Pembinaan Bangunan Kekal Giatmara Mukah 361 Days Thu 18/6/20 Thu 4/11/21

This document outlines the schedule for the construction of a permanent building for GIATMARA Mukah in Sarawak, Malaysia over 361 days. It involves preliminary works like site possession, documentation, surveying and mobilization. Earthworks, piling works, and building works will be carried out. Piling works include test piles, load testing, pile integrity testing and installing 248 precast reinforced concrete piles of various sizes. Building works include structural works and architectural, mechanical and electrical works to complete the administration block.

Uploaded by

Kevin Chang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
99 views

Pembinaan Bangunan Kekal Giatmara Mukah 361 Days Thu 18/6/20 Thu 4/11/21

This document outlines the schedule for the construction of a permanent building for GIATMARA Mukah in Sarawak, Malaysia over 361 days. It involves preliminary works like site possession, documentation, surveying and mobilization. Earthworks, piling works, and building works will be carried out. Piling works include test piles, load testing, pile integrity testing and installing 248 precast reinforced concrete piles of various sizes. Building works include structural works and architectural, mechanical and electrical works to complete the administration block.

Uploaded by

Kevin Chang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

TENDER KALI KEDUA CADANGAN PEMBINAAN BANGUNAN KEKAL GIATMARA MUKAH, LOT 5907, BLOCK 48, MUKAH LAND

DISTRICT, MUKAH SARAWAK


ID Task Name Duration Start Finish 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half
0 PEMBINAAN BANGUNAN KEKAL GIATMARA MUKAH 361 days Thu 18/6/20 Thu 4/11/21 PEMBINAAN BANGUNAN KEKAL GIATMARA MUKA
1 1 Site Possession 0 days Thu 18/6/20 Thu 18/6/20 18/6 18/6
2 1.1 Site Possession 0 days Thu 18/6/20 Thu 18/6/20 18/6 18/6
3 2 Preliminaries and general work 361 days Thu 18/6/20 Thu 4/11/21 Preliminaries and general work
4 2.1 P&G documentation 361 days Thu 18/6/20 Thu 4/11/21 P&G documentation
5 2.2 Boundary and topograhphy 7 days Wed 1/7/20 Thu 9/7/20 Boundary and topograhphy
6 2.3 Mobilisation 7 days Tue 7/7/20 Wed 15/7/20 Mobilisation
7 2.4 Site Setting Out 7 days Tue 7/7/20 Wed 15/7/20 Site Setting Out
8 2.5 Installation of site office 14 days Thu 16/7/20 Tue 4/8/20 Installation of site office
9 2.6 Installation of worker's quarters 14 days Thu 16/7/20 Tue 4/8/20 Installation of worker's quarters
10 3 Site Clearance 7 days Thu 16/7/20 Fri 24/7/20 Site Clearance
11 4 Earthwork 37 days Mon 27/7/20 Tue 15/9/20 Earthwork
12 5 Piling Works 267 days Wed 16/9/20 Thu 23/9/21 Piling Works
13 5.1 Test Piles 7 days Wed 16/9/20 Thu 24/9/20 Test Piles
14 5.2 Load Test 7 days Fri 25/9/20 Mon 5/10/20 Load Test
15 5.3 Pile integrity test 7 days Tue 6/10/20 Wed 14/10/20 Pile integrity test
16 5.4 200mm X 200mm Precast RC. Piles (Total = 248pts.) 106 days Thu 15/10/20 Thu 11/3/21 200mm X 200mm Precast RC. Piles (Total = 248pts.)
17 5.4.1 Blok Pentadbiran (75pts.) 21 days Thu 15/10/20 Thu 12/11/20 Blok Pentadbiran (75pts.)
18 5.4.2 Bengkel PEL (25pts.) 10 days Thu 5/11/20 Wed 18/11/20 Bengkel PEL (25pts.)
19 5.4.3 Bengkel KFL (42pts.) 18 days Thu 12/11/20 Mon 7/12/20 Bengkel KFL (42pts.)
20 5.4.4 Blok Transit Lelaki (2pts.) 1 day Tue 8/12/20 Tue 8/12/20 Blok Transit Lelaki (2pts.)
21 5.4.5 Blok Transit Perempuan (29pts.) 11 days Wed 9/12/20 Wed 23/12/20 Blok Transit Perempuan (29pts.)
22 5.4.6 Pusat Sampah (4pts.) 2 days Fri 18/12/20 Mon 21/12/20 Pusat Sampah (4pts.)
23 5.4.7 RC Road Crossing - Main Access (38pts.) 14 days Tue 2/2/21 Fri 19/2/21 RC Road Crossing - Main Access (38pts.)
24 5.4.8 RC Road Crossing - Sesco Sub (17pts.) 7 days Mon 22/2/21 Tue 2/3/21 RC Road Crossing - Sesco Sub (17pts.)
25 5.4.9 Brickwall Fencing (16pts.) 7 days Wed 3/3/21 Thu 11/3/21 Brickwall Fencing (16pts.)
26 5.5 Bakau Piles 110 days Fri 23/4/21 Thu 23/9/21 Bakau Piles
27 5.5.1 Septic Tank & Manhole (661pts.) 21 days Fri 23/4/21 Fri 21/5/21 Septic Tank & Manhole (661pts.)
28 5.5.2 300mm wide Drain (1599pts.) 30 days Mon 24/5/21 Fri 2/7/21 300mm wide Drain (1599pts.)
29 5.5.3 300mm box culvert (39pts.) 7 days Mon 5/7/21 Tue 13/7/21 300mm box culvert (39pts.)
30 5.5.4 450mm box culvert (36pts.) 7 days Wed 14/7/21 Thu 22/7/21 450mm box culvert (36pts.)
31 5.5.5 Single Air Valve - Thrust Block (25pts.) 7 days Fri 23/7/21 Mon 2/8/21 Single Air Valve - Thrust Block (25pts.)
32 5.5.6 160mm dia. PN10 HDPE Pipe (1046pts.) 28 days Tue 3/8/21 Thu 9/9/21 160mm dia. PN10 HDPE Pipe (1046pts.)
33 5.5.7 150mm dia. DI pipe (161pts.) 10 days Fri 10/9/21 Thu 23/9/21 150mm dia. DI pipe (161pts.)
34 6 Building Work 254 days Fri 13/11/20 Wed 3/11/21 Building Work
35 6.1 Blok Pentadbiran 254 days Fri 13/11/20 Wed 3/11/21 Blok Pentadbiran
36 6.1.1 Structural Work 164 days Fri 13/11/20 Wed 30/6/21 Structural Work
37 6.1.1.1 Footing and stump 30 days Fri 13/11/20 Thu 24/12/20 Footing and stump
38 6.1.1.2 Ground floor beam 30 days Fri 11/12/20 Thu 21/1/21 Ground floor beam

Task Project Summary Rolled Up Baseline Inactive Milestone Start-only

Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only

Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline

Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task

Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress

APPL ENGINEERING SERVICES SDN BHD Page 1


TENDER KALI KEDUA CADANGAN PEMBINAAN BANGUNAN KEKAL GIATMARA MUKAH, LOT 5907, BLOCK 48, MUKAH LAND DISTRICT, MUKAH SARAWAK
ID Task Name Duration Start Finish 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half
39 6.1.1.3 Ground slab 30 days Thu 31/12/20 Wed 10/2/21 Ground slab
40 6.1.1.4 Ground floor column 21 days Thu 11/2/21 Thu 11/3/21 Ground floor column
41 6.1.1.5 First floor slab 30 days Fri 12/3/21 Thu 22/4/21 First floor slab
42 6.1.1.6 First floor beam 23 days Thu 1/4/21 Mon 3/5/21 First floor beam
43 6.1.1.7 First floor column 21 days Tue 4/5/21 Tue 1/6/21 First floor column
44 6.1.1.8 Staircase 21 days Wed 2/6/21 Wed 30/6/21 Staircase
45 6.1.2 Roofing work 65 days Wed 2/6/21 Tue 31/8/21 Roofing work
46 6.1.2.1 Roof slab 21 days Wed 2/6/21 Wed 30/6/21 Roof slab
47 6.1.2.2 Roof beam 21 days Tue 22/6/21 Tue 20/7/21 Roof beam
48 6.1.2.3 RC Plinth (Water Tank) 14 days Thu 1/7/21 Tue 20/7/21 RC Plinth (Water Tank)
49 6.1.2.4 Roof truss 30 days Wed 21/7/21 Tue 31/8/21 Roof truss
50 6.1.3 Architectural Work 111 days Wed 2/6/21 Wed 3/11/21 Architectural Work
51 6.1.3.1 Ground floor works 111 days Wed 2/6/21 Wed 3/11/21 Ground floor works
52 6.1.3.1.1 Brickwall External 14 days Wed 2/6/21 Mon 21/6/21 Brickwall External
53 6.1.3.1.2 Brickwall Internal 14 days Fri 11/6/21 Wed 30/6/21 Brickwall Internal
54 6.1.3.1.3 Ground floor plastering (external internal) 21 days Thu 1/7/21 Thu 29/7/21 Ground floor plastering (external internal)
55 6.1.3.1.4 GF Screeding 14 days Thu 29/7/21 Tue 17/8/21 GF Screeding
56 6.1.3.1.5 Ground floor tile finishes 14 days Wed 18/8/21 Mon 6/9/21 Ground floor tile finishes
57 6.1.3.1.6 Ground floor wall finishes 21 days Fri 27/8/21 Fri 24/9/21 Ground floor wall finishes
58 6.1.3.1.7 Ground floor ceiling finishes 21 days Wed 18/8/21 Wed 15/9/21 Ground floor ceiling finishes
59 6.1.3.1.8 Ground floor door frame 7 days Mon 27/9/21 Tue 5/10/21 Ground floor door frame
60 6.1.3.1.9 Ground floor window frame 7 days Mon 27/9/21 Tue 5/10/21 Ground floor window frame
61 6.1.3.1.10 Ground floor door installation 7 days Wed 6/10/21 Thu 14/10/21 Ground floor door installation
62 6.1.3.1.11 Ground floor window installation 7 days Wed 6/10/21 Thu 14/10/21 Ground floor window installation
63 6.1.3.1.12 Ground floor paint works (external & internal) 14 days Fri 15/10/21 Wed 3/11/21 Ground floor paint works (external & internal)
64 6.1.3.2 First floor works 111 days Wed 2/6/21 Wed 3/11/21 First floor works
65 6.1.3.2.1 First floor plastering work (external and 21 days Wed 2/6/21 Wed 30/6/21 First floor plastering work (external and internal)
internal)
66 6.1.3.2.2 First floor screeding 14 days Tue 22/6/21 Fri 9/7/21 First floor screeding
67 6.1.3.2.3 First floor hardener 14 days Mon 12/7/21 Thu 29/7/21 First floor hardener
68 6.1.3.2.4 First floor wall tiles 21 days Fri 30/7/21 Fri 27/8/21 First floor wall tiles
69 6.1.3.2.5 First floor ceiling finishes 21 days Mon 12/7/21 Mon 9/8/21 First floor ceiling finishes
70 6.1.3.2.6 First floor door frame 7 days Mon 30/8/21 Tue 7/9/21 First floor door frame
71 6.1.3.2.7 First floor window frame 7 days Wed 8/9/21 Thu 16/9/21 First floor window frame
72 6.1.3.2.8 First floor door installation 7 days Fri 17/9/21 Mon 27/9/21 First floor door installation
73 6.1.3.2.9 First floor window installation 7 days Tue 28/9/21 Wed 6/10/21 First floor window installation
74 6.1.3.2.10 First floor paint works (external & internal) 20 days Thu 7/10/21 Wed 3/11/21 First floor paint works (external & internal)
75 6.1.3.3 Roof floor works 63 days Wed 21/7/21 Fri 15/10/21 Roof floor works
76 6.1.3.3.1 Metal deck roof 21 days Wed 21/7/21 Wed 18/8/21 Metal deck roof

Task Project Summary Rolled Up Baseline Inactive Milestone Start-only

Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only

Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline

Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task

Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress

APPL ENGINEERING SERVICES SDN BHD Page 2


TENDER KALI KEDUA CADANGAN PEMBINAAN BANGUNAN KEKAL GIATMARA MUKAH, LOT 5907, BLOCK 48, MUKAH LAND DISTRICT, MUKAH SARAWAK
ID Task Name Duration Start Finish 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half
77 6.1.3.3.2 Metal gutter 14 days Thu 19/8/21 Tue 7/9/21 Metal gutter
78 6.1.3.3.3 RWDP 14 days Wed 8/9/21 Mon 27/9/21 RWDP
79 6.1.3.3.4 Signboard 14 days Tue 28/9/21 Fri 15/10/21 Signboard
80 6.2 Bengkel Pendawaian Elektrik 233 days Thu 19/11/20 Mon 11/10/21 Bengkel Pendawaian Elektrik
81 6.2.1 Structural work 100 days Thu 19/11/20 Wed 7/4/21 Structural work
82 6.2.1.1 Footing and stump 30 days Thu 19/11/20 Wed 30/12/20 Footing and stump
83 6.2.1.2 Ground floor beam 21 days Thu 31/12/20 Thu 28/1/21 Ground floor beam
84 6.2.1.3 Ground floor slab 14 days Wed 20/1/21 Mon 8/2/21 Ground floor slab
85 6.2.1.4 Ground floor column 21 days Tue 9/2/21 Tue 9/3/21 Ground floor column
86 6.2.1.5 Ground floor apron 21 days Wed 10/3/21 Wed 7/4/21 Ground floor apron
87 6.2.2 Roofing work 70 days Wed 10/3/21 Tue 15/6/21 Roofing work
88 6.2.2.1 Roof beam 21 days Wed 10/3/21 Wed 7/4/21 Roof beam
89 6.2.2.2 Roof slab 21 days Tue 30/3/21 Tue 27/4/21 Roof slab
90 6.2.2.3 RC Plinth (Water Tank) 14 days Wed 28/4/21 Mon 17/5/21 RC Plinth (Water Tank)
91 6.2.2.4 Roof Truss 21 days Tue 18/5/21 Tue 15/6/21 Roof Truss
92 6.2.3 Architectural Work 133 days Thu 8/4/21 Mon 11/10/21 Architectural Work
93 6.2.3.1 Brickwall External 14 days Thu 8/4/21 Tue 27/4/21 Brickwall External
94 6.2.3.2 Brickwal Internal 14 days Mon 19/4/21 Thu 6/5/21 Brickwal Internal
95 6.2.3.3 Plastering work (external and internal) 21 days Fri 7/5/21 Fri 4/6/21 Plastering work (external and internal)
96 6.2.3.4 Floor screeding 14 days Mon 7/6/21 Thu 24/6/21 Floor screeding
97 6.2.3.5 Ceiling finishes 21 days Fri 25/6/21 Fri 23/7/21 Ceiling finishes
98 6.2.3.6 Floor tiles 14 days Mon 26/7/21 Thu 12/8/21 Floor tiles
99 6.2.3.7 Floor harderner 21 days Fri 13/8/21 Fri 10/9/21 Floor harderner
100 6.2.3.8 Wall tiles 21 days Fri 13/8/21 Fri 10/9/21 Wall tiles
101 6.2.3.9 Painting work (external internal) 21 days Mon 13/9/21 Mon 11/10/21 Painting work (external internal)
102 6.3 Bengkel Teknologi Kimpalan & Fabrikasi 227 days Tue 8/12/20 Wed 20/10/21 Bengkel Teknologi Kimpalan & Fabrikasi
103 6.3.1 Structural Work 86 days Tue 8/12/20 Tue 6/4/21 Structural Work
104 6.3.1.1 Footing and stump 30 days Tue 8/12/20 Mon 18/1/21 Footing and stump
105 6.3.1.2 Ground floor beam 21 days Tue 19/1/21 Tue 16/2/21 Ground floor beam
106 6.3.1.3 Ground floor slab 21 days Mon 8/2/21 Mon 8/3/21 Ground floor slab
107 6.3.1.4 Ground floor column 21 days Tue 9/3/21 Tue 6/4/21 Ground floor column
108 6.3.2 Roofing work 70 days Wed 7/4/21 Tue 13/7/21 Roofing work
109 6.3.2.1 Roof beam 21 days Wed 7/4/21 Wed 5/5/21 Roof beam
110 6.3.2.2 Roof slab 21 days Tue 27/4/21 Tue 25/5/21 Roof slab
111 6.3.2.3 RC Plinth (Water Tank) 14 days Wed 26/5/21 Mon 14/6/21 RC Plinth (Water Tank)
112 6.3.2.4 Roof Truss 21 days Tue 15/6/21 Tue 13/7/21 Roof Truss
113 6.3.3 Architectural Work 141 days Wed 7/4/21 Wed 20/10/21 Architectural Work
114 6.3.3.1 Brickwall External 14 days Wed 7/4/21 Mon 26/4/21 Brickwall External
115 6.3.3.2 Brickwal Internal 14 days Fri 16/4/21 Wed 5/5/21 Brickwal Internal

Task Project Summary Rolled Up Baseline Inactive Milestone Start-only

Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only

Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline

Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task

Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress

APPL ENGINEERING SERVICES SDN BHD Page 3


TENDER KALI KEDUA CADANGAN PEMBINAAN BANGUNAN KEKAL GIATMARA MUKAH, LOT 5907, BLOCK 48, MUKAH LAND DISTRICT, MUKAH SARAWAK
ID Task Name Duration Start Finish 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half
116 6.3.3.3 Plastering work (external and internal) 21 days Thu 6/5/21 Thu 3/6/21 Plastering work (external and internal)
117 6.3.3.4 Floor screeding 21 days Fri 4/6/21 Fri 2/7/21 Floor screeding
118 6.3.3.5 Floor tiles 21 days Mon 5/7/21 Mon 2/8/21 Floor tiles
119 6.3.3.6 Floor harderner 15 days Tue 3/8/21 Mon 23/8/21 Floor harderner
120 6.3.3.7 Ceiling finishes 21 days Mon 5/7/21 Mon 2/8/21 Ceiling finishes
121 6.3.3.8 Wall tiles 21 days Tue 24/8/21 Tue 21/9/21 Wall tiles
122 6.3.3.9 Painting work (external internal) 21 days Wed 22/9/21 Wed 20/10/21 Painting work (external internal)
123 6.4 Transit Lelaki 236 days Wed 9/12/20 Wed 3/11/21 Transit Lelaki
124 6.4.1 Structural Work 104 days Wed 9/12/20 Mon 3/5/21 Structural Work
125 6.4.1.1 Footing and stump 27 days Wed 9/12/20 Thu 14/1/21 Footing and stump
126 6.4.1.2 Ground floor beam 21 days Fri 15/1/21 Fri 12/2/21 Ground floor beam
127 6.4.1.3 Ground floor slab 21 days Thu 4/2/21 Thu 4/3/21 Ground floor slab
128 6.4.1.4 Ground floor column 21 days Fri 5/3/21 Fri 2/4/21 Ground floor column
129 6.4.1.5 RC Apron 21 days Mon 5/4/21 Mon 3/5/21 RC Apron
130 6.4.2 Roofing work 56 days Tue 4/5/21 Tue 20/7/21 Roofing work
131 6.4.2.1 Roof beam 21 days Tue 4/5/21 Tue 1/6/21 Roof beam
132 6.4.2.2 Roof slab 21 days Mon 24/5/21 Mon 21/6/21 Roof slab
133 6.4.2.3 Roof Truss 21 days Tue 22/6/21 Tue 20/7/21 Roof Truss
134 6.4.3 Architectural Work 132 days Tue 4/5/21 Wed 3/11/21 Architectural Work
135 6.4.3.1 Ground floor 132 days Tue 4/5/21 Wed 3/11/21 Ground floor
136 6.4.3.1.1 Brickwall External 14 days Tue 4/5/21 Fri 21/5/21 Brickwall External
137 6.4.3.1.2 Brickwall Internal 14 days Thu 13/5/21 Tue 1/6/21 Brickwall Internal
138 6.4.3.1.3 Ground floor plastering (external internal) 20 days Wed 2/6/21 Tue 29/6/21 Ground floor plastering (external internal)
139 6.4.3.1.4 GF Screeding 14 days Wed 30/6/21 Mon 19/7/21 GF Screeding
140 6.4.3.1.5 Ground floor ceiling finishes 14 days Tue 20/7/21 Fri 6/8/21 Ground floor ceiling finishes
141 6.4.3.1.6 Ground floor tiles finishes 21 days Mon 9/8/21 Mon 6/9/21 Ground floor tiles finishes
142 6.4.3.1.7 Ground floor wall finishes 21 days Tue 7/9/21 Tue 5/10/21 Ground floor wall finishes
143 6.4.3.1.8 Ground floor door frame 7 days Mon 27/9/21 Tue 5/10/21 Ground floor door frame
144 6.4.3.1.9 Ground floor window frame 7 days Mon 27/9/21 Tue 5/10/21 Ground floor window frame
145 6.4.3.1.10 Ground floor door installation 7 days Wed 6/10/21 Thu 14/10/21 Ground floor door installation
146 6.4.3.1.11 Ground floor window installation 7 days Wed 6/10/21 Thu 14/10/21 Ground floor window installation
147 6.4.3.1.12 Ground floor paint works (external & internal) 14 days Fri 15/10/21 Wed 3/11/21 Ground floor paint works (external & internal)
148 6.4.3.2 Roofing work 49 days Wed 21/7/21 Mon 27/9/21 Roofing work
149 6.4.3.2.1 Metal deck roof 21 days Wed 21/7/21 Wed 18/8/21 Metal deck roof
150 6.4.3.2.2 Metal gutter 14 days Thu 19/8/21 Tue 7/9/21 Metal gutter
151 6.4.3.2.3 RWDP 14 days Wed 8/9/21 Mon 27/9/21 RWDP
152 6.5 Transit Perempuan 225 days Thu 24/12/20 Wed 3/11/21 Transit Perempuan
153 6.5.1 Structural Work 107 days Thu 24/12/20 Fri 21/5/21 Structural Work
154 6.5.1.1 Footing and stump 30 days Thu 24/12/20 Wed 3/2/21 Footing and stump

Task Project Summary Rolled Up Baseline Inactive Milestone Start-only

Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only

Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline

Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task

Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress

APPL ENGINEERING SERVICES SDN BHD Page 4


TENDER KALI KEDUA CADANGAN PEMBINAAN BANGUNAN KEKAL GIATMARA MUKAH, LOT 5907, BLOCK 48, MUKAH LAND DISTRICT, MUKAH SARAWAK
ID Task Name Duration Start Finish 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half
155 6.5.1.2 Ground floor beam 21 days Thu 4/2/21 Thu 4/3/21 Ground floor beam
156 6.5.1.3 Ground floor slab 21 days Wed 24/2/21 Wed 24/3/21 Ground floor slab
157 6.5.1.4 Ground floor column 21 days Thu 25/3/21 Thu 22/4/21 Ground floor column
158 6.5.1.5 RC Apron 21 days Fri 23/4/21 Fri 21/5/21 RC Apron
159 6.5.2 Roofing work 56 days Fri 23/4/21 Fri 9/7/21 Roofing work
160 6.5.2.1 Roof beam 21 days Fri 23/4/21 Fri 21/5/21 Roof beam
161 6.5.2.2 Roof slab 21 days Thu 13/5/21 Thu 10/6/21 Roof slab
162 6.5.2.3 Roof Truss 21 days Fri 11/6/21 Fri 9/7/21 Roof Truss
163 6.5.3 Architectural Work 125 days Thu 13/5/21 Wed 3/11/21 Architectural Work
164 6.5.3.1 Ground floor 125 days Thu 13/5/21 Wed 3/11/21 Ground floor
165 6.5.3.1.1 Brickwall External 14 days Thu 13/5/21 Tue 1/6/21 Brickwall External
166 6.5.3.1.2 Brickwall Internal 14 days Mon 24/5/21 Thu 10/6/21 Brickwall Internal
167 6.5.3.1.3 Ground floor plastering (external internal) 21 days Fri 11/6/21 Fri 9/7/21 Ground floor plastering (external internal)
168 6.5.3.1.4 GF Screeding 21 days Mon 12/7/21 Mon 9/8/21 GF Screeding
169 6.5.3.1.5 Ground floor ceiling finishes 21 days Tue 10/8/21 Tue 7/9/21 Ground floor ceiling finishes
170 6.5.3.1.6 Ground floor tiles finishes 21 days Mon 12/7/21 Mon 9/8/21 Ground floor tiles finishes
171 6.5.3.1.7 Ground floor wall finishes 21 days Tue 10/8/21 Tue 7/9/21 Ground floor wall finishes
172 6.5.3.1.8 Ground floor door frame 10 days Mon 30/8/21 Fri 10/9/21 Ground floor door frame
173 6.5.3.1.9 Ground floor window frame 10 days Wed 8/9/21 Tue 21/9/21 Ground floor window frame
174 6.5.3.1.10 Ground floor door installation 10 days Mon 13/9/21 Fri 24/9/21 Ground floor door installation
175 6.5.3.1.11 Ground floor window installation 10 days Wed 22/9/21 Tue 5/10/21 Ground floor window installation
176 6.5.3.1.12 Ground floor paint works (external & internal)21 days Wed 6/10/21 Wed 3/11/21 Ground floor paint works (external & internal)
177 6.5.3.2 Roofing work 49 days Mon 12/7/21 Thu 16/9/21 Roofing work
178 6.5.3.2.1 Metal deck roof 21 days Mon 12/7/21 Mon 9/8/21 Metal deck roof
179 6.5.3.2.2 Metal gutter 14 days Tue 10/8/21 Fri 27/8/21 Metal gutter
180 6.5.3.2.3 RWDP 14 days Mon 30/8/21 Thu 16/9/21 RWDP
181 6.6 Pusat Sampah 49 days Tue 22/12/20 Fri 26/2/21 Pusat Sampah
182 6.6.1 Structural Work 49 days Tue 22/12/20 Fri 26/2/21 Structural Work
183 6.6.1.1 Footing and stump 21 days Tue 22/12/20 Tue 19/1/21 Footing and stump
184 6.6.1.2 Ground floor beam 14 days Wed 20/1/21 Mon 8/2/21 Ground floor beam
185 6.6.1.3 Ground floor slab 14 days Tue 9/2/21 Fri 26/2/21 Ground floor slab
186 7 External Work 123 days Mon 17/5/21 Wed 3/11/21 External Work
187 7.1 Road and Carpark 37 days Wed 18/8/21 Thu 7/10/21 Road and Carpark
188 7.2 Manholes 21 days Mon 24/5/21 Mon 21/6/21 Manholes
189 7.3 Polysept Septic Tank 21 days Fri 11/6/21 Fri 9/7/21 Polysept Septic Tank
190 7.4 300mm wide conc. Drain 21 days Mon 5/7/21 Mon 2/8/21 300mm wide conc. Drain
191 7.5 300mm box culvert 21 days Wed 14/7/21 Wed 11/8/21 300mm box culvert
192 7.6 450mm box culvert 21 days Fri 23/7/21 Fri 20/8/21 450mm box culvert
193 7.7 RC Road Crossing - Main Access 21 days Mon 17/5/21 Mon 14/6/21 RC Road Crossing - Main Access

Task Project Summary Rolled Up Baseline Inactive Milestone Start-only

Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only

Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline

Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task

Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress

APPL ENGINEERING SERVICES SDN BHD Page 5


TENDER KALI KEDUA CADANGAN PEMBINAAN BANGUNAN KEKAL GIATMARA MUKAH, LOT 5907, BLOCK 48, MUKAH LAND DISTRICT, MUKAH SARAWAK
ID Task Name Duration Start Finish 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half
194 7.8 RC Road Crossing - Sesco Sub 21 days Wed 26/5/21 Wed 23/6/21 RC Road Crossing - Sesco Sub
195 7.9 Concrete footpaths 21 days Wed 29/9/21 Wed 27/10/21 Concrete footpaths
196 7.10 160mm dia. PN10 HDPE Pipe 21 days Fri 10/9/21 Fri 8/10/21 160mm dia. PN10 HDPE Pipe
197 7.11 150mm dia. DI pipe 10 days Fri 24/9/21 Thu 7/10/21 150mm dia. DI pipe
198 7.12 Pillar hydrant 10 days Fri 8/10/21 Thu 21/10/21 Pillar hydrant
199 7.13 Brickwall Fencing 10 days Fri 8/10/21 Thu 21/10/21 Brickwall Fencing
200 7.14 Earth bund 9 days Fri 22/10/21 Wed 3/11/21 Earth bund
201 8 Mechanical and Electrical Services 220 days Thu 31/12/20 Wed 3/11/21 Mechanical and Electrical Services
202 8.1 Mechanical Services 217 days Thu 31/12/20 Fri 29/10/21 Mechanical Services
203 8.1.1 Blok Pendtabiran 194 days Thu 31/12/20 Tue 28/9/21 Blok Pendtabiran
204 8.1.1.1 Fire Protection System 30 days Wed 18/8/21 Tue 28/9/21 Fire Protection System
205 8.1.1.2 Air conditioning & mechanical ventilation system 30 days Wed 18/8/21 Tue 28/9/21 Air conditioning & mechanical ventilation system
206 8.1.1.3 Internal cold water supply system 70 days Thu 31/12/20 Wed 7/4/21 Internal cold water supply system
207 8.1.1.4 Internal sanitary plumbing 60 days Thu 8/4/21 Wed 30/6/21 Internal sanitary plumbing
208 8.1.2 Blok Pendawaian Elektrik 203 days Wed 20/1/21 Fri 29/10/21 Blok Pendawaian Elektrik
209 8.1.2.1 Fire Protection System 14 days Tue 12/10/21 Fri 29/10/21 Fire Protection System
210 8.1.2.2 Air conditioning & mechanical ventilation system 19 days Fri 25/6/21 Wed 21/7/21 Air conditioning & mechanical ventilation system
211 8.1.2.3 Internal cold water supply system 21 days Wed 20/1/21 Wed 17/2/21 Internal cold water supply system
212 8.1.2.4 Internal Sanitary plumbing 21 days Thu 18/2/21 Thu 18/3/21 Internal Sanitary plumbing
213 8.1.3 Blok Teknologi Kimpalan & Fabrikasi 190 days Mon 8/2/21 Fri 29/10/21 Blok Teknologi Kimpalan & Fabrikasi
214 8.1.3.1 Fire Protection System 7 days Thu 21/10/21 Fri 29/10/21 Fire Protection System
215 8.1.3.2 Air conditioning & mechanical ventilation system 21 days Mon 5/7/21 Mon 2/8/21 Air conditioning & mechanical ventilation system
216 8.1.3.3 Internal cold water supply system 21 days Mon 8/2/21 Mon 8/3/21 Internal cold water supply system
217 8.1.3.4 Internal Sanitary plumbing 21 days Tue 9/3/21 Tue 6/4/21 Internal Sanitary plumbing
218 8.1.4 Transit Lelaki 182 days Thu 4/2/21 Fri 15/10/21 Transit Lelaki
219 8.1.4.1 Fire Protection System 14 days Tue 28/9/21 Fri 15/10/21 Fire Protection System
220 8.1.4.2 Internal cold water supply system 21 days Thu 4/2/21 Thu 4/3/21 Internal cold water supply system
221 8.1.4.3 Internal sanitary plumbing 21 days Fri 5/3/21 Fri 2/4/21 Internal sanitary plumbing
222 8.1.5 Transit Perempuan 161 days Wed 24/2/21 Wed 6/10/21 Transit Perempuan
223 8.1.5.1 Fire Protection System 14 days Fri 17/9/21 Wed 6/10/21 Fire Protection System
224 8.1.5.2 Internal cold water supply system 21 days Wed 24/2/21 Wed 24/3/21 Internal cold water supply system
225 8.1.5.3 Internal Sanitary plumbing 21 days Thu 25/3/21 Thu 22/4/21 Internal Sanitary plumbing
226 8.1.6 Rumah Sampah 28 days Tue 9/2/21 Thu 18/3/21 Rumah Sampah
227 8.1.6.1 Internal cold water supply system 14 days Tue 9/2/21 Fri 26/2/21 Internal cold water supply system
228 8.1.6.2 Internal sanitary plumbing 14 days Mon 1/3/21 Thu 18/3/21 Internal sanitary plumbing
229 8.2 Electrical Services 60 days Fri 25/6/21 Thu 16/9/21 Electrical Services
230 8.2.1 Blok Pentadbiran 49 days Mon 12/7/21 Thu 16/9/21 Blok Pentadbiran
231 8.2.1.1 Internal Lighting and Power Installation System 14 days Wed 18/8/21 Mon 6/9/21 Internal Lighting and Power Installation System (Ground F
(Ground Floor)
Task Project Summary Rolled Up Baseline Inactive Milestone Start-only

Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only

Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline

Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task

Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress

APPL ENGINEERING SERVICES SDN BHD Page 6


TENDER KALI KEDUA CADANGAN PEMBINAAN BANGUNAN KEKAL GIATMARA MUKAH, LOT 5907, BLOCK 48, MUKAH LAND DISTRICT, MUKAH SARAWAK
ID Task Name Duration Start Finish 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half
232 8.2.1.2 Internal Lighting and Power Installation System 14 days Mon 12/7/21 Thu 29/7/21 Internal Lighting and Power Installation System (First Floor)
(First Floor)
233 8.2.1.3 Lightning protection and earthing system 14 days Fri 30/7/21 Wed 18/8/21 Lightning protection and earthing system
234 8.2.1.4 Internal telecommunication system 21 days Thu 19/8/21 Thu 16/9/21 Internal telecommunication system
235 8.2.2 Blok Pendawaian Elektrik 14 days Fri 25/6/21 Wed 14/7/21 Blok Pendawaian Elektrik
236 8.2.2.1 Internal Lighting and Power Installation System 14 days Fri 25/6/21 Wed 14/7/21 Internal Lighting and Power Installation System
237 8.2.3 Blok Teknologi Kimpalan dan Fabrikasi 14 days Mon 5/7/21 Thu 22/7/21 Blok Teknologi Kimpalan dan Fabrikasi
238 8.2.3.1 Internal Lighting and Power Installation System 14 days Mon 5/7/21 Thu 22/7/21 Internal Lighting and Power Installation System
239 8.2.4 Transit Lelaki 14 days Tue 20/7/21 Fri 6/8/21 Transit Lelaki
240 8.2.4.1 Internal Lighting and Power Installation System 14 days Tue 20/7/21 Fri 6/8/21 Internal Lighting and Power Installation System
241 8.2.5 Transit Perempuan 14 days Tue 10/8/21 Fri 27/8/21 Transit Perempuan
242 8.2.5.1 Internal lighting and Power Installation System 14 days Tue 10/8/21 Fri 27/8/21 Internal lighting and Power Installation System
243 8.2.6 External/Compound Lighting System 14 days Mon 30/8/21 Thu 16/9/21 External/Compound Lighting System
244 8.2.6.1 External/Compound Lighting System 14 days Mon 30/8/21 Thu 16/9/21 External/Compound Lighting System
245 8.3 Testing and Comissioning 3 days Mon 1/11/21 Wed 3/11/21 Testing and Comissioning
246 8.3.1 Testing and Comissioning 3 days Mon 1/11/21 Wed 3/11/21 Testing and Comissioning
247 9 Project Handover 1 day Thu 4/11/21 Thu 4/11/21 Project Handover
248 9.1 Site Touch Up Works 1 day Thu 4/11/21 Thu 4/11/21 Site Touch Up Works
249 9.2 Project Handover 0 days Thu 4/11/21 Thu 4/11/21 4/11 4/11

Task Project Summary Rolled Up Baseline Inactive Milestone Start-only

Task Progress Group By Summary Rolled Up Baseline Milestone Inactive Summary Finish-only

Project: GIATMARA MUKAH Split Rolled Up Task Rolled Up Progress Manual Task Deadline
Date: Fri 9/10/20 Milestone Rolled Up Critical Task External Tasks Duration-only Baseline

Baseline Milestone Rolled Up Milestone External Milestone Manual Summary Rollup Critical Task

Summary Baseline Summary Inactive Task Manual Summary Critical Task Progress

APPL ENGINEERING SERVICES SDN BHD Page 7