1. The document provides unit rates and remarks for various construction works including excavation, filling, plastering, masonry, and concrete works.
2. Unit rates are provided for excavation by manual and hydraulic methods, filling with sand, antitermite treatment, masonry works, concrete works, centering and shuttering, reinforcement, and plastering/finishing works.
3. Rates are specified separately for works in the ground floor, first floor, second floor, third floor, fourth floor, and fifth floor as applicable.
1. The document provides unit rates and remarks for various construction works including excavation, filling, plastering, masonry, and concrete works.
2. Unit rates are provided for excavation by manual and hydraulic methods, filling with sand, antitermite treatment, masonry works, concrete works, centering and shuttering, reinforcement, and plastering/finishing works.
3. Rates are specified separately for works in the ground floor, first floor, second floor, third floor, fourth floor, and fifth floor as applicable.
Earth work excavation of foundation in all kinds of soil with in 59m initial lead and 1.50m initial lift including rough dressing breaking clods maximum 5cm to 7 cm & laying in layers not 1 exceding 0.3m depth for the work complete as directed by incharge.
Upto 1.5m depth Manual cum 137.37
With Hydraulic Excavator cum 50.00 Supplying and filling in foundation trenches and plinth with sand well watered and rammed in layers not exceeding 23cm in depth with all lead and lift including cost, conveyance, 2 cum 864.81 royalties, taxes of the material, cost of all labour, T&P etc., required for
Providing and applying of Antitermite treatment before
construction at different stage as per specification and the holes should be pluged with filling materials including cost of 3 sqm 117.30 all materials, labour charges, conveyance and all taxes, hire charges of m
Laterite stone masonry in C.M(1:6) in Foundation & Plinth.
Cum 4,359.60 Providing Plain Cement concrete PCC (1:3:6) below raft, ramp using 40 mm nominal size Graded hard crusher broken granite stone aggregate, mechanically mixed, placed in 4 foundation and compacted by vibration including labour, Cum 5,149.94 curing complete
Rigid and smooth Steel centering and shuttering at all heights
for raft, column,beam, lintel, chajja, stair case, plinth beam 5 and ramp etc., works using required nos of vertical and horizontal supports of scaffolding with joists, N.G. rails and channels
5.01 GF Sqm. 421.72
5.02 1st Sqm. 506.06 5.03 2nd Sqm. 607.27 5.04 3rd Sqm. 728.73 5.05 4th Sqm. 874.47 5.06 5th Sqm. 1,049.37 R.C.C. work of M-25 in following works using 12 mm. to 20 mm. size (20 mm. not less than 50%) hard black crusher broken granite stone chips of approved quality from approved quarry including hoisting, lowering, laying and compacting concrete, watering curing and finishing the exposed surfaces smooth with cost, conveyance, royalties, taxes of all materials with all labour,labour cess and T & P required for the work 10 etc. complete in all respect but excluding the cost and conveyance of Tor steel and binding wire of 18 to 20 gauge, labour and centering & shuttering charges for straightening, cutting, bending, binding and tying the grills and placing in proper position and as per the direction of the Engineer-in- charge.
10.01 GF Cum. 5,264.25
10.02 1st Cum. 5,346.21 10.03 2nd Cum. 5,440.47 10.04 3rd Cum. 5,536.62 10.05 4th Cum. 5,646.90 10.06 5th Cum. 5,773.45 Supplying Cutting, straightening or bent up Fe-500D tor steel of primary steel producers such as SAIL / Tiscon / RINL / JINDAL STEEL / SHYAM STEEL (grade Fe-500D) etc. including bending, binding, welding and jointing if necessary and tying the grills and placing in position as required for R.C.C. Work and for providing fan hooks as required, hoisting, lowering, laying including cost, conveyances, taxes of tor steel and 11 binding wires of 18 to 20 gauge and labour required for the work for bending, binding and tying the grills in all floors with labour cess etc. (payment will be made on standard weight of B.I.S. for or tor steel only) etc. complete as per specification & direction of Engineer-in-charge.
11.01 GF Qntl. 6,029.70
11.02 1st Qntl. 6,052.88 11.03 2nd Qntl. 6,077.21 11.04 3rd Qntl. 6,109.94 11.05 4th Qntl. 6,144.29 11.06 5th Qntl. 6,180.37 Fly Ash brick masonry in cement mortar (1:6) in foundation & plinth using Fly Ash bricks of 23 x 11 x 8 cm size having a crushing strength of not less than 75 kg./sqcm with dimensional tolerance ± 2% including splays cutting circular moulding chamfering and corbelling and similar such type of works with all necessary projections watering and curing and 12 scaffolding after immersing the bricks in water at least for six hours before use including cost, conveyance, royalties and taxes of all materials with all labour,labour cess and T & P required for the work complete in all respect as per direction of Engineer-in-Charge.
12.01 GF Cum. 4,370.43
12.02 1st Cum. 4,630.01 12.03 2nd Cum. 4,928.52 12.04 3rd Cum. 5,323.38 12.05 4th Cum. 5,718.16 12.06 5th Cum. 6,172.16 Supplying all materials, labour, T&P and providing 12mm thick cement plaster (1:6) on brickwork inclding watering, curing,scaffoding, cost, conveyance,royalities,taxes of all 13 materials to worksite etc all complete as per specification and direction of the Engineer in charge
13.01 GF Sqm. 140.97
13.02 1st Sqm. 144.20 13.03 2nd Sqm. 147.53 13.04 3rd Sqm. 150.95 13.05 4th Sqm. 154.48 13.06 5th Sqm. 158.12 Providing 16 mm thick cement plaster with cement mortar of mix (1:6) with screened and washed sharp sand for mortar and finished smooth to the rough surface of walls in all heights after racking out joints including watering,scaffoding and curing, rounding of corners, providing grooves where ever necessary with cost, conveyance, royalties and taxes of all 14 materials with cost of all labour,labour cess, T&P, and scaffolding required for the work etc. complete in all respect as directed by the Engineer in charge.
14.01 GF Sqm. 199.83
14.02 1st Sqm. 207.82 14.03 2nd Sqm. 216.22 14.04 3rd Sqm. 225.03 14.05 4th Sqm. 234.28 14.06 5th Sqm. 243.99 Providing Cement washing one coat including watering,scaffoding, curing, cost all materials, labour and T&P 15 etc complete as per requirement as directed by Engineer-in- Charge
15.01 GF Sqm. 13.89
15.02 1st Sqm. 14.27 15.03 2nd Sqm. 14.67 15.04 3rd Sqm. 15.09 15.05 4th Sqm. 15.53 15.06 5th Sqm. 15.99 Finishing plastered surfaces of walls with Cement based Putty & making smooth to receive painting including cost of Putty 16 as per requirement as directed by Engineer-in-Charge
16.01 GF Sqm. 71.38
16.02 1st Sqm. 72.69 16.03 2nd Sqm. 74.03 16.04 3rd Sqm. 75.42 16.05 4th Sqm. 76.84 16.06 5th Sqm. 78.31 Priming one coat with any approved primer including cost of 17 material & labour as per requirement as directed by Engineer- in-Charge 17.01 GF Sqm. 59.51 17.02 1st Sqm. 60.95 17.03 2nd Sqm. 62.42 17.04 3rd Sqm. 63.95 17.05 4th Sqm. 65.51 17.06 5th Sqm. 63.95 Priming one coat with any approved primer including cost of 18 material & labour as per requirement as directed by Engineer- in-Charge -outside 18.01 GF Sqm. 59.51 18.02 1st Sqm. 61.90 18.03 2nd Sqm. 64.41 18.04 3rd Sqm. 67.05 18.05 4th Sqm. 69.82 18.06 5th Sqm. 72.73 Wall painting TWO coats with plastic emulsion paint of approved shade on new work to give an even shade including 18 cost of brushes and putty including cost of paint. 18.01 GF Sqm. 78.83 18.02 1st Sqm. 80.38 18.03 2nd Sqm. 81.97 18.04 3rd Sqm. 83.62 18.05 4th Sqm. 85.31 18.06 5th Sqm. 87.05 Wall painting 2 coats with weather paint of approved shade on wall surface to give an even shade including cost of 18 brushes and putty including cost of paint scrapping, cleaning rubbing, scaffolding etc. 18.01 GF Sqm. 73.34 18.02 1st Sqm. 75.92 18.03 2nd Sqm. 78.63 18.04 3rd Sqm. 81.48 18.05 4th Sqm. 84.47 18.06 5th Sqm. 87.60 Providing Two Coat enamel paint over a one coat of Priming to grills in front of window works with any approved quality 19 of enamel paint and primer including cost of material & labour as per requirement as directed by Engineer-in-Charge
19.01 GF Sqm. 135.54
19.02 1st Sqm. 141.23 19.03 2nd Sqm. 147.20 19.04 3rd Sqm. 153.48 19.05 4th Sqm. 160.06 19.06 5th Sqm. 166.98 Providing 2.5cm thick Grading Concrete over roof slab with cement concrete (1:2:2) using 6mm size black hard granite crusher broken chips and screened & washed sharp sand for mortar and finished smooth to the rough surface of slab including watering and curing with cost, conveyance, royalties 20 and taxes of all materials with cost of all labour, labour cess and T&P required for the work etc. complete in all respect as directed by the Engineer in charge.(Over 5th floor)
20.01 Terrace floor sqm 533.56
Supply, Fitting and fixing of vertified tiles (colour/printed ,Size 600mm X 600mm) (Border Wall Tile - (Make -Johnson / Khajaria/Somali)IS:13755 of approved make laid on 20mm 24 thick cement mortar (1:4) (1 cement :4 Course sand) and filling joints with white cement of approved quality including cost, conveyance, taxes, cost of all labour etc., complete.
24.01 Ground floor sqm 926.71
24.02 1st floor sqm 936.32 24.03 2nd floor sqm 946.41 24.04 3rd floor sqm 957.00 24.05 4th floor sqm 968.12 24.06 5th floor sqm 979.80 Supply, Fitting and fixing of ceramic tiles with approved make conforming to IS: 13755 laid on 20mm thick cement mortar (1:4) (1 cement :4 Course sand) and filling joints with 25 white cement of approved quality including cost, conveyance, taxes, cost of all labour etc., complete.
25.01 Ground floor sqm 709.94
25.02 1st floor sqm 719.55 25.03 2nd floor sqm 729.64 25.04 3rd floor sqm 740.23 25.05 4th floor sqm 751.36 25.06 5th floor sqm 763.04 Fixing granite tiles of above 0.4 Sqm of 20 mm thick in treads and raise of steps in stair case and dado side of the steps of thickness 150 mm over a 25mm thick bed of cement mortar 26 1:1 (1 cement : 1 sand) jointed with neat cement slurry mixed with pigment to match the shades on the tiles etc., complete. 26.01 Ground floor sqm 1,649.59 26.02 1st floor sqm 1,670.32 26.03 2nd floor sqm 1,692.08 26.04 3rd floor sqm 1,714.92 26.05 4th floor sqm 1,738.92 26.06 5th floor sqm 1,764.11 26.07 terrace sqm 1,790.56 Fixing of chequred tile in floors treads or steps and landing on 25mm thick bed of cement mortar 1:1 (1cement : 1sand) jointed with neat cement slury mixed with pigment to match 26 the shades of the tiles including rubbing and polishing complete excluding cost of precast tiles etc.
26.01 Ground floor sqm 534.35
Providing 6 mm thick cement plaster with cement mortar of mix (1:4) with screened and washed sharp sand for mortar and finished smooth to the ceiling in all heights including watering, curing and scaffloding rounding of corners, 27 providing grooves where ever necessary with cost, conveyance, royalties and taxes of all materials with cost of all labour,labour cess, T&P, and scaffolding required for the work etc. complete in all respect as directed by the Engineer in charge. 27.01 Ground floor sqm 129.71 27.02 1st floor sqm 132.94 27.03 2nd floor sqm 136.27 27.04 3rd floor sqm 139.69 27.05 4th floor sqm 143.22 27.06 5th floor sqm 146.86
1 All cost are excluding GST & 12% GST will be added. 2 Cement will be recovered @ 250 per Bag 3 Steel will be recovered @ 45000 per MT