Daily Progress Report 16.10.2020

The daily progress report from October 16, 2020 provides an update on work for supplying, fabricating, and laying a clear water transmission main from Harohalli to Vajarahalli. Key activities on that date included 3 edges being cut, 15 meters of SAW welding, and 37 total manpower from contractor SPML working on the pipeline project. No civil works structures or progress are listed for the report date.

Uploaded by

Jagadeesan S M
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views

Daily Progress Report 16.10.2020

The daily progress report from October 16, 2020 provides an update on work for supplying, fabricating, and laying a clear water transmission main from Harohalli to Vajarahalli. Key activities on that date included 3 edges being cut, 15 meters of SAW welding, and 37 total manpower from contractor SPML working on the pipeline project. No civil works structures or progress are listed for the report date.

Uploaded by

Jagadeesan S M
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Harohalli

DAILY PROGRESS REPORT DATE:16.10.2020


MS PIPELINE WORKS

Sl No Description Previous Day Present Day


1 Edge cutting (Nos) 30.0 3

2 Rolling (Nos) 21.0 0

3 Fit up (Meters) 30.0 0

4 SAW Welding (Meters) 0.0 15

5 Radiography test (Meters) 0.0 0

6 Hydraulic test (Meters) 0.0 0

7 Epoxy coating (Meters) 0.0 0

8 Wrapping of welded mesh (Meters) 0.0 0

9 Guniting (Meters) 0.0 0

CIVIL WORKS

NAME OF THE STRUCTURE WORK PROGRESS STATUS

MANPOWER

Name of Contractor Supervisor Fitter Welder Cutter Grinders

1
SPML 6 3 3 7 4
2

3
ransmission main from Harohalli to Vajarahalli.
DATE:16.10.2020

Present Day Cummulative Quantity


3 33

0 21

0 30

15 15

0 0

0 0

0 0

0 0

0 0

NAME OF THE CONTRACTOR REMARKS

Riggers Operators Helpers Total

5 3 6 37