CT Site Test Report Current Transformer: Pre-Commissioning Checklist

1. The document is a test report for current transformers at a 220/11kV substation. 2. It provides details of the pre-commissioning checks performed on the CTs including installation, connections, cabling, and nameplate information. 3. Test results are reported for insulation resistance, polarity, winding resistance, magnetizing current, and ratio accuracy which all meet specifications.

Uploaded by

Naveed
Copyright
© © All Rights Reserved
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
591 views

CT Site Test Report Current Transformer: Pre-Commissioning Checklist

1. The document is a test report for current transformers at a 220/11kV substation. 2. It provides details of the pre-commissioning checks performed on the CTs including installation, connections, cabling, and nameplate information. 3. Test results are reported for insulation resistance, polarity, winding resistance, magnetizing current, and ratio accuracy which all meet specifications.

Uploaded by

Naveed
Copyright
© © All Rights Reserved
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 6

Doc. No.

CT SITE TEST REPORT RNS /S / 01 –CT


Equipment Date : 3/-10/2018
CURRENT TRANSFORMER
R Ph Sl. No.:2114525 Y Ph Sl. No.:2114524 B Ph Sl. No.:2114526

Location & Designation: 203 BAY Page 1 of 10


Customer: Project: Job order No.
RNS INFRASTRUCTURE 220 / 11KV S/S RNSIL /UBP/2010/066 DT-
30/04/2010 & RNSIL /UBP/2010/
DT-30/09/2010

Pre-Commissioning Checklist:

1. Check the erection of equipment is carried out as per the approved drawings

2. Check there is no damage to any part of CT assembly and CT is cleaned


And free from dust/dirt etc.

3. Check the primary terminals P1& P2 are connected to the bus as shown in the drawing

4. Check the position of the secondary terminal box is as per the approved drawing

5. Check for oil marks/oil leakage, oil level, any damage to


The primary/secondary terminals

6. Check the earth connections of the equipment are completed as per the drawing

7. Terminal Box:
a. Secondary connections are completed properly as per the drawing
And terminals are tightened
b. The tan delta terminal is connected properly to Earth
c. The cable tags, ferrules for all cores are provided
d. Cables are properly dressed and clamped
e. Unused holes are sealed properly

8. CT Junction Box/ marshalling box:


a. Check the cabling from CT to JB are completed
b. Check external cabling from JB to relay panel is completed
c. Unused secondary cores, if any are shorted and earthed in the JB/ TB
d. The star point has been formed and earthed at one end only
e. Links and connections are tightened properly
f. Check the aux. CT (if supplied) connections are made as per drawing & ratio
Mentioned on the name plate of CT

9. Check Nitrogen Pressure at SCHRADER Valve (If applicable)

Tested by Witnessed – Client


Testing Agency
Name NAVEEN KUMAR ABB INDIA LIMITED KPTCL/KNNL
Signature
Date
Doc. No.
CT SITE TEST REPORT RNS /S / 01 –CT
Equipment Date : 3/-10/2018
CURRENT TRANSFORMER
R Ph Sl. No.:2114525 Y Ph Sl. No.:2114524 B Ph Sl. No.:2114526

Location & Designation: 203 BAY Page 2 of 10


Customer: Project: Job order No.
RNS INFRASTRUCTURE 220 / 11KV S/S RNSIL /UBP/2010/066 DT-
30/04/2010 & RNSIL /UBP/2010/
DT-30/09/2010

Name Plate Details:

Make ABB
Type IMB 245
Highest System Voltage 245 KV
Rated Insulation 245/460/1050
Rated Primary Current 800 A

Core Details:

Burden Knee point Winding


Core ref Ratio CL Imag in mA Purpose
(VA) voltage Resistance

Core – 1 800/1 5 0.2 _ _ _ METERING

Core – 2 800/1 5 0.2 _ _ _ METERING

Tested by Witnessed – Client


Testing Agency
Name NAVEEN KUMAR ABB INDIA LIMITED KPTCL/KNNL
Signature
Date
Doc. No.
CT SITE TEST REPORT RNS /S / 01 –CT
Equipment Date : 3/-10/2018
CURRENT TRANSFORMER
R Ph Sl. No.:2114525 Y Ph Sl. No.:2114524 B Ph Sl. No.:2114526

Location & Designation: 203 BAY Page 3 of 10


Customer: Project: Job order No.
RNS INFRASTRUCTURE 220 / 11KV S/S RNSIL /UBP/2010/066 DT-
30/04/2010 & RNSIL /UBP/2010/
DT-30/09/2010

1. Insulation Resistance Test: (values in Giga ohms)

Circuit ref. Megger used R Y B

Primary – Earth 5 kV 41 18 36

Primary – Core 1 5 kV >1 >1 >1

Primary – Core 2 5 kV >1 >1 >1

Core 1 – Earth 500 V >1 >1 >1

Core 2 – Earth 500 V >1 >1 >1

Core 1 – Core 2 500 V >1 >1 >1

2. Polarity Test:

Core R Y B
Core – 1 OK OK OK
Core – 2 OK OK OK

3. Winding Resistance Test: (values in Ohms)

Resistance in Ohms
Core Sec. Terminals
R Y B
1S1 – 1S2
Core – 1 0.6 0.6 0.6

2S1 – 2S2
Core – 2 0.6 0.6 0.6

Tested by Witnessed – Client


Testing Agency
Name NAVEEN KUMAR ABB INDIA LIMITED KPTCL/KNNL
Signature
Date
Doc. No.
CT SITE TEST REPORT RNS /S / 01 –CT
Equipment Date : 3/-10/2018
CURRENT TRANSFORMER
R Ph Sl. No.:2114525 Y Ph Sl. No.:2114524 B Ph Sl. No.:2114526

Location & Designation: 203 BAY Page 4 of 10


Customer: Project: Job order No.
RNS INFRASTRUCTURE 220 / 11KV S/S RNSIL /UBP/2010/066 DT-
30/04/2010 & RNSIL /UBP/2010/
DT-30/09/2010

4. Magnetizing Current test: (for All class )

Rated Knee Point Voltage (Vk): V

Magnetizing Current in Ma
Core Applied Volts
R Y B
1S1-1S5 500 5 4.6 5.1
2S1-2S5 500 5.6 4.6 4.9
3S1-3S5 48 232 2.4A [email protected]
4S1-4S2 500 4.5 5.1 4.6
5S1-5S2 500 4.9 4.1 4.5

5. Ratio Test:

Injected current Secondary PA error Ratio found %error


current

Core1 Core2 Core1 Core2 Core1 Core2 Core1 Core2 Core1 Core2

199.97 199.97 0.9999 1.00005 -0.01* -0.03* 200:1.0001 200:1.0002 0.01% 0.01%

199.96 199.94 1.00006 0.9999 -0.04* -0.00* 200:1.0003 200:1.0002 0.03% 0.02%

199.95 199.94 1.00004 0.9999 -0.03* -0.01* 200:1.0003 200:1.0003 0.03% 0.02%

Tested by Witnessed – Client


Testing Agency
Name NAVEEN KUMAR ABB INDIA LIMITED KPTCL/KNNL
Signature
Date
Doc. No.
CT SITE TEST REPORT RNS /S / 01 –CT
Equipment Date : 3/-10/2018
CURRENT TRANSFORMER
R Ph Sl. No.:2114525 Y Ph Sl. No.:2114524 B Ph Sl. No.:2114526

Location & Designation: 203 BAY Page 5 of 10


Customer: Project: Job order No.
RNS INFRASTRUCTURE 220 / 11KV S/S RNSIL /UBP/2010/066 DT-
30/04/2010 & RNSIL /UBP/2010/
DT-30/09/2010

6. Capacitance and Tan-Delta Measurement

MODE R Ph Y Ph B Ph

VOLTAGE(KV)
CURRENT(mA)
Capacitance in pF
UST MODE Tan Delta in %
POWER
FREQUENCY
VDF%

MODE R Ph Y Ph B Ph

VOLTAGE(KV)
CURRENT(mA)
Capacitance in pF
GST GUARD
Tan Delta in %
MODE
POWER
FREQUENCY
VDF%

Tested by Witnessed – Client


Testing Agency
Name NAVEEN KUMAR ABB INDIA LIMITED KPTCL/KNNL
Signature
Date
Doc. No.
CT SITE TEST REPORT RNS /S / 01 –CT
Equipment Date : 3/-10/2018
CURRENT TRANSFORMER
R Ph Sl. No.:2114525 Y Ph Sl. No.:2114524 B Ph Sl. No.:2114526

Location & Designation: 203 BAY Page 6 of 10


Customer: Project: Job order No.
RNS INFRASTRUCTURE 220 / 11KV S/S RNSIL /UBP/2010/066 DT-
30/04/2010 & RNSIL /UBP/2010/
DT-30/09/2010

MODE R Ph Y Ph B Ph

VOLTAGE(KV)
CURRENT(mA)
Capacitance in pF
GST MODE Tan Delta in %
POWER
FREQUENCY
VDF%

Tested by Witnessed – Client


Testing Agency
Name NAVEEN KUMAR ABB INDIA LIMITED KPTCL/KNNL
Signature
Date