Pembinaan Bangunan Kekal Giatmara Mukah 361 Days Thu 18/6/20 Thu 4/11/21
Pembinaan Bangunan Kekal Giatmara Mukah 361 Days Thu 18/6/20 Thu 4/11/21
Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only
Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline
Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task
Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress
Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only
Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline
Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task
Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress
Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only
Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline
Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task
Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress
Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only
Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline
Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task
Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress
Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only
Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline
Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task
Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress
Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only
Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline
Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task
Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress
Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only
Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline
Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task
Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress