is stable, whilst B is not.
A B
40
55 55
Case Study
Beaumont Hospital car park is an excellent example of lateral stability design, car
park design, and building control joints. Similarly to the two walls that are very close
together in the building just above, two X-braced frames either side of the control
joint are clearly visible.
62 Dr C. Caprani
BE Structural Eng – Project III
Every building and structure is unique in every way. The designers’ solution reflects
this, and must also be unique – an optimum balance of pros and cons sympathetic to
the project. This is so both for the materials to be used, and for the type of
construction to be used.
63 Dr C. Caprani
BE Structural Eng – Project III
Introduction
The principal criteria which influence the choice of structural material are:
(a) strength;
(b) durability (resistance to corrosion);
(c) architectural requirements;
(d) versatility;
(e) safety;
(f) speed of erection;
(g) maintenance;
(h) cost;
(i) craneage.
64 Dr C. Caprani
BE Structural Eng – Project III
The properties of reinforced and prestressed concrete are compared below with the
properties of structural steel, timber and masonry under each of these nine headings.
It should be noted that only one or two structural materials tend to be used in any
given construction project. This is to minimise the diversity of skills required in the
workforce.
Strength
The relative strengths of the six main structural materials have already been discussed
above. However, it should also be noted that the ability of a material to sustain
external loads is dependent on the mechanisms by which the loads are carried in
a member. For example, members which are in pure compression or tension will
carry their loads more efficiently than members in bending since the stress is evenly
distributed across the section (this will be seen in the following section). For this
reason, the available strength of a structural material depends as much on the method
of load transfer as its characteristic strength. Nevertheless, it can in general be stated
that reinforced and prestressed concrete and structural steel are strong materials.
Relative to these, timber and masonry are generally rather weak and are more suitable
for short spans and/or light loads.
Durability
The durability of a material can be defined as its ability to resist deterioration under
the action of the environment for the period of its design life. Of the four raw
materials used in construction, steel has by far the least resistance to such corrosion
(or rusting as it is more commonly known), particularly in aggressive humid
environments. Hence, the durability of a structural material which is wholly or partly
made from steel will largely be governed by how well the steel is protected.
structural materials is their superior durability. The durability of the concrete itself
is related to the proportions of its constituents, the methods of curing and the level of
workmanship in the mixing and placing of the wet concrete. The composition of a
concrete mix can be adjusted so that its durability specifically suits the particular
environment. The protection of the steel in reinforced and prestressed concrete
against the external environment is also dependent on the concrete properties,
especially the porosity. However, its resistance to corrosion is also proportional to the
amount of surrounding concrete, known as the cover, and the widths to which cracks
open under day-to-day service loads.
Structural steel, like concrete, is considered to be very durable against the agents of
wear and physical weathering (such as abrasion). However, one of its greatest
drawbacks is its lack of resistance to corrosion. Severe rusting of steel members
will result in a loss in strength and, eventually, to collapse. The detrimental effect of
rusting is found to be negligible when the relative humidity of the atmosphere is less
than approximately 70 per cent and therefore protection is only required in unheated
temperate environments. Where corrosion is likely to be a problem, it can often be
prevented by protective paints. Although protective paints are very effective in
preventing corrosion, they do add significantly to the maintenance costs (unlike
concrete for which maintenance costs ire minimal).
66 Dr C. Caprani
BE Structural Eng – Project III
Masonry, like concrete, can also be adapted to suit specific environments by selecting
more resistant types of blocks/bricks for harsh environments. Unreinforced masonry
is particularly durable and can last well beyond the typical 50 year design life.
Architectural requirements
For concrete, this final appearance is dependent on the standards of placement and
compaction and the quality of the formwork. Badly finished concrete faces, with
little or no variation in colour or texture over large areas, can form the most unsightly
views. Concrete is a versatile material, however, and when properly placed, it is
possible to produce structures with a wide variety of visually appealing finishes In the
case of precast concrete, an excellent finished appearance can usually be assured
since manufacture is carried out in a controlled environment.
Exposed structural steel in buildings is displeasing to the eye in many settings and
must be covered in cladding in order to provide an acceptable finish. An exception to
this is the use of brightly painted closed, hollow, circular or rectangular sections.
Versatility
forms and shapes and (b) to undergo substantial last-minute alterations on site
without detriment to the overall design. Steel can easily be worked into many
efficient shapes on fabrication but is only readily available from suppliers in standard
sections. Concrete is far more versatile in this respect as it can readily be formed by
moulds into very complex shapes. Timber is the most limited as it is only available
from suppliers in a limited number of standard sides. Laminated timber, on the
other hand can be profiled and bent into complex shapes. Masonry can be quite
versatile since the dimensions of walls and columns can readily be changed at any
time up to construction. The disadvantage of steel, timber and precast concrete
construction is their lack of versatility on site compared with in situ reinforced
concrete and masonry to which substantial last-minute changes can be made. In situ
prestressed concrete is not very versatile as changes can require substantial
rechecking of stresses.
Safety
The raw material of concrete is very brittle and failure at its ultimate strength can
often occur with little or no warning. Steel, being a very ductile material, will
undergo large plastic deformations before collapse, thus giving adequate warning
of failure. The safety of reinforced concrete structures can be increased by providing
'under-reinforced' concrete members (the concepts of under-reinforced and over-
reinforced concrete are discussed in Chapter 7). In such members, the ductile steel
reinforcement effectively fails in tension before the concrete fails in compression,
and there is considerable deformation of the member before complete failure.
Although timber is a purely elastic material, it has a very low stiffness
(approximately 1/20th that of steel) and hence, like steel, it will generally undergo
considerable defection before collapse.
68 Dr C. Caprani
BE Structural Eng – Project III
loses its strength rapidly as its temperature increases and so steel members must be
protected from fire to prevent collapse before the occupants of the structure have time
to escape. For structural steel, protection in the form of intumescent paints, spray-
applied cement-binded fibres or encasing systems, is expensive and can often be
unsightly. Concrete and masonry possess fire-resisting properties far superior to most
materials. In reinforced and prestressed concrete members, the concrete acts as a
protective barrier to the reinforcement, provided there is sufficient cover. Hence,
concrete members can retain their strength in a fire for sufficient time to allow the
occupants to escape safely from a building. Timber, although combustible, does not
ignite spontaneously below a temperature of approximately 500 °C. At lower
temperatures, timber is only charred by direct contact with flames. The charcoal
layer which builds up on the surface of timber during a fire protects the underlying
wood from further deterioration and the structural properties of this 'residual' timber
remain unchanged.
Speed of erection
In many projects, the speed at which the structure can be erected is often of
paramount importance due to restrictions on access to the site or completion
deadlines. In such circumstances, the preparation and fabrication of units offsite
will significantly reduce the erection time. Thus, where precast concrete
(reinforced and/or prestressed) and structural steel are used regularly, the construction
tends to be very fast Complex timber units, such as laminated members and roof
trusses, can also be fabricated offsite and quickly erected.
The construction of in situ concrete structures requires the fixing of reinforcement the
erection of shuttering, and the castings, compaction and curing of the concrete. The
shutters can only be removed or 'struck' when the concrete has achieved sufficient
strength to sustain its self-weight. During the period before the shutters can be struck,
69 Dr C. Caprani
BE Structural Eng – Project III
which can be several days, very little other construction work can take place (on that
part of the structure) and hence the overall erection time of the complete structure
tends to be slow. Masonry construction, though labour intensive, can be erected
very rapidly and the structure can often be built on after as little as a day.
Maintenance
Less durable structural materials such as structural steel and timber require treatment
to prevent deterioration. The fact that the treatment must be repeated at intervals
during the life of the structure means that there is a maintenance requirement
associated with these materials. In fact, for some of the very large exposed steel
structures, protective paints must be applied on a continuous basis. Most concrete and
masonry structures require virtually no maintenance.
Cost
For example, although concrete is cheaper per unit volume than structural steel,
reinforced concrete members generally require a greater volume than their equivalent
structural steel members because of the lower strength of concrete.
70 Dr C. Caprani
BE Structural Eng – Project III
Craneage
In general, in situ concrete requires little craneage although cranes, when available,
can be used for moving large shutters.
The table below serves as a summary of the relative advantages and disadvantages of
the four types of structural material under the categories discussed above. At this
stage, it should be appreciated that the choice of any structural material is heavily
dependent on the particular structure and the conditions under which it is constructed.
71 Dr C. Caprani
Comparison of the structural properties of concrete (reinforced and prestressed), structural steel, timber and masonry.
corrosion*
72
Safety Excellent Poor fire resistance* Good Excellent
Speed of Slow for in-situ Very fast Very fast Very fast but labour
erection intensive
*unless protected
Dr C. Caprani
Order of priority given to the material evaluation criteria by different design team members.
Building
Structural Quantity
Priority Client Contractor Architect Services
Engineer Surveyor
Engineer
1
BE Structural Eng – Project III
73
3
Dr C. Caprani
BE Structural Eng – Project III
All of the Case Studies, though on different topics, try to show that there are a
number of factors that contribute, in different measures, to the structural scheme
adopted. Also, it will be clear that there is no perfect answer – simply a weighted
balance of the pros and cons of any given solution. Factors include:
1. Technical Requirements
• Structure Scale:
− Stability in all directions – Vertical and Orthogonal Horizontals
− Accommodation of movement – either by joints or stress design
− Global load paths are identified
• Element Scale:
− Proportional sizes, e.g. span/d ratios or N/20 etc.
− Global actions are allowed for in the element scheme
2. Economic Requirements
• Materials (Refer to the handout):
− Raw cost – can it be locally sourced?
− Placement cost – e.g. block layers are expensive currently
− Transport of fabricated elements – special requirements?
• Constructability
− Is the structure repeatable as possible
− Minimum number of trades on site
− Transport/craneage appropriate for the material considered?
74 Dr C. Caprani
BE Structural Eng – Project III
3. Functional Requirements
• Building Service Integration:
− Expect holes in beams – allow for it early on
− Flat soffits are beneficial in heavily serviced buildings
• Client’s focus:
− Speculative commercial will require clear spans for example
− Landmark headquarters will possibly mean a dramatic structure
• Architecture:
− Complement the architecture if possible
− Get involved as early as possible in the design
• Planning:
− Minimise structural depths if required
− Drainage schemes to be appropriate to site and local drainage
− Environmental considerations
Choice of Form
The span of the structure is the main consideration. For the two usual forms of
construction, the first of the following charts advises what forms of construction are
appropriate for what spans for steel and concrete.
The second chart gives a comparison of the weights of structure required for various
spans and types of construction for single-storey steel buildings. These buildings tend
to be extremely well engineering economically.
75 Dr C. Caprani
BE Structural Eng – Project III
76 Dr C. Caprani
BE Structural Eng – Project III
77 Dr C. Caprani
BE Structural Eng – Project III
4. Precedence Studies
4.1 Introduction
In this section we have a look at some interesting structures of the past and see how
they integrate the preceding ideas of stability, material and form to achieve economic
aesthetic and stunning solutions to the design brief.
78 Dr C. Caprani
BE Structural Eng – Project III
79 Dr C. Caprani
BE Structural Eng – Project III
80 Dr C. Caprani
BE Structural Eng – Project III
81 Dr C. Caprani
BE Structural Eng – Project III
82 Dr C. Caprani
BE Structural Eng – Project III
Utzon wanted to remove the columns and asked the engineers if it would be possible.
The engineers said yes, but it would be more expensive. But why is it necessary to
remove them: the area is for deliveries only, and the columns to not interfere with
that function?
83 Dr C. Caprani
BE Structural Eng – Project III
Even Candela was brought in to aid the design of the shells but to no avail. Would it
all have been easier if Utzon had an engineer on board from day one?
84 Dr C. Caprani
BE Structural Eng – Project III
85 Dr C. Caprani
BE Structural Eng – Project III
86 Dr C. Caprani
BE Structural Eng – Project III
87 Dr C. Caprani
BE Structural Eng – Project III
88 Dr C. Caprani
BE Structural Eng – Project III
89 Dr C. Caprani
BE Structural Eng – Project III
90 Dr C. Caprani
BE Structural Eng – Project III
91 Dr C. Caprani
BE Structural Eng – Project III
92 Dr C. Caprani
BE Structural Eng – Project III
93 Dr C. Caprani
BE Structural Eng – Project III
Two bow-string trusses are provided; one each for positive and negative (suction)
pressures on the glazed elevation.
Of significance though, is that there are no vertical cable elements. By causing the
truss and the glass to roate about different axes (X-X and Y-Y), the glass dead weight
stabilizes the whole structure.
94 Dr C. Caprani
BE Structural Eng – Project III
95 Dr C. Caprani
BE Structural Eng – Project III
96 Dr C. Caprani
BE Structural Eng – Project III
Here is an example of the Engineer’s Aesthetic – why was Torroja not satisfied with
event he second scheme which is structurally indistinct from the final scheme?
97 Dr C. Caprani
BE Structural Eng – Project III
98 Dr C. Caprani
BE Structural Eng – Project III
99 Dr C. Caprani
BE Structural Eng – Project III
100 Dr C. Caprani
BE Structural Eng – Project III
101 Dr C. Caprani
BE Structural Eng – Project III
102 Dr C. Caprani
BE Structural Eng – Project III
103 Dr C. Caprani
BE Structural Eng – Project III
104 Dr C. Caprani
BE Structural Eng – Project III
Khan realized that the solution to this was to stiffen the perimeter walls by brining
internal shear walls out to the perimeter:
This is not ideal for the function of the building. But Kahn and Graham (SOM
architect) realized that this full resistance was not required all the way up the
structure, and that these interior walls might be exterior at different levels.
Thus the concept of the bundled tube was born, leading to…
105 Dr C. Caprani
BE Structural Eng – Project III
106 Dr C. Caprani
BE Structural Eng – Project III
107 Dr C. Caprani
BE Structural Eng – Project III
108 Dr C. Caprani
BE Structural Eng – Project III
And the tube-in-a-tube idea, where beams link the two stability stuctures:
109 Dr C. Caprani
BE Structural Eng – Project III
110 Dr C. Caprani
BE Structural Eng – Project III
111 Dr C. Caprani
BE Structural Eng – Project III
In summary, Khan helped develop the concepts used in the world’s tallest structures.
It is clear that structural considerations play the prime role in final form of the
building.
112 Dr C. Caprani
BE Structural Eng – Project III
5. Preliminary Analysis
Imposed Loading
113 Dr C. Caprani
BE Structural Eng – Project III
114 Dr C. Caprani
BE Structural Eng – Project III
115 Dr C. Caprani
BE Structural Eng – Project III
116 Dr C. Caprani
BE Structural Eng – Project III
Dead Load
Dead loads are derived from the densities of materials to be used. However, usually
the dimensions of the elements are not known prior to preliminary sizing.
Reinforced concrete 24
Structural steel 77
Timber – softwood 4–6
Timber – hardwood 6 – 10
Blocks – solid 21
Blocks – hollow 12
Bricks 22
Designers usually build up a list of the dead loads for common build-ups – two sets
of build-ups are in the following pages.
After calculation of dead and imposed load, determine the composite gamma factor.
This provides insight into the governing type of load (dead or live) and is also very
useful after the full load takedown when only service loads are to be designed for in
the foundation dedsign.
117 Dr C. Caprani
BE Structural Eng – Project III
wser = Gk + Qk
wult = γ G ⋅ Gk + γ Q ⋅ Qk
wult
γ Comp =
wser
Values of γ Comp nearer 1.4 indicate dead load is governing; those nearer 1.6 indicate
live load is governing. To reduce loads overall if there is a problem, try change the
governing load first.
118 Dr C. Caprani
BE Structural Eng – Project III
119 Dr C. Caprani
BE Structural Eng – Project III
120 Dr C. Caprani
BE Structural Eng – Project III
These are the basis of more complicated analyses: the usual cases need to be known.
w
A B
C
L
VA VB
wL wL2 5wL4
VA = VB = , MC = , δC =
2 8 384 EI
A B
C
L
VA VB
P PL PL3
VA = VB = , MC = , δC =
2 4 48 EI
MA B wL2 wL4
A VA = wL , M A = , δB =
2 8 EI
L
V
MA B PL3
A VA = P , M A = PL , δ B =
L 3EI
VA
121 Dr C. Caprani
BE Structural Eng – Project III
w
MA MB
A B
VA L VB
wL4
δC =
wL2 384 EI wL2
MA = MB =
12 12
w
MA B
A
5 L 3
VA = wL VB = wL
8 8
2 wL4
δC =
384 EI
wL2
MA =
8
122 Dr C. Caprani
BE Structural Eng – Project III
Continuous Beams
The reactions have been considered previously, so only moments are done here.
w
A C
B
L L
VA VB VC
wL2
MB =
8
123 Dr C. Caprani
BE Structural Eng – Project III
w
A D
B C
L L L
VA VD
VB VC
wL2 wL2
MB = MC =
10 10
w
A E
B C D
L L L L
VA VC VD VE
VB
wL2 wL2 wL2
MB = MC = MD =
10 12 10
124 Dr C. Caprani
BE Structural Eng – Project III
For more spans, the moments over the first interior supports are as shown, and the
wL2
moments over other internal supports are taken as .
12
125 Dr C. Caprani
BE Structural Eng – Project III
126 Dr C. Caprani
BE Structural Eng – Project III
Workings:
127 Dr C. Caprani
BE Structural Eng – Project III
To get a rough idea of the rebar required for your scheme, it is usual to take the
largest moment in your section:
1. What is your configuration – propped cantilever, 3-span beam etc…
2. Take the maximum value of moment (i.e. smallest value of denominator).
wL2 wL2
So for a 3-span beam take , for a fixed-fixed beam take etc.
10 12
For more detailed design, or to find the positions of the points of contraflexure, the
following is helpful:
MA w MB
A B
L VB
VA
MA d d MB
b c
128 Dr C. Caprani
BE Structural Eng – Project III
Load Patterning
This presents problems with our moment formulae previously. A way around this is
to do the following:
129 Dr C. Caprani
BE Structural Eng – Project III
Consider the beam shown in the figures, should the RC beam (250W×300Dp.) be
designed for moments at support B? And if so, what value would you take?
Remember that large amounts of cracking are not desirable.
Moment
A w B
RC-detailed
pin connection
Structure 1
A w B
Continuity
250×250 RC
Structure 2 Column
A w B
Full steel
250×500 RC
Column
Structure 3
A w B
Full steel
Shear wall
Structure 4
130 Dr C. Caprani
BE Structural Eng – Project III
Take a rectangular plate, simply supported on all sides, loaded with a uniformly
distributed load, w, and consider two central unit-width strips:
ly
lx
The load on the strip in the x-direction is wx; likewise, wy. Also, w = wx + wy. The
5wx lx4 5wy l y4
deflection of each strip must be identical at the centre point: = . Hence,
384 EI x 384 EI y
ly
assuming I x = I y , and letting r = , then wx = wy r 4 and as r > 1 the load taken in the x-
lx
1 r4
direction is greater than that in the y-direction. Further, wy = w ⋅ and w = w ⋅ .
1+ r4 1+ r4
x
Other support conditions can be used, and a similar approach using compatibility of
displacement can be used.
131 Dr C. Caprani
BE Structural Eng – Project III
A B
L
RA RB
wL
As the reactions RA = RB = , they have an TL of L 2 .
2
w
A
B C
L L
RA RB RC
132 Dr C. Caprani
BE Structural Eng – Project III
3L 10 L 3L
TL for RA = TL for RB = TL for RC =
8 8 8
w
A
B C
L L
3wL 10 wL 3wL
RA = RB = RC =
8 8 8
For more than two spans, the intermediate spans have a TL of L. The end support has
3L 5L L 9 L
a TL of , whilst the second internal support has a TL of + = :
8 8 2 8
3L 9L
TL for RA = TL for RB = TL for RC = L
8 8
w
A
B C
L L L
3wL
RA = 9 wL RC = wL
8 RB =
8
133 Dr C. Caprani
BE Structural Eng – Project III
Load Width
For beams, the UDL arises from the loads applied to the flooring system.
The simple case is a one-way spanning simply-supported flooring system (say precast
units):
w (kN/m2)
The load-width is the same as the TL for the “beam” of the floor system.
134 Dr C. Caprani
BE Structural Eng – Project III
Tributary Area
The combination of the loadwidth (transverse to a beam) and the tributary length
(longitudinal to the beam) result in the tributary area for a beam support. Fill in the
lengths for following floor plate layout:
Note that the lengths indicated depend on the type of spans – continuous or simply
supported, and result from application of the loadwidths and tributary lengths.
135 Dr C. Caprani
BE Structural Eng – Project III
For two-way spans, the load is shared between the supports on all sides:
Beams on
all sides
Beam A
Beam B Beam C
Beam D
But, for the internal columns, the tributary areas remain rectangular.
136 Dr C. Caprani
BE Structural Eng – Project III
137 Dr C. Caprani
BE Structural Eng – Project III
wL2
Taking ∑ Moments about A : 2
= VB l1 and ∑F Y = 0 : VA = VB − wL .
wL2 ⎛l +l ⎞ l ⎛ r +1⎞ ⎛ r −1 ⎞
So, VB = = wL ⎜ 1 2 ⎟ . Let r = 2 ; hence VB = wL ⎜ ⎟ and VA = wL ⎜ ⎟
2l1 ⎝ 2l1 ⎠ l1 ⎝ 2 ⎠ ⎝ 2 ⎠
The term in brackets indicates the multiplier to be applied to the total load on the
span which is wL .
For example, when r = 2 , VB = 1.5wL and VA = −0.5wL . So a 50% increase of the total
load on the span occurs at the prop reaction, due simply to the geometry.
138 Dr C. Caprani
BE Structural Eng – Project III
A rough section through this grandstand and its overall structural idealization is:
BMD
Horizontal
The ‘bending moments’ in the frame are resisted by the tension and compression of
the top and bottom chord of the roof truss:
M T
equals lever
arm
139 Dr C. Caprani
BE Structural Eng – Project III
The members that contribute to the roof cantilever are shown below. What are the
structural actions on the members?
Horizontal
Bracing
140 Dr C. Caprani
BE Structural Eng – Project III
6. Preliminary Design
Structural design and analysis is often an iterative process. Section sizes may be
needed before an analysis can be carried out to determine the load effects that
sections must be designed for (which in turn dictates the size of the section).
• Preliminary sizes are obtained from experience and rules of thumb (other people’s
experience). These are used in the preliminary analysis.
• The results of the analysis are used to obtain more refined approximate designs.
In preliminary design, these steps are only carried out once. In detailed design the
process can take many iterations.
For the usual materials and forms of construction we considered both of these stages.
141 Dr C. Caprani
BE Structural Eng – Project III
Preliminary sizing
Bending members
Sized through span-effective depth ratios:
Flat
Construction One-way Two-way
slab
Imposed
Simply- Simply-
load Contin. Canti. Contin.
supported supported
(kN/m2)
5 27 31 11 30 40 36
Slab
10 24 28 10 28 39 33
Beam -
any 10 12 6
Rectang.
Beam –
any 12 15 6
flanged
The breadth of a beam is around d/3 but not always. Fire resistance requirements
stipulate minimum widths, but for ease of construction, 200 mm is a rough minimum,
giving about 2 hours fire resistance.
142 Dr C. Caprani
BE Structural Eng – Project III
Columns
These rules only apply for stocky braced columns for which the minimum horizontal
dimension is clear height/17.5.
Very roughly: Acol = N × 50 (in mm2) where N is the ultimate axial load in kN. Or
assume an average stress across the column of about 25 N/mm2.
Loads from other floors may be considered fully axial; sketch these requirements:
143 Dr C. Caprani
BE Structural Eng – Project III
Bending members:
Percentage area of steel for a singly reinforced section:
⎛ M ⎞
ρs ≈ ⎜ 2 ⎟ π
⎝ bd ⎠
The π is to make it look fancy! Any number from 3.1 (for a loose design) up to about
ρs
4.3 (for a tight design) can be used. Note that As = bd . Combining these two
100
expressions leads to a very quick estimate of:
M
As =
300d
Columns:
Given an area of column, its resistance can be got by considering a mean ‘resistance
stress’ as:
ρ
0.35 f cu +
100
( 0.67 f y − 0.35 f cu )
N Acol − 14
Alternatively, roughly: ρ≈
3
Derive this:
144 Dr C. Caprani
BE Structural Eng – Project III
Punching shear:
The column reaction, Vt , is modified as follows to take account of moment transfer:
• Internal Columns: Veff = 1.15Vt ;
where a and b are the plan dimensions of a rectangular column and µ is the
perimeter multiplier of d: in this case, µ = 1.5 . If:
v ≤ vc : No shear reinforcement required.
v ≤ 2vc : Link reinforcement may be used.
v > 2vc : Alternative proven system to be used.
For preliminary design, it is sufficient to pass Step 1 and to know that v ≤ 2vc at the
critical perimeter.
145 Dr C. Caprani
BE Structural Eng – Project III
146 Dr C. Caprani
BE Structural Eng – Project III
Hollowcore Slabs
147 Dr C. Caprani
BE Structural Eng – Project III
Composite Hollowcore
148 Dr C. Caprani
BE Structural Eng – Project III
Table for Composite Hollowcore floors tells us that a 200mm deep slab with a 50 mm
structural screed will carry an imposed (SLS) load of 11.5 kN/m2. Therefore, try a
200 mm deep hollowcore slab.
ULS load,
wu = 1.4(4.3) + 1.6(5) =14.0 kN/m2
The 1.2 m is the width of the precast unit; hence the line load on the unit is 1.2×14
kN/m. The ultimate moment capacity of the composite floor is 188.3 kNm/m hence
the floor has ample ultimate capacity.
149 Dr C. Caprani
BE Structural Eng – Project III
Typical span
Element Span/depth ratio
(m)
Floor UBs 4 – 12 15 – 18
Slimfloor 6–9 25 – 28
Castellated beams 4 – 12 14 – 17
Transfer beams 6 – 30 10
Trusses supporting floors 6 – 30 10
Plate girders 10 – 30 10 – 12
Parallel chord roof truss 10 – 100 12 – 20
Pitched roof truss 8 – 20 5 – 10
Light roof beams 6 – 60 18 – 30
Lattice roof truss 5 – 20 12 – 15
Space frame (w/ pre-camber) 10 – 100 15 – 30
Columns: UC: single storey 2–8 20 – 25
: multi storey 2–4 7 – 18
Columns: hollow sections: single storey 2–8 20 – 35
: multi storey 2–4 7 – 28
Columns:
150 Dr C. Caprani
BE Structural Eng – Project III
Slab:
• RC: 125-150 mm thick
• Metal deck: 115-175 mm, spanning 2.5 to 3.6 m.
• Precast units: 75-100 mm with 50-200 mm topping can span 3 to 8 m.
A 150 mm deep overall slab with 60 mm decking spans about 2.8-3.5 m depending
on mesh and concrete density.
Beam:
Initially size as 80% of non-composite.
For a better check, size beam with Z = (non-composite Z)×(1.6 to 2).
151 Dr C. Caprani
BE Structural Eng – Project III
7.1 Introduction
Car park layout design usually falls to the structural engineer. This is because the
structural layout and car-park design are integral to one another. Simply put, you
can’t put a column in a driving lane. Balancing the car park and structural layout is
important for the floors overhead. Often two different structural layouts are used for
the car park and for (say) overhead offices. A transfer structure is needed in between
to link these two layouts.
Defintions
Bay: the parking space for a single vehicle.
Aisle: the driving lane adjacent to the parking bays.
Bin: A ‘unit’ comprising bays on both sides of an aisle.
Usage
The layout of a car park depends critically on its foreseen use:
• Short or long stay;
• Regular or irregular users;
• Small or large scale parking.
152 Dr C. Caprani
BE Structural Eng – Project III
Notes:
153 Dr C. Caprani
BE Structural Eng – Project III
Note: Width includes wing mirrors, Height excludes roof bars/boxes etc. Taken
from a 1999/2000 UK Review.
The actual design criteria (given later) are governed by the swept path of a large car.
In the case of special design, outside the limits of the recommendations, the figure
below must be used to verify the design’s adequacy. Using CAD software, the figure
below can be superimposed on any part of a proposed layout to verify that there are
no clashes. This is not necessary for usual standard designs, however.
154 Dr C. Caprani
BE Structural Eng – Project III
Notes:
155 Dr C. Caprani
BE Structural Eng – Project III
For driving lanes we allow for the largest of vehicles. However, the individual
parking bays can be designed for a more reasonable vehicle size. Lanes must also be
designed to allow cars back out of a space. Therefore, 1-way and 2-way lanes are of
similar width. Applying the swept path configuration, the recommendations for
parking dimensions are given as:
156 Dr C. Caprani
BE Structural Eng – Project III
The next figure illustrates the implications for the bin layout. For 3 spaces, the 2.4 m
bay width allows for 300 mm extra (over the minimum width of 2.3 m) in which the
column can be placed.
In the figure above, the dimension A is usually about 0.9 m to the column centre line.
157 Dr C. Caprani
BE Structural Eng – Project III
A 2×B A
L
Lx = 7.2 m
Ly Ly Ly Ly
By applying the requirements for A and B, we can relate the inset to the spacing Ly:
8.6
8.4
1-way
Column Spacing (m)
8.2
EvenTransverse
2-way
8
7.8
7.6
7.4
7.2
0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
Inset to Centre Line of Columns (m)
158 Dr C. Caprani
BE Structural Eng – Project III
Lines of
1-way
This layout also works for post-tensioned RC floor-slabs (e.g. Dublin Airport).
159 Dr C. Caprani
BE Structural Eng – Project III
In such cases, transition ramps are used at the start and end of each ramp:
160 Dr C. Caprani
BE Structural Eng – Project III
The storey height is related to the headroom required as shown in the next figure. The
minimum headroom is 2.10 m and this will allow for all MPVs and 4×4s. Where
provision is required for high-top converted vehicles for disabled people, the
minimum headroom is 2.60 m.
161 Dr C. Caprani
BE Structural Eng – Project III
7.5 Ventilation
Car parks must be adequately ventilated due to noxious fumes. To save on
mechanical ventilation, natural ventilation is used as much as possible. For this,
openings should have an aggregate area of 2.5% of the area of the parking space at
that level and be distributed so as to provide effective cross ventilation.
This requirement often results in ‘planters’ around single-storey basement car parks.
Sketch an example:
162 Dr C. Caprani
BE Structural Eng – Project III
7.6 Miscellaneous
• Durability requirements for car parks are usually more onerous than other
structures as chlorides can be brought in by the vehicles.
• Fire protection of structures needs to be considered, especially for structural steel
elements, though uncased steel elements are usual in car parks.
• Traffic management can be difficult for large car parks; adequate design is
essential.
• The car park surface is usually sloped for drainage: the minimum fall is 1:60, the
maximum, 1:20.
• Expansion joints need to be detailed to avoid water ingress.
163 Dr C. Caprani
BE Structural Eng – Project III
8. Examples
Problem
Do a load takedown for the following structure and determine the ultimate and
service loads for the pad footings under the columns.
Edge Beams 300×400 Dp.
50
Plan
Lightweight roof
4@ No internal columns
3m
c/c 100-100-100 cavity
wall
Section
Use: Speculative offices.
Columns are evenly spaced.
Plant rooms located over lift/stair cores.
Ignore takedown for lift/stair cores – only do it for the columns.
164 Dr C. Caprani
BE Structural Eng – Project III
Solution
Structural Actions
A flat slab is a two-way spanning reinforced concrete slab. Therefore the tributary
areas are derived from those of the ‘continuous’ form of tributary lengths studied
previously. The cladding is non-structural: the masonry is supported on the edge-
beam at each storey level. The edge beams are supported at each level by the
perimeter columns. The roof trusses span N-S onto each perimeter column.
Exercise: you should be able to sketch the actions/load paths just described.
Notes:
165 Dr C. Caprani
BE Structural Eng – Project III
Element Loads
The loads upon each element are required:
Σ= 6.6 5.0
wser = 6.6 + 5.0 = 11.6 kN/m2 wult = 1.4 × 6.6 + 1.6 × 5.0 = 17.24 kN/m2
Σ= 5.35 0
Beam downstand (24 × 0.125 × 0.3) = 0.9 kN/m service, 1.26 kN/m ult.
Composite Load Factor: 1.4. The perimeter line load caused by the wall is:
wult = 0.6 (proportion of wall) × 3 m (storey height) × 6.23 kN/m2 + 1.26 = 12.5 kN/m
wser = 12.5/1.4 = 9 kN/m
166 Dr C. Caprani
BE Structural Eng – Project III
Truss 0.2
Purlins 0.1
Glazing 0.5
Services 0.1
Imposed (BS 6399: Pt. 3: 1988) 0.6
Σ= 0.9 0.6
wser = 0.9 + 0.6 = 1.5 kN/m2 wult = 1.4 × 0.9 + 1.6 × 0.6 = 2.22 kN/m2
Composite Load Factor: 2.22/1.5 = 1.48, so dead load is slightly more important.
Tributary Areas
3 9
Tributary areas are worked on the basis of the L , L and L formulae for
8 8
continuous spans. As a result, the columns take many different tributary areas:
6.7 F 15.7
F
Typ. Int. 41.9
167 Dr C. Caprani
BE Structural Eng – Project III
Σ= 2770 2009
Σ= 1355 927
168 Dr C. Caprani
BE Structural Eng – Project III
Σ= 596 412
Notes:
169 Dr C. Caprani
BE Structural Eng – Project III
Quicker Solution
3.3 A B
6.7 C
6.7
Note that the calculations that remain unchanged are the ultimate loads for the floor,
perimeter, and roof loadings. Thus:
Column C
Pult = 3 × 6.25 × 6.7 × 17.5 = 2200 kN; Pser = 2200/1.486 = 1480 kN
Column B
Pult = 2200/2 + 6.25 × 11.2 + 10 × 6.25 × 2.22
= 1100 + 70 + 139 = 1310 kN; Pser = 1310/1.486 = 881 kN
Column A
Pult = 2200/4 + 70 + 139/2 = 690 kN; Pser = 690/1.486 = 464 kN
Compare to the previous results, and examine where the inaccuracies come from. The
results are approximate, but this is good enough for many preliminary purposes.
170 Dr C. Caprani
BE Structural Eng – Project III
Problem
Do a complete preliminary design for slabs, beams and columns of this 4-storey
office building. There is no basement car-parking.
30 m PLAN
11 m N
The building is stabilised with shear walls. Assume an in-situ slab spanning onto
beams and (continuous) beams spanning onto columns.
6m
171 Dr C. Caprani
BE Structural Eng – Project III
Solution
In the following each element is considered in turn. For each element identify the
four steps just described.
Dead load:
24×0.3 (slab s.w.) + 0.5 (ceilings + services)
= 7.7 kN/m2
Imposed load:
2.5 (occupancy) + 1 (partitions) = 3.5 kN/m2
172 Dr C. Caprani
BE Structural Eng – Project III
w = 16.4 kN/m
A C
B
7 4
76 kNm
The spans are uneven and so we cannot assume that the moment at B is wL2/8
because we don’t know which L to take. Conservatively, we could take the large L
and design for it:
wL2 16.4 × 7 2
( M B ) AB = = = 101 kNm
8 8
which is much bigger than the same moment for the span BC:
wL2 16.4 × 42
( M B ) BC = = = 33 kNm
8 8
( M B ) AB + ( M B ) BC
MB = = 67 kNm
2
The smart way is to split the difference in inverse proportion to the lengths (why?):
173 Dr C. Caprani
BE Structural Eng – Project III
1/ 7
( M B ) AB = 101 − 68 × = 76 kNm
1/ 7 + 1/ 4
1/ 4
( M B ) BC = 33 + 68 × = 76 kNm
1/ 7 + 1/ 4
As the answers are the same it means the joint is balanced ( ∑ Moments about B = 0 ).
⎛ 76 ×106 ⎞
ρs ≈ ⎜ 2 ⎟
π = 0.327
⎝ 1000 × 272 ⎠
ρs
As = bd
100
0.327
= × 1000 × 272
100
= 890 mm 2
174 Dr C. Caprani
BE Structural Eng – Project III
4 7
PLAN
Hence the loadwidth on the spine beam is 2.5 + 4.4 = 6.9 m and the load per meter is:
wu = 16.4 × 7 = 115 kN/m
The load to the N-S beams is appears to be zero as they span in the same direction as
the slab. However they do attract load as they must deflect the same as the adjacent
slab. So we take maybe 0.5 × loadwidth of a 2-span bay. Hence a 45° load-spread
gives a loadwidth of 3 m (for the 6 m column spacing); hence use a 1.5 m loadwidth
giving w = 25 kN/m.
w = 25 kN/m
w = 25 kN/m
w = 115 kN/m
w = 25 kN/m
w = 43 kN/m
175 Dr C. Caprani
BE Structural Eng – Project III
The actual values from a full analysis are 14 / 119 / 47 kN/m. The differences are
caused by the uneven spans. Even still though, our values are good enough.
The spans in the spine beam are all even and so the approximate formulae for
moments and shears apply:
wL2 wL2
MB = MC =
10 12 w = 115 kN/m
6
3wL 9 wL
VA = VB = VC = wL
8 8
If we had carried on the more exact results, allowed for the downstand, and carried
out a full ‘proper’ analysis the moments would be 474 / 354 kNm. Hence our
approximate design is still ‘ballpark’.
Note that to check the worst shear force we do not choose the highest support
reaction value.
176 Dr C. Caprani
BE Structural Eng – Project III
To determine the breadth we will examine the maximum shear stress and limit it to
2.0 N/mm2:
V V 431×103
= 2.0 ⇒ bw = = = 532 mm
bw d 2.0d 2.0 × 405
177 Dr C. Caprani
BE Structural Eng – Project III
This is very wide. We can reduce it by increasing d. A breadth of 300 would fit in
nicely with the preliminary column dimension, hence:
V V 431×103
= 2.0 ⇒ d= = = 716 mm
bw d 2.0bw 2.0 × 300
725 425
300
This is drawn to scale (more or less!): the important point is that it looks in
proportion and this is usually as good a guide as the numbers.
For the main tension steel we use the quick formula:
M 414 × 106
As = = = 2026 mm 2
300d 300 × 681
3 T32 bars provide 2413 mm2. Choose this to give that extra little bit of ‘room’ in our
design.
178 Dr C. Caprani
BE Structural Eng – Project III
Beam N and Beam S will be the same dimensions as this beam but will have different
steel (and probably each have the same) to this beam for ease of construction.
Also note that having the width of the beam the same as that of our column eases the
formwork at the beam/column junctions.
3/8×4
4m
5/8×4
5/8×7
7m
3/8×7
PLAN
179 Dr C. Caprani
BE Structural Eng – Project III
For the roof load assume steel roof trusses spanning the full 11 m. Hence, use the
same roof loading as per the Load Takedown example:
180 Dr C. Caprani
BE Structural Eng – Project III
The façade columns will not be critical in this case (Why? Check one).
181 Dr C. Caprani
BE Structural Eng – Project III
Thus a square column is: h = 123650 = 352 mm , which is significantly greater than the
300 square columns. The next level of detail is:
N Acol − 14
ρ≈
3
⎡ 3 ⎤
⎢⎣ 0.35 × 40 + 100 ( 0.67 × 460 − 0.35 × 40 ) ⎥⎦ 350 > 2473 × 10
2 3
So the columns are acceptable at this level of design. The area of steel required is:
3
Asc = × 3502 = 3676 mm 2
100
182 Dr C. Caprani
BE Structural Eng – Project III
Problem
Using the building example from the load takedown Design Exercise:
Edge Beams 300×400 Dp.
50
Plan
Lightweight roof
No internal
4@ 100-100-100 cavity wall
3m 40% glazing
Section
Do the following:
1. Check the slab is adequate, without detailed analysis;
2. Check that punching shear is adequate for the slab and columns shown;
3. Check that the columns as shown are adequate.
In all cases propose appropriate design changes as required.
183 Dr C. Caprani
BE Structural Eng – Project III
Solution
Assemble the pertinent information first: from the load takedown solution:
• E-W spacing is: 50/8 = 6.25 m;
• N-S spacing is: 20/3 ≈ 6.7 m.
• wult = 17.24 kN/m2;
• Pult = 2770 kN.
Check that punching shear is adequate for the slab and columns shown
• Internal Column:
Vt = 6.25 × 6.7 ×17.24 = 722 kN
830 × 103
vmax = = 2.92 N/mm 2
1200 × 237
184 Dr C. Caprani
BE Structural Eng – Project III
830 ×103
v1.5 d = = 0.87 N/mm 2
4044 × 237
If we conservatively take vc = 0.5 N/mm 2 , then vc ≤ v1.5d ≤ 2vc and shear
reinforcement is to be provided.
Check next perimeter, 1.5d + 0.75d = 2.25d from column face:
u2.25 d = u1.5 d + 8 × 0.75d = 5466 mm
830 × 103
v1.5 d = = 0.64 N/mm 2
5466 × 237
Again, vc ≤ v1.5d ≤ 2vc and a second perimeter of shear reinforcement is to be
provided. It is not necessary to check the next perimeter as it is clear it will be
below the conservative value vc = 0.6 N/mm 2 , or the actual value, which should
be around vc = 0.65 N/mm 2 .
Result: expect 2 perimeters of shear reinforcement.
• Perimeter Column:
722
Veff = ×1.4 = 505 kN
2
Maximum shear at face of column:
u0 = 3 × 300 = 900 mm
505 ×103
vmax = = 2.37 N/mm 2
900 × 237
185 Dr C. Caprani
BE Structural Eng – Project III
Thus a square column is: h = 138500 = 372 mm , which is significantly greater than the
300 square columns.
Result: increase column size to 350 square, at least for internal ground floor.
186 Dr C. Caprani
BE Structural Eng – Project III
Problem
The architect informs you that two WC/fire-escape-staircore blocks are required on
each floor, as well as two other fire-escape staircores (as shown in the figure); you
are required to integrate these elements into your scheme and to advise the architect
as to their location. In doing so, you should pay due regard to lateral stability, any
expansion joints and travel distance in deciding your layout.
(b) Assuming a reinforced concrete solution, size the principal members (beam,
slab and column) for a typical floor, choosing the most probable critical
element in each case. For each element, indicate the approximate areas of
reinforcement required.
(50%)
187 Dr C. Caprani
BE Structural Eng – Project III
55000
15000 20000
45000
15000
FULL HEIGHT
ATRIUM
EXTENT OF DOUBLE
15000 STOREY−HEIGHT
ENTRANCE
ENTRANCE
21500 12000
PLAN
ALL DIMENSIONS IN
MILLIMETRES
2500
GLAZED EXTENT OF
ROOF ATRIUM
5 @ 3000
55000
FRONT ELEVATION
6x7.5m FIRE
WC
ESCAPE/WC BLOCK
6x3m FIRE ESCAPE
STAIRS
45000
FIGURE Q.2
188 Dr C. Caprani
BE Structural Eng – Project III
Solution
Instead of giving answers, this is left to you to try. What is given, however, is the
feedback given to a group of students after reading their answers at the problem.
They made the mistakes so you don’t have to!
General
Overall few got the right balance of text & sketches for Part (a).
Make sure put all of your work in the answer book – even the doodles.
There were a few cases of “magic” numbers.
Lift cores should have been mentioned in the question.
Scheme
Consider expansion joints carefully – make your choice & stick to it.
Having looked at alternative grids, choose one & draw it properly.
There were some very large spans – study the “Economic Span Ranges” carefully.
There was no need for shear walls.
Use rough judgment to size some of Pt. (a) e.g. roof truss member sizes.
Preliminary Design
Errors with basic bending moments, e.g. wL2/8 and PL/4.
Know the design shortcuts, e.g. tributary lengths/areas for beams/columns.
Errors in the use of “quick” formulae (e.g. wL2/10) – make sure you understand
where they come from & their limitations.
Do not confuse “critical” & “typical” – the question asked for “typical”
beams/cols/slab – not the very difficult unusual ones.
Drawings
Sketches and plans were very poor.
The Plan needs to fill as much of a page as possible & drawn to scale (graph paper).
189 Dr C. Caprani
BE Structural Eng – Project III
190 Dr C. Caprani
BE Structural Eng – Project III
Problem
The architect informs you that two WC/fire-escape-staircore blocks are required on
each floor, as well as two other fire-escape staircores (as shown in the figure); you
are required to integrate these elements into your scheme and to advise the architect
as to their location. In doing so, you should pay due regard to lateral stability, any
expansion joints and travel distance in deciding your layout.
(d) Assuming a reinforced concrete solution, size the principal members (beam,
slab and column) for a typical floor, choosing the most probable critical
element in each case. For each element, indicate the approximate areas of
reinforcement required.
(50%)
191 Dr C. Caprani
BE Structural Eng – Project III
192 Dr C. Caprani
BE Structural Eng – Project III
Solution
193 Dr C. Caprani
BE Structural Eng – Project III
194 Dr C. Caprani
BE Structural Eng – Project III
195 Dr C. Caprani
BE Structural Eng – Project III
196 Dr C. Caprani
BE Structural Eng – Project III
197 Dr C. Caprani
BE Structural Eng – Project III
198 Dr C. Caprani
BE Structural Eng – Project III
Problem
An architect has sent you preliminary sketches of a 4-storey apartment building over
an open-air car park; as shown in Figure Q.2. You are required to advise the architect
whether or not expansion joints are needed. In addition you need to assess whether
lateral stability is achieved with the proposed layout.
(b) Assuming a reinforced and/or precast concrete solution, size the principal
members for a typical floor, and a column at car park level – choosing the
critical element in each case. For each element, indicate the approximate areas
of reinforcement required.
(50%)
199 Dr C. Caprani
BE Structural Eng – Project III
10000
12000
Stair/Lift
A Core A
Entrance
10000
6000
Site Boundary
Corridor
12000
10000
Car Services
Park
Access
Entrance
Car Park
SECTION A-A
(All dimensions in mm)
200 Dr C. Caprani
BE Structural Eng – Project III
Solution
General
Overall few got the right balance of text & sketches for Part (a).
Those who used graph paper seemed to provide better sketches.
The term “transfer beam” has a particular meaning.
Scheme
Shear wall overkill – only a few thought of the use of the building.
No need to “assume” preliminary sizes – fill in after prelim design.
Do the service cores go into the car park?
The car park layout should have been first – the “top down approach”.
Parking dimensions not adhered to – narrow driving aisles with columns in them!
Drainage info usually not needed in a structural scheme design.
Preliminary Design
The numbers generally seemed good.
Inappropriate formulae used: e.g. wL2/10 for a simply supported span!
Rebar for slabs is specified at a spacing, not a number of bars, e.g. T16-200 not 4T16.
Drawings
Sketches and plans were very poor.
Every line has a meaning: not enough information on the sketches.
The Plan needs to fill as much of a page as possible & drawn to scale (graph paper).
Draw gridlines on your plan.
Show cols as quick square dots (i.e. with a solid hatching).
Isometric drawings are not needed.
201 Dr C. Caprani
BE Structural Eng – Project III
Problem
An architect has sent you preliminary sketches of a 4-storey (3.5 m floor to floor)
development as shown in Figure Q.2. The client wants flexibility in the use of the
building:
• Initially the building is to be used as apartments with the layout shown in Figure
Q.2. Sound and fire isolation of dwellings is important. The building will be
masonry clad with 25% glazing.
• The use may change to open-plan offices with fully glazed elevations.
The client understands that there are cost implications for this and that works would
be necessary to change the use. Also, the Architect understands that some structural
elements may be necessary in the larger apartments.
Part (a)
Propose a structural scheme for the building, giving sufficient information on:
1. The provision of lateral stability when the building is to be used as apartments,
taking any expansion joints into account, if deemed necessary.
2. The layout of the vertical load transfer structure; the floor plate; beams, and;
structural walls, as applicable to your scheme. This should reflect the possible
change of use.
3. The works necessary to achieve lateral stability if in the future the use is to change
to open-plan offices.
(50%)
Part (b)
Important: In Part (b), only consider the loading appropriate when the building is
used as apartments.
202 Dr C. Caprani
BE Structural Eng – Project III
Assuming a reinforced and/or precast concrete solution, size the principal members
(beam, floor slab, and column) for a typical floor, choosing the critical element in
each case. For each element, indicate the approximate areas of reinforcement
required.
(50%)
203 Dr C. Caprani
BE Structural Eng – Project III
30000
10000
10000
Stairs and lift
Entrance
27500
6000 6000 6000 6000 6000
7500 Corridor
20000
12000 15000
3000
PLAN
(All dimension in mm)
FIGURE Q.2
204 Dr C. Caprani
BE Structural Eng – Project III
Solution
205 Dr C. Caprani
BE Structural Eng – Project III
206 Dr C. Caprani
BE Structural Eng – Project III
207 Dr C. Caprani
BE Structural Eng – Project III
208 Dr C. Caprani
BE Structural Eng – Project III
209 Dr C. Caprani
BE Structural Eng – Project III
210 Dr C. Caprani
BE Structural Eng – Project III
9. References
• Ivan Margolius, Architects + Engineers = Structures, Wiley Academy, 2002.
• Pier Luigi Nervi, Aesthetics and Technology in Building, Harvard University
Press, 1966.
• Eladio Dieste, La Estructura Ceramica, 1987.
• Bill Addis, Creativity and Innovation; The Structural Engineer’s Contribution
to Design, Architectural Press, 2001.
• H. Seymour Howard, Jr., Structure: An Architect’s Approach, McGraw-Hill,
1966.
• Alan Holgate, The Art in Structural Design, Clarendon Press, 1986.
• Eduardo Torroja, The Structures of Eduardo Torroja, F.W. Dodge
Corporation, 1958.
• Yasmin Sabina Khan, Engineering Architecture; The vision of Fazlur R. Khan,
W.W. Norton, 2004.
• Angus Macdonnald, Structure & Architecture, 2nd edn., Architectural Press,
1997.
• Malcolm Millais, Building Structures; From Concepts to Design, 2nd edn.,
Spon Press, 2005.
• Peter Rice, An Engineer Imagines, Artemis, 1997.
• Christian Menn, Prestressed Concrete Bridges, Birkhauser, 1990.
• David Billignton, The Tower and The Bridge; The New Art of Structural
Engineering, Princeton University Press, 1983.
• David Billington, Robert Maillart and The Art of Reinforced Concrete, MIT
Press, 1989.
• Anthony Hunt, Tony Hunt’s Structures Notebook, 2nd edn., Architectural
Press, 2003.
• Philip Garrison, Basic Structures for Engineers & Architects, Blackwell, 2005.
• Spiro Pollalis, What is a Bridge? The Making of Calatrava’s Bridge in Seville,
MIT Press, 1999.
211 Dr C. Caprani